PRIDE RESIDENCY
by M V CORP · Dixit Colony, Palghar
Possession: PRIDE RESIDENCY is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000019050. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about PRIDE RESIDENCY?
How the possession date of PRIDE RESIDENCY has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT99000013392)
Reason the builder gave MahaRERA: “We have applied for Occupation Certificate with the competent authority on 31st January,2022 which is under process. A copy of the acknowledgement received is enclosed along with the application.”
Source: PRIDE RESIDENCY’s extension records on MahaRERA (P99000019050), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PRIDE RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000019050
- Status
- Completed
- Builder
- M V CORP
- Location
- Dixit Colony, Palghar · 401102
- Project type
- Residential / Group Housing
- Registered on
- 28 Dec 2018
- Completion date at registration
- December 2022
- Latest completion date
- December 2023
- Delay so far
- 12 months
- Homes
- 25
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of PRIDE RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PRIDE RESIDENCY | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRIDE RESIDENCY every month.
PRIDE RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: PRIDE RESIDENCY (6 floors)
- Land: 1,580 sq m (about 0.4 acres) · sanctioned built-up 1,649 sq m
The builder’s record and reviews
M V Corp has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of PRIDE RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PRIDE RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PRIDE RESIDENCY
What is the possession date of PRIDE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PRIDE RESIDENCY in Dixit Colony, Palghar is 30 December 2023 — 12 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for PRIDE RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PRIDE RESIDENCY's builder has filed on MahaRERA, the official one, is 30 December 2023, already 12 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PRIDE RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), PRIDE RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 30 December 2023, giving the reason "We have applied for Occupation Certificate with the competent authority on 31st January,2022 which is under process. A copy of the acknowledgement received is enclosed along with the application.".
What is the RERA number of PRIDE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PRIDE RESIDENCY in Dixit Colony, Palghar is P99000019050.
Is PRIDE RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PRIDE RESIDENCY is registered as P99000019050 and its status is "Completed".
What is the construction status of PRIDE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), PRIDE RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on PRIDE RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does PRIDE RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is PRIDE RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PRIDE RESIDENCY is registered on MahaRERA as P99000019050, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PRIDE RESIDENCY's possession date changes?
The latest dates are on PRIDE RESIDENCY's MahaRERA page (P99000019050). GharKundli's Kundli Watch sends a free WhatsApp update on PRIDE RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PRIDE RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), PRIDE RESIDENCY has one building filed: PRIDE RESIDENCY with 6 floors.
How big is the land of PRIDE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), PRIDE RESIDENCY stands on 1,580 sq m of land (about 0.4 acres), with 1,649 sq m of sanctioned built-up area.
What is the track record of PRIDE RESIDENCY's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), M V Corp has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PRIDE RESIDENCY?
Google Maps has reviews of PRIDE RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PRIDE RESIDENCY?
PRIDE RESIDENCY by M V CORP is in Dixit Colony, Palghar (pincode 401102), Maharashtra, and is registered on MahaRERA as P99000019050, per GharKundli's check of MahaRERA records.
How many homes are in PRIDE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), PRIDE RESIDENCY has 25 homes in 1 tower registered on MahaRERA.
When was PRIDE RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PRIDE RESIDENCY was registered on MahaRERA on 28 December 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on PRIDE RESIDENCY?
No court cases are listed for PRIDE RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of PRIDE RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M V CORP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PRIDE RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Palghar
- Sunshine Complex
- Elite Residency
- Rubicon Shinde Heritage
- V SQUARE ARCADE
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Other projects by M V CORP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.