Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail
by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED (Rustomjee) · Virar, Palghar
Possession date of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail: 31 December 2025, moved from 30 September 2023 (27 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000020216. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
How the possession date of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail has moved
30 September 2023
Completion date given when the project was registered
29 September 2024
Extended at the builder's request (MahaRERA application EXT99000011503)
Reason the builder gave MahaRERA:
“The promoter has received full approval of building plans and has completed construction upto plinth level; however, Promoter is awaiting further commencement Certificate to commence construction as more particularly mentioned in applicatio…” Read the full reason
“The promoter has received full approval of building plans and has completed construction upto plinth level; however, Promoter is awaiting further commencement Certificate to commence construction as more particularly mentioned in application.”31 December 2025
Extended at the builder's request (MahaRERA application EXT99000019068)
Reason the builder gave MahaRERA:
“1. The Real Estate Project comprises of three Buildings i.e. Wing I, Wing J and Retail Building. The super structure of Wing I and Wing J of the said Real Estate Project is completed and is presently at the stage of completion of block work…” Read the full reason
“1. The Real Estate Project comprises of three Buildings i.e. Wing I, Wing J and Retail Building. The super structure of Wing I and Wing J of the said Real Estate Project is completed and is presently at the stage of completion of block work together with internal finishing works. However, the construction of the Retail Building of said Real Estate Project has still not progressed. 2. There are several instances that have caused hurdles in the said Real Estate Project’s completion and yet Wing I and Wing J of the Real Estate Project have been substantially completed. We state that Covid 19 p…”
Source: Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail’s extension records on MahaRERA (P99000020216), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000020216
- Status
- Lapsed (registration period ended)
- Builder
- KEYSTONE INFRASTRUCTURE PRIVATE LIMITED
- Location
- Virar, Palghar · 401303
- Project type
- Others
- Registered on
- 29 Mar 2019
- Completion date at registration
- September 2023
- Latest completion date
- December 2025
- Delay so far
- 27 months
- Homes
- 238
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing I | 100% | 100% | 90% | 50% |
| Wing J | 100% | 100% | 40% | 50% |
| Retail | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail every month.
Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing I (18 floors) · Wing J (18 floors) · Retail (4 floors)
- Land: 1,319 sq m (about 0.3 acres) · sanctioned built-up 10,383 sq m
The builder’s record and reviews
Keystone Infrastructure (a group of 2 linked companies) has 10 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 3 lapsed. 3 complaints on MahaRERA across 3 projects.
Read Google reviews of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail
What is the possession date of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail in Virar, Palghar is 31 December 2025 — 27 months later than 30 September 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail's builder has filed on MahaRERA, the official one, is 31 December 2025, already 27 months later than the 30 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail's builder applied to MahaRERA to extend the completion date 2 times: to 29 September 2024, giving the reason "The promoter has received full approval of building plans and has completed construction upto plinth level; however, Promoter is awaiting further commencement Certificate to commence construction as more particularly mentioned in application."; to 31 December 2025, giving the reason "1. The Real Estate Project comprises of three Buildings i.e. Wing I, Wing J and Retail Building. The super structure of Wing I and Wing J of the said Real Estate Project is completed and is presently at the stage of completion of block work together with internal finishing works. However, the construction of the Retail Building of said Real Estate Project has still not progressed. 2. There are several instances that have caused hurdles in the said Real Estate Project’s completion and yet Wing I and Wing J of the Real Estate Project have been substantially completed. We state that Covid 19 p…".
What is the RERA number of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail in Virar, Palghar is P99000020216.
Is Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail is registered as P99000020216 and its status is "Lapsed (registration period ended)".
What is the construction status of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail is registered on MahaRERA as P99000020216, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 27 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail's possession date changes?
The latest dates are on Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail's MahaRERA page (P99000020216). GharKundli's Kundli Watch sends a free WhatsApp update on Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail have?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail has 3 buildings filed: Wing I with 18 floors; Wing J with 18 floors; Retail with 4 floors.
How big is the land of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail stands on 1,319 sq m of land (about 0.3 acres), with 10,383 sq m of sanctioned built-up area.
What is the track record of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Keystone Infrastructure (a group of 2 linked companies) has 10 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 3 lapsed. 3 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
Google Maps has reviews of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED (Rustomjee) is in Virar, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000020216, per GharKundli's check of MahaRERA records.
How many homes are in Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail has 238 homes in 3 towers registered on MahaRERA.
When was Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail was registered on MahaRERA on 29 March 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
1 court case is listed for Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KEYSTONE INFRASTRUCTURE PRIVATE LIMITED, the company Rustomjee files this project under, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401303
- VIVA CITY - A5
- Bhakti Greens
- S M TOWER
- VIMALNATH Building no-2
- UNIQUE APARTMENT
- VALENCIA CHS
- Belle Vue 9
- SUPER HOMEZ-HARMONY PHASE III
Other projects by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED
- Rustomjee Virar Avenue L1-L2 and L4 Wing H and Retail
- Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building
- Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building
- Rustomjee Virar Avenue L1-L2 and L4 Wing K
- Rustomjee Virar Avenue L1-L2 and L4 Wing G
- Rustomjee Virar Avenue L1-L2 And L4 Wing C and D
- RUSTOMJEE VIRAR AVENUE D1 WING A AND WING B AND RETAIL BUILDING
- RUSTOMJEE VIRAR AVENUE D1 WING C AND WING D
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.