Skip to content
GharKundli

Sai Vihar

by ATTHARVA DEVELOPERS · Lavale, Pune

Possession date of Sai Vihar: 30 December 2024, moved from 30 December 2022 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100008162. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about Sai Vihar?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sai Vihar has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT52100013167)

    Reason the builder gave MahaRERA:
    “Our project Sai Vihar (RERA No. P52100008162) got delayed due to stoppage of work in lockdown of COVID-19 pandemic, shortage of material and labour supply and price inflation and also due to correction in sanctioned layout plan. So we reque…” Read the full reason“Our project Sai Vihar (RERA No. P52100008162) got delayed due to stoppage of work in lockdown of COVID-19 pandemic, shortage of material and labour supply and price inflation and also due to correction in sanctioned layout plan. So we request you to grant us relief in the form of extension of due date to complete the project by one year.”
  3. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT52100018218)

    Reason the builder gave MahaRERA:
    “Dear Sir, Our project got delayed due stoppage of work in lockdown of COVID-19 pandemic and also due shortage of material supply and price inflation. So we request you to grant us relief in the form extension of due date to complete the pro…” Read the full reason“Dear Sir, Our project got delayed due stoppage of work in lockdown of COVID-19 pandemic and also due shortage of material supply and price inflation. So we request you to grant us relief in the form extension of due date to complete the project by one year. Humbly request you to extend the completion date to 30/12/2024.”

Source: Sai Vihar’s extension records on MahaRERA (P52100008162), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sai Vihar

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100008162
Status
Lapsed (registration period ended)
Builder
ATTHARVA DEVELOPERS
Location
Lavale, Pune · 412115
Project type
Residential / Group Housing
Registered on
18 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2024
Delay so far
24 months
Homes
24
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Sai Vihar, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A100%100%100%0%
B50%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Vihar every month.

Sai Vihar: buildings, flats and land, as filed on MahaRERA

  • Buildings: A (3 floors) · B (3 floors)
  • Land: 1,700 sq m (about 0.4 acres) · sanctioned built-up 948 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sai Vihar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Vihar: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sai Vihar

What is the possession date of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sai Vihar in Lavale, Pune is 30 December 2024 — 24 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Sai Vihar?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Vihar's builder has filed on MahaRERA, the official one, is 30 December 2024, already 24 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sai Vihar extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Vihar's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2023, giving the reason "Our project Sai Vihar (RERA No. P52100008162) got delayed due to stoppage of work in lockdown of COVID-19 pandemic, shortage of material and labour supply and price inflation and also due to correction in sanctioned layout plan. So we request you to grant us relief in the form of extension of due date to complete the project by one year."; to 30 December 2024, giving the reason "Dear Sir, Our project got delayed due stoppage of work in lockdown of COVID-19 pandemic and also due shortage of material supply and price inflation. So we request you to grant us relief in the form extension of due date to complete the project by one year. Humbly request you to extend the completion date to 30/12/2024.".

What is the RERA number of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sai Vihar in Lavale, Pune is P52100008162.

Is Sai Vihar registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Vihar is registered as P52100008162 and its status is "Lapsed (registration period ended)".

What is the construction status of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Vihar's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Sai Vihar have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Sai Vihar safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Vihar is registered on MahaRERA as P52100008162, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sai Vihar's possession date changes?

The latest dates are on Sai Vihar's MahaRERA page (P52100008162). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Vihar every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Vihar have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Vihar has 2 buildings filed: A with 3 floors; B with 3 floors.

How big is the land of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Vihar stands on 1,700 sq m of land (about 0.4 acres), with 948 sq m of sanctioned built-up area.

Where can I read reviews of Sai Vihar?

Google Maps has reviews of Sai Vihar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sai Vihar?

Sai Vihar by ATTHARVA DEVELOPERS is in Lavale, Pune (pincode 412115), Maharashtra, and is registered on MahaRERA as P52100008162, per GharKundli's check of MahaRERA records.

How many homes are in Sai Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Vihar has 24 homes in 2 towers registered on MahaRERA.

When was Sai Vihar registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Vihar was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Sai Vihar?

No court cases are listed for Sai Vihar on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sai Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ATTHARVA DEVELOPERS.

Other projects in Lavale

All 197 projects in Bhugaon (412115) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.