R K PARADISE
by PANKAJ KASHINATH PATIL · Pimple Nilakh, Pune
Possession date of R K PARADISE: 20 December 2023, moved from 31 December 2018 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100009381. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2023) has passed.
What do you want to know about R K PARADISE?
How the possession date of R K PARADISE has moved
31 December 2018
Completion date given when the project was registered
30 August 2020
Extended at the builder's request (MahaRERA application EXT52100002122)
Reason the builder gave MahaRERA: “We are awaiting completion certificate for the project from concerned authority.”
30 August 2020
Extended at the builder's request (MahaRERA application EXT52100005469)
Reason the builder gave MahaRERA: “THE PROJECT IS 100 % COMPLETE . WE R IN PROCESS OF PROJECT COMPLETION . SO PLEASE ALLOW FOR EXTENTION, THANK YOU .”
20 December 2023
Extended at the builder's request (MahaRERA application EXT52100012842)
Reason the builder gave MahaRERA: “building work is done, the completion process is going on. I request you to please give me the project extension. thank you”
Source: R K PARADISE’s extension records on MahaRERA (P52100009381), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on R K PARADISE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100009381
- Status
- Lapsed (registration period ended)
- Builder
- PANKAJ KASHINATH PATIL
- Location
- Pimple Nilakh, Pune · 412101
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2023
- Delay so far
- 60 months
- Homes
- 18
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of R K PARADISE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| R K PARADISE | 100% | 100% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on R K PARADISE every month.
R K PARADISE: buildings, flats and land, as filed on MahaRERA
- Buildings: R K PARADISE (7 floors)
- Land: 428 sq m (about 0.1 acres) · sanctioned built-up 847 sq m
The builder’s record and reviews
Pankaj Kashinath Patil has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 90 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of R K PARADISE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
R K PARADISE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about R K PARADISE
What is the possession date of R K PARADISE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for R K PARADISE in Pimple Nilakh, Pune is 20 December 2023 — 60 months later than 31 December 2018, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for R K PARADISE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date R K PARADISE's builder has filed on MahaRERA, the official one, is 20 December 2023, already 60 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of R K PARADISE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), R K PARADISE's builder applied to MahaRERA to extend the completion date 3 times: to 30 August 2020, giving the reason "We are awaiting completion certificate for the project from concerned authority."; to 30 August 2020, giving the reason "THE PROJECT IS 100 % COMPLETE . WE R IN PROCESS OF PROJECT COMPLETION . SO PLEASE ALLOW FOR EXTENTION, THANK YOU ."; to 20 December 2023, giving the reason "building work is done, the completion process is going on. I request you to please give me the project extension. thank you".
What is the RERA number of R K PARADISE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of R K PARADISE in Pimple Nilakh, Pune is P52100009381.
Is R K PARADISE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), R K PARADISE is registered as P52100009381 and its status is "Lapsed (registration period ended)".
What is the construction status of R K PARADISE?
According to GharKundli's check of MahaRERA records (updated November 2026), R K PARADISE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on R K PARADISE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does R K PARADISE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is R K PARADISE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), R K PARADISE is registered on MahaRERA as P52100009381, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if R K PARADISE's possession date changes?
The latest dates are on R K PARADISE's MahaRERA page (P52100009381). GharKundli's Kundli Watch sends a free WhatsApp update on R K PARADISE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does R K PARADISE have?
According to GharKundli's check of MahaRERA records (updated November 2026), R K PARADISE has one building filed: R K PARADISE with 7 floors.
How big is the land of R K PARADISE?
According to GharKundli's check of MahaRERA records (updated November 2026), R K PARADISE stands on 428 sq m of land (about 0.1 acres), with 847 sq m of sanctioned built-up area.
What is the track record of R K PARADISE's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Pankaj Kashinath Patil has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 90 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of R K PARADISE?
Google Maps has reviews of R K PARADISE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is R K PARADISE?
R K PARADISE by PANKAJ KASHINATH PATIL is in Pimple Nilakh, Pune (pincode 412101), Maharashtra, and is registered on MahaRERA as P52100009381, per GharKundli's check of MahaRERA records.
How many homes are in R K PARADISE?
According to GharKundli's check of MahaRERA records (updated November 2026), R K PARADISE has 18 homes in 1 tower registered on MahaRERA.
When was R K PARADISE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), R K PARADISE was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on R K PARADISE?
No court cases are listed for R K PARADISE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of R K PARADISE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PANKAJ KASHINATH PATIL, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of R K PARADISE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pimple Nilakh
- R K PRIDE
- SAHIL HEIGHTS A1
- Green Alley Phase - II
- SHAVIRA RESIDENCY
- MARIGOLD CALENDULA
- SWAYAMBHU PRATHAM
- Green Alley Phase - I
- MIDORI TOWER PHASE 2
Other projects by PANKAJ KASHINATH PATIL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.