PARAMOUNT ENCLAVE BLDG NO 3A 3B

by SUN INFRA · Palghar West, Palghar

Possession date of PARAMOUNT ENCLAVE BLDG NO 3A 3B: 30 April 2029, moved from 30 March 2023 (69 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000017504, and currently active. Its completion date has moved from March 2023 to April 2029: 69 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about PARAMOUNT ENCLAVE BLDG NO 3A 3B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PARAMOUNT ENCLAVE BLDG NO 3A 3B has moved

  1. 30 March 2023

    Completion date given when the project was registered

  2. 29 March 2024

    Extended at the builder's request (MahaRERA application EXT99000015216)

    Reason the builder gave MahaRERA: “Our 1 wing is completely ready. Another wing is also at finishing stage. We have slightly delay in completing due COVID effect. Due to COVID our working were adversly affected for some time.”
  3. 31 December 2028

    Extended at the builder's request (MahaRERA application EXT99000019374)

    Reason the builder gave MahaRERA:
    “We need some more extension time to complete all the aspects of completion of Building work, we have attached architect certificate, only few things have been left for completion of buildings and all the apartments have been not sold out ti…” Read the full reason“We need some more extension time to complete all the aspects of completion of Building work, we have attached architect certificate, only few things have been left for completion of buildings and all the apartments have been not sold out till yet. and after few months we will apply for Occupancy Certificate as a our project township is very big following with various buildings some of the buildings have applied for occupancy certificate. After all aspects of completion of construction work we will accordingly upload Form 4 and Occupancy Certificate, please grant us a extension period till 3…”
  4. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PARAMOUNT ENCLAVE BLDG NO 3A 3B’s extension records on MahaRERA (P99000017504), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PARAMOUNT ENCLAVE BLDG NO 3A 3B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000017504
Status
Registered and active
Builder
SUN INFRA
Location
Palghar West, Palghar · 401404
Project type
Residential / Group Housing
Registered on
23 Aug 2018
Completion date at registration
March 2023
Latest completion date
April 2029
Delay so far
69 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
188
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of PARAMOUNT ENCLAVE BLDG NO 3A 3B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PARAMOUNT ENCLAVE BLDG NO 3A 3B100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARAMOUNT ENCLAVE BLDG NO 3A 3B every month.

PARAMOUNT ENCLAVE BLDG NO 3A 3B: buildings, flats and land, as filed on MahaRERA

  • Buildings: PARAMOUNT ENCLAVE BLDG NO 3A 3B (9 floors)
  • Land: 5,295 sq m (about 1.3 acres) · sanctioned built-up 5,714 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PARAMOUNT ENCLAVE BLDG NO 3A 3B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PARAMOUNT ENCLAVE BLDG NO 3A 3B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PARAMOUNT ENCLAVE BLDG NO 3A 3B

What is the possession date of PARAMOUNT ENCLAVE BLDG NO 3A 3B?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PARAMOUNT ENCLAVE BLDG NO 3A 3B in Palghar West, Palghar is 30 April 2029 — 69 months later than 30 March 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PARAMOUNT ENCLAVE BLDG NO 3A 3B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PARAMOUNT ENCLAVE BLDG NO 3A 3B's builder has filed on MahaRERA, the official one, is 30 April 2029, already 69 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PARAMOUNT ENCLAVE BLDG NO 3A 3B extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE BLDG NO 3A 3B's builder applied to MahaRERA to extend the completion date 2 times: to 29 March 2024, giving the reason "Our 1 wing is completely ready. Another wing is also at finishing stage. We have slightly delay in completing due COVID effect. Due to COVID our working were adversly affected for some time."; to 31 December 2028, giving the reason "We need some more extension time to complete all the aspects of completion of Building work, we have attached architect certificate, only few things have been left for completion of buildings and all the apartments have been not sold out till yet. and after few months we will apply for Occupancy Certificate as a our project township is very big following with various buildings some of the buildings have applied for occupancy certificate. After all aspects of completion of construction work we will accordingly upload Form 4 and Occupancy Certificate, please grant us a extension period till 3…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of PARAMOUNT ENCLAVE BLDG NO 3A 3B?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PARAMOUNT ENCLAVE BLDG NO 3A 3B in Palghar West, Palghar is P99000017504.

Is PARAMOUNT ENCLAVE BLDG NO 3A 3B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE BLDG NO 3A 3B is registered as P99000017504 and its status is "Registered and active".

What is the construction status of PARAMOUNT ENCLAVE BLDG NO 3A 3B?

According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE BLDG NO 3A 3B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PARAMOUNT ENCLAVE BLDG NO 3A 3B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does PARAMOUNT ENCLAVE BLDG NO 3A 3B have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PARAMOUNT ENCLAVE BLDG NO 3A 3B safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE BLDG NO 3A 3B is registered on MahaRERA as P99000017504, its completion date has moved 69 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PARAMOUNT ENCLAVE BLDG NO 3A 3B's possession date changes?

The latest dates are on PARAMOUNT ENCLAVE BLDG NO 3A 3B's MahaRERA page (P99000017504). GharKundli's Kundli Watch sends a free WhatsApp update on PARAMOUNT ENCLAVE BLDG NO 3A 3B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PARAMOUNT ENCLAVE BLDG NO 3A 3B have?

According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE BLDG NO 3A 3B has one building filed: PARAMOUNT ENCLAVE BLDG NO 3A 3B with 9 floors.

How big is the land of PARAMOUNT ENCLAVE BLDG NO 3A 3B?

According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE BLDG NO 3A 3B stands on 5,295 sq m of land (about 1.3 acres), with 5,714 sq m of sanctioned built-up area.

Where can I read reviews of PARAMOUNT ENCLAVE BLDG NO 3A 3B?

Google Maps has reviews of PARAMOUNT ENCLAVE BLDG NO 3A 3B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PARAMOUNT ENCLAVE BLDG NO 3A 3B?

PARAMOUNT ENCLAVE BLDG NO 3A 3B by SUN INFRA is in Palghar West, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000017504, per GharKundli's check of MahaRERA records.

How many homes are in PARAMOUNT ENCLAVE BLDG NO 3A 3B?

According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE BLDG NO 3A 3B has 188 homes in 1 tower registered on MahaRERA.

When was PARAMOUNT ENCLAVE BLDG NO 3A 3B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE BLDG NO 3A 3B was registered on MahaRERA on 23 August 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on PARAMOUNT ENCLAVE BLDG NO 3A 3B?

No court cases are listed for PARAMOUNT ENCLAVE BLDG NO 3A 3B on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of PARAMOUNT ENCLAVE BLDG NO 3A 3B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUN INFRA.

All projects with possession due in 2029 in Palghar →

Other projects in pincode 401404

All 419 projects in Palghar (401404) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.