Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building
by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED (Rustomjee) · Virar, Palghar
Possession date of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building: 31 December 2025, moved from 28 February 2023 (34 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000020234. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
How the possession date of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building has moved
28 February 2023
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT99000017984)
Reason the builder gave MahaRERA:
“The Real Estate Project comprises of three Buildings i.e. Wing E, Wing F and Retail Building. The Wing E and Wing F of the said Real Estate Project have received Occupation Certificate dated 6.12.2022 and possession of the Flats have been h…” Read the full reason
“The Real Estate Project comprises of three Buildings i.e. Wing E, Wing F and Retail Building. The Wing E and Wing F of the said Real Estate Project have received Occupation Certificate dated 6.12.2022 and possession of the Flats have been handed over to the allottees. However, the Retail Building of the said Real Estate Project has not received the occupation certificate since, the construction of the same is in progress. There are several instances that have caused hurdles in the said Real Estate Project’s completion and yet Wing E and Wing F have been completed with Occupation Certificate…”
Source: Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building’s extension records on MahaRERA (P99000020234), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000020234
- Status
- Lapsed (registration period ended)
- Builder
- KEYSTONE INFRASTRUCTURE PRIVATE LIMITED
- Location
- Virar, Palghar · 401303
- Project type
- Others
- Registered on
- 29 Mar 2019
- Completion date at registration
- February 2023
- Latest completion date
- December 2025
- Delay so far
- 34 months
- Homes
- 239
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING E | 100% | 100% | 100% | 100% |
| WING F | 100% | 100% | 100% | 100% |
| Retail Building | 100% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building every month.
Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building: buildings, flats and land, as filed on MahaRERA
- Buildings: WING E (18 floors) · WING F (18 floors) · Retail Building (5 floors)
- Land: 1,502 sq m (about 0.4 acres) · sanctioned built-up 11,143 sq m
The builder’s record and reviews
Keystone Infrastructure (a group of 2 linked companies) has 10 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 3 lapsed. 3 complaints on MahaRERA across 3 projects.
Read Google reviews of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building
What is the possession date of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building in Virar, Palghar is 31 December 2025 — 34 months later than 28 February 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building's builder has filed on MahaRERA, the official one, is 31 December 2025, already 34 months later than the 28 February 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "The Real Estate Project comprises of three Buildings i.e. Wing E, Wing F and Retail Building. The Wing E and Wing F of the said Real Estate Project have received Occupation Certificate dated 6.12.2022 and possession of the Flats have been handed over to the allottees. However, the Retail Building of the said Real Estate Project has not received the occupation certificate since, the construction of the same is in progress. There are several instances that have caused hurdles in the said Real Estate Project’s completion and yet Wing E and Wing F have been completed with Occupation Certificate…".
What is the RERA number of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building in Virar, Palghar is P99000020234.
Is Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building is registered as P99000020234 and its status is "Lapsed (registration period ended)".
What is the construction status of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
According to GharKundli's check of MahaRERA records (updated November 2026), Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building is registered on MahaRERA as P99000020234, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 34 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building's possession date changes?
The latest dates are on Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building's MahaRERA page (P99000020234). GharKundli's Kundli Watch sends a free WhatsApp update on Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building have?
According to GharKundli's check of MahaRERA records (updated November 2026), Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building has 3 buildings filed: WING E with 18 floors; WING F with 18 floors; Retail Building with 5 floors.
How big is the land of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
According to GharKundli's check of MahaRERA records (updated November 2026), Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building stands on 1,502 sq m of land (about 0.4 acres), with 11,143 sq m of sanctioned built-up area.
What is the track record of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Keystone Infrastructure (a group of 2 linked companies) has 10 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 3 lapsed. 3 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
Google Maps has reviews of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED (Rustomjee) is in Virar, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000020234, per GharKundli's check of MahaRERA records.
How many homes are in Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
According to GharKundli's check of MahaRERA records (updated November 2026), Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building has 239 homes in 3 towers registered on MahaRERA.
When was Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building was registered on MahaRERA on 29 March 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
2 court cases are listed for Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KEYSTONE INFRASTRUCTURE PRIVATE LIMITED, the company Rustomjee files this project under, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Rustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail Building
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401303
- VIVA CITY - A3
- VIVA CITY - A5
- Bhakti Greens
- S M TOWER
- VIMALNATH Building no-2
- VALENCIA CHS
- Belle Vue 9
- SUPER HOMEZ-HARMONY PHASE III
Other projects by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED
- Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail
- Rustomjee Virar Avenue L1-L2 and L4 Wing H and Retail
- Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail Building
- Rustomjee Virar Avenue L1-L2 and L4 Wing K
- Rustomjee Virar Avenue L1-L2 and L4 Wing G
- Rustomjee Virar Avenue L1-L2 And L4 Wing C and D
- RUSTOMJEE VIRAR AVENUE D1 WING A AND WING B AND RETAIL BUILDING
- RUSTOMJEE VIRAR AVENUE D1 WING C AND WING D
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.