Skip to content
GharKundli

Silver Park - B Wing

by HAKKE AND KAD DEVELOPERS · Uruli Devachi, PuneAlso near Phursungi

Possession date of Silver Park - B Wing: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100025181, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Silver Park - B Wing?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Silver Park - B Wing has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Silver Park - B Wing’s extension records on MahaRERA (P52100025181), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Silver Park - B Wing

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100025181
Status
Registered and active
Builder
HAKKE AND KAD DEVELOPERS
Location
Uruli Devachi, Pune · 412308
Project type
Residential / Group Housing
Registered on
20 Mar 2020
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
179
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Silver Park - B Wing, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING B100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Silver Park - B Wing every month.

Silver Park - B Wing: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING B (17 floors)
  • Land: 3,874 sq m (about 1.0 acres) · sanctioned built-up 3,168 sq m · recreational space 775 sq m

The builder’s record and reviews

Hakke Buildcon (a group of 3 linked companies) has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 3 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Silver Park - B Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Silver Park - B Wing: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Silver Park - B Wing

What is the possession date of Silver Park - B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Silver Park - B Wing in Uruli Devachi, Pune is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Silver Park - B Wing?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Silver Park - B Wing's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Silver Park - B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Silver Park - B Wing in Uruli Devachi, Pune is P52100025181.

Is Silver Park - B Wing registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Silver Park - B Wing is registered as P52100025181 and its status is "Registered and active".

What is the construction status of Silver Park - B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Silver Park - B Wing's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WING B is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Silver Park - B Wing have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Silver Park - B Wing safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Silver Park - B Wing is registered on MahaRERA as P52100025181, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Silver Park - B Wing's possession date changes?

The latest dates are on Silver Park - B Wing's MahaRERA page (P52100025181). GharKundli's Kundli Watch sends a free WhatsApp update on Silver Park - B Wing every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Silver Park - B Wing have?

According to GharKundli's check of MahaRERA records (updated November 2026), Silver Park - B Wing has one building filed: WING B with 17 floors.

How big is the land of Silver Park - B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Silver Park - B Wing stands on 3,874 sq m of land (about 1.0 acres), with 3,168 sq m of sanctioned built-up area and 775 sq m of recreational open space.

What is the track record of Silver Park - B Wing's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Hakke Buildcon (a group of 3 linked companies) has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Silver Park - B Wing?

Google Maps has reviews of Silver Park - B Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Silver Park - B Wing?

Silver Park - B Wing by HAKKE AND KAD DEVELOPERS is in Uruli Devachi, Pune (pincode 412308), near Phursungi, Maharashtra, and is registered on MahaRERA as P52100025181, per GharKundli's check of MahaRERA records.

How many homes are in Silver Park - B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Silver Park - B Wing has 179 homes in 1 tower registered on MahaRERA.

When was Silver Park - B Wing registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Silver Park - B Wing was registered on MahaRERA on 20 March 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Silver Park - B Wing?

No court cases are listed for Silver Park - B Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Silver Park - B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HAKKE AND KAD DEVELOPERS.

All projects with possession due in 2027 in Pune →

Other projects in pincode 412308

All 69 projects in Fursungi (412308) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.