by FUTURISTIC HOMES · Pawar Wasti, Pune 411033Also near Tathawade, Chinchwad, Jeevan Nagar

What’s in the report? →

Possession date of The Spectrum (MahaRERA P52100022934): 30 December 2023, and it has already passed. It has 66 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100022934. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100022934, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about The Spectrum?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on The Spectrum

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100022934
Status
Lapsed (registration period ended)
Builder
FUTURISTIC HOMES
Location
Pawar Wasti, Pune · 411033
Project type
Residential / Group Housing
Registered on
5 Nov 2019
Completion date at registration
December 2023
Latest completion date
December 2023
Homes
66
Sold or booked
0%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of The Spectrum, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B BUILDING50%0%0%0%
C BUILDING50%0%0%0%
A BUILDING50%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Spectrum every 1–2 months.

The Spectrum: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Futuristic Homes (a group of 5 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 3 finished, all within the promised date; 6 still being built, 1 past the promised date (typically 34 months late); 2 lapsed. No complaints on MahaRERA.

Read Google reviews of The Spectrum →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Spectrum: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The Spectrum

What is the possession date of The Spectrum?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Spectrum in Pawar Wasti, Pune is 30 December 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for The Spectrum?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Spectrum's builder has filed on MahaRERA, the official one, is 30 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of The Spectrum?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Spectrum in Pawar Wasti, Pune is P52100022934.

Is The Spectrum registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), The Spectrum is registered as P52100022934 and its status is "Lapsed (registration period ended)".

What is the current construction status of The Spectrum? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), The Spectrum's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does The Spectrum have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is The Spectrum safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), The Spectrum is registered on MahaRERA as P52100022934, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The Spectrum?

The Spectrum isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The Spectrum?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in The Spectrum: gharkundli.com/tools/property-cost-calculator

Has The Spectrum received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), The Spectrum isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for The Spectrum?

According to GharKundli's check of MahaRERA records (updated November 2026), The Spectrum's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has The Spectrum uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for The Spectrum was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The Spectrum's possession date changes?

The latest dates are on The Spectrum's MahaRERA page (P52100022934). GharKundli's Kundli Watch sends a free WhatsApp update on The Spectrum every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Spectrum have?

According to GharKundli's check of MahaRERA records (updated November 2026), The Spectrum has 3 buildings filed: B BUILDING with 12 floors; C BUILDING with 12 floors; A BUILDING with 12 floors.

How big is the land of The Spectrum?

According to GharKundli's check of MahaRERA records (updated November 2026), The Spectrum stands on 3,200 sq m of land (about 0.8 acres), with 2,544 sq m of sanctioned built-up area and 320 sq m of recreational open space.

What is the track record of The Spectrum's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Futuristic Homes (a group of 5 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 3 finished, all within the promised date; 6 still being built, 1 past the promised date (typically 34 months late); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of The Spectrum?

Google Maps has reviews of The Spectrum written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The Spectrum?

The Spectrum by FUTURISTIC HOMES is in Pawar Wasti, Pune, pincode 411033 (near Tathawade, Chinchwad, Jeevan Nagar), Maharashtra, and is registered on MahaRERA as P52100022934, per GharKundli's check of MahaRERA records. Its land is filed as 78/2/3P. GharKundli lists all 613 MahaRERA projects in Chinchwadgaon (411033).

How many flats are in The Spectrum, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), The Spectrum has 66 homes in 3 towers registered on MahaRERA, and 0% of them are sold or booked.

When was The Spectrum registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), The Spectrum was registered on MahaRERA on 5 November 2019. GharKundli did not find a title report on the land on file there.

Does The Spectrum have any legal issues or court cases?

No court cases are listed for The Spectrum on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of The Spectrum?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is FUTURISTIC HOMES, which has 4 other projects registered on MahaRERA.

Other projects in Mulshi

All 613 projects in Chinchwadgaon (411033) →

Other projects by FUTURISTIC HOMES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.