Skip to content
GharKundli

Maruti Kalpataru

by Shree Maruti Buildcon · Chakan, Pune 410501Also near MedankarwadiRegistered on MahaRERA as “Kalpataru”

What’s in the report? →

Possession: Maruti Kalpataru (MahaRERA P52100012215) is marked completed on MahaRERA. It has 88 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100012215. Status: Completed.

Source: MahaRERA website — records for P52100012215, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Maruti Kalpataru?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Maruti Kalpataru has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 June 2020

    Extended at the builder's request (MahaRERA application EXT52100004003)

    Reason the builder gave MahaRERA:
    “We have registered our project named “KALPATARU” on MAHARERA website. As we have mentioned completion date 31/12/2019 while registering project. We have develop 7th floor building and We have obtained Commencement Certificate on dated 29/07…” Read the full reason“We have registered our project named “KALPATARU” on MAHARERA website. As we have mentioned completion date 31/12/2019 while registering project. We have develop 7th floor building and We have obtained Commencement Certificate on dated 29/07/2017 for 4th Floor Building, Then We have Submit file for Road Handover to PMRDA on dated 29/11/2017 , After we have submitted file for 7th floor building on dated 04/04/2018 to PMRDA. Then we have get latter for Road Handover on dated 19/07/2018. While this process PMRDA give latter for Opinion on dated 08/10/2018 to PWD No objection for Road Winding. A…”
  3. 30 December 2020

    Revised completion date on MahaRERA

Source: Maruti Kalpataru’s extension records on MahaRERA (P52100012215), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Maruti Kalpataru

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100012215
Status
Completed
Builder
Shree Maruti Buildcon
Location
Chakan, Pune · 410501
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
December 2019
Latest completion date
December 2020
Delay so far
12 months
Homes
88
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Maruti Kalpataru, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Wing100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Maruti Kalpataru every 1–2 months.

Maruti Kalpataru: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Success Infra (a group of 5 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 6 finished, 4 within the promised date and 2 needed more time (typically 12 months); 1 still being built, none past the promised date yet; 1 lapsed. 5 complaints on MahaRERA across 1 project.

Read Google reviews of Maruti Kalpataru →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Maruti Kalpataru: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Maruti Kalpataru

What is the possession date of Maruti Kalpataru?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Maruti Kalpataru in Chakan, Pune is 30 December 2020 — 12 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Maruti Kalpataru?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Maruti Kalpataru's builder has filed on MahaRERA, the official one, is 30 December 2020, already 12 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Maruti Kalpataru extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru's builder applied to MahaRERA to extend the completion date once: to 30 June 2020, giving the reason "We have registered our project named “KALPATARU” on MAHARERA website. As we have mentioned completion date 31/12/2019 while registering project. We have develop 7th floor building and We have obtained Commencement Certificate on dated 29/07/2017 for 4th Floor Building, Then We have Submit file for Road Handover to PMRDA on dated 29/11/2017 , After we have submitted file for 7th floor building on dated 04/04/2018 to PMRDA. Then we have get latter for Road Handover on dated 19/07/2018. While this process PMRDA give latter for Opinion on dated 08/10/2018 to PWD No objection for Road Winding. A…".

What is the RERA number of Maruti Kalpataru?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Maruti Kalpataru in Chakan, Pune is P52100012215.

Is Maruti Kalpataru registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru is registered as P52100012215 and its status is "Completed".

What is the current construction status of Maruti Kalpataru? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru's status on MahaRERA is "Completed". As filed by the builder, slab work on A Wing is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Maruti Kalpataru have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Maruti Kalpataru safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru is registered on MahaRERA as P52100012215, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Maruti Kalpataru?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Maruti Kalpataru?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Maruti Kalpataru: gharkundli.com/tools/property-cost-calculator

Has Maruti Kalpataru received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Maruti Kalpataru completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru is marked completed on MahaRERA, and the completion date filed there is 30 December 2020. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Maruti Kalpataru uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Maruti Kalpataru was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Maruti Kalpataru's possession date changes?

The latest dates are on Maruti Kalpataru's MahaRERA page (P52100012215). GharKundli's Kundli Watch sends a free WhatsApp update on Maruti Kalpataru every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Maruti Kalpataru have?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru has one building filed: A Wing with 7 floors.

How big is the land of Maruti Kalpataru?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru stands on 2,423 sq m of land (about 0.6 acres), with 2,906 sq m of sanctioned built-up area.

What is the track record of Maruti Kalpataru's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Success Infra (a group of 5 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 6 finished, 4 within the promised date and 2 needed more time (typically 12 months); 1 still being built, none past the promised date yet; 1 lapsed. 5 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Maruti Kalpataru?

Google Maps has reviews of Maruti Kalpataru written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Maruti Kalpataru?

Maruti Kalpataru by Shree Maruti Buildcon is in Chakan, Pune, pincode 410501 (near Medankarwadi), Maharashtra, and is registered on MahaRERA as P52100012215, per GharKundli's check of MahaRERA records. Its boundaries filed there include Chakan shikrapur Road, Villege Road. Its land is filed as Gat No 107. GharKundli lists all 174 MahaRERA projects in Chakan (410501).

How many flats are in Maruti Kalpataru?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru has 88 homes in 1 tower registered on MahaRERA.

When was Maruti Kalpataru registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Maruti Kalpataru was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Does Maruti Kalpataru have any legal issues or court cases?

No court cases are listed for Maruti Kalpataru on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Maruti Kalpataru?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shree Maruti Buildcon, which has 1 other project registered on MahaRERA.

Other projects in Chakan (410501)

All 174 projects in Chakan (410501) →

Other projects by Shree Maruti Buildcon

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.