SAI DHAM BUILDING NO. 03
by SHREE SAI DEVELOPERS · Boisar, Palghar
Possession date of SAI DHAM BUILDING NO. 03: 31 December 2024, moved from 28 August 2022 (28 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000017331. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about SAI DHAM BUILDING NO. 03?
How the possession date of SAI DHAM BUILDING NO. 03 has moved
28 August 2022
Completion date given when the project was registered
28 August 2023
Extended at the builder's request (MahaRERA application EXT99000012413)
Reason the builder gave MahaRERA: “Labour issue”
31 December 2024
Extended at the builder's request (MahaRERA application EXT99000017517)
Reason the builder gave MahaRERA: “wORK COMPLETED JUST OC PENDING”
Source: SAI DHAM BUILDING NO. 03’s extension records on MahaRERA (P99000017331), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI DHAM BUILDING NO. 03
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000017331
- Status
- Lapsed (registration period ended)
- Builder
- SHREE SAI DEVELOPERS
- Location
- Boisar, Palghar · 401501
- Project type
- Residential / Group Housing
- Registered on
- 7 Aug 2018
- Completion date at registration
- August 2022
- Latest completion date
- December 2024
- Delay so far
- 28 months
- Homes
- 70
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 28
Construction progress of SAI DHAM BUILDING NO. 03, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI DHAM BUILDING NO 3 | 100% | 100% | 95% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI DHAM BUILDING NO. 03 every month.
SAI DHAM BUILDING NO. 03: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI DHAM BUILDING NO 3 (2 floors)
- Land: 2,500 sq m (about 0.6 acres) · sanctioned built-up 2,419 sq m · recreational space 250 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAI DHAM BUILDING NO. 03 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI DHAM BUILDING NO. 03: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI DHAM BUILDING NO. 03
What is the possession date of SAI DHAM BUILDING NO. 03?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI DHAM BUILDING NO. 03 in Boisar, Palghar is 31 December 2024 — 28 months later than 28 August 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SAI DHAM BUILDING NO. 03?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI DHAM BUILDING NO. 03's builder has filed on MahaRERA, the official one, is 31 December 2024, already 28 months later than the 28 August 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI DHAM BUILDING NO. 03 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI DHAM BUILDING NO. 03's builder applied to MahaRERA to extend the completion date 2 times: to 28 August 2023, giving the reason "Labour issue"; to 31 December 2024, giving the reason "wORK COMPLETED JUST OC PENDING".
What is the RERA number of SAI DHAM BUILDING NO. 03?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI DHAM BUILDING NO. 03 in Boisar, Palghar is P99000017331.
Is SAI DHAM BUILDING NO. 03 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI DHAM BUILDING NO. 03 is registered as P99000017331 and its status is "Lapsed (registration period ended)".
What is the construction status of SAI DHAM BUILDING NO. 03?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI DHAM BUILDING NO. 03's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI DHAM BUILDING NO 3 is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does SAI DHAM BUILDING NO. 03 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SAI DHAM BUILDING NO. 03 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI DHAM BUILDING NO. 03 is registered on MahaRERA as P99000017331, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 28 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI DHAM BUILDING NO. 03's possession date changes?
The latest dates are on SAI DHAM BUILDING NO. 03's MahaRERA page (P99000017331). GharKundli's Kundli Watch sends a free WhatsApp update on SAI DHAM BUILDING NO. 03 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI DHAM BUILDING NO. 03 have?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI DHAM BUILDING NO. 03 has one building filed: SAI DHAM BUILDING NO 3 with 2 floors.
How big is the land of SAI DHAM BUILDING NO. 03?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI DHAM BUILDING NO. 03 stands on 2,500 sq m of land (about 0.6 acres), with 2,419 sq m of sanctioned built-up area and 250 sq m of recreational open space.
Where can I read reviews of SAI DHAM BUILDING NO. 03?
Google Maps has reviews of SAI DHAM BUILDING NO. 03 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI DHAM BUILDING NO. 03?
SAI DHAM BUILDING NO. 03 by SHREE SAI DEVELOPERS is in Boisar, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000017331, per GharKundli's check of MahaRERA records.
How many homes are in SAI DHAM BUILDING NO. 03?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI DHAM BUILDING NO. 03 has 70 homes in 1 tower registered on MahaRERA.
When was SAI DHAM BUILDING NO. 03 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI DHAM BUILDING NO. 03 was registered on MahaRERA on 7 August 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI DHAM BUILDING NO. 03?
No court cases are listed for SAI DHAM BUILDING NO. 03 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAI DHAM BUILDING NO. 03?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE SAI DEVELOPERS, which has 28 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAI DHAM BUILDING NO. 03
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401501
- Luxury Empire Township Phase I
- OM SAI COMPLEX
- MAHAVIR SAPPHIRE
- YOSH EMPIRE
- VALUE HOMES
- Shree Aadinath Park
- SHREE GALAXY
- Sai Shraddha Apartment
Other projects by SHREE SAI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.