SHREE SWAMI SAMARTH RESIDENCY

by ANIL VASANTRAO CHAVAN · Kiwale, PuneAlso near Dehu Road Cantt

Possession date of SHREE SWAMI SAMARTH RESIDENCY: 31 March 2024, moved from 15 February 2023 (13 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100025793. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2024) has passed.

What do you want to know about SHREE SWAMI SAMARTH RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREE SWAMI SAMARTH RESIDENCY has moved

  1. 15 February 2023

    Completion date given when the project was registered

  2. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52100015184)

    Reason the builder gave MahaRERA: “As prescribed under circular no. 07/2019 dated 8 Feb 2019 the consent of 51% of the allotees is enclosed herewith”

Source: SHREE SWAMI SAMARTH RESIDENCY’s extension records on MahaRERA (P52100025793), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREE SWAMI SAMARTH RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100025793
Status
Lapsed (registration period ended)
Builder
ANIL VASANTRAO CHAVAN
Location
Kiwale, Pune · 412101
Project type
Residential / Group Housing
Registered on
16 Jul 2020
Completion date at registration
February 2023
Latest completion date
March 2024
Delay so far
13 months
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHREE SWAMI SAMARTH RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE SWAMI SAMARTH RESIDENCY100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE SWAMI SAMARTH RESIDENCY every month.

SHREE SWAMI SAMARTH RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE SWAMI SAMARTH RESIDENCY (5 floors)
  • Land: 1,295 sq m (about 0.3 acres) · sanctioned built-up 2 sq m · recreational space 844 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHREE SWAMI SAMARTH RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREE SWAMI SAMARTH RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREE SWAMI SAMARTH RESIDENCY

What is the possession date of SHREE SWAMI SAMARTH RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREE SWAMI SAMARTH RESIDENCY in Kiwale, Pune is 31 March 2024 — 13 months later than 15 February 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SHREE SWAMI SAMARTH RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE SWAMI SAMARTH RESIDENCY's builder has filed on MahaRERA, the official one, is 31 March 2024, already 13 months later than the 15 February 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREE SWAMI SAMARTH RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SWAMI SAMARTH RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 March 2024, giving the reason "As prescribed under circular no. 07/2019 dated 8 Feb 2019 the consent of 51% of the allotees is enclosed herewith".

What is the RERA number of SHREE SWAMI SAMARTH RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREE SWAMI SAMARTH RESIDENCY in Kiwale, Pune is P52100025793.

Is SHREE SWAMI SAMARTH RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SWAMI SAMARTH RESIDENCY is registered as P52100025793 and its status is "Lapsed (registration period ended)".

What is the construction status of SHREE SWAMI SAMARTH RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SWAMI SAMARTH RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHREE SWAMI SAMARTH RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHREE SWAMI SAMARTH RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHREE SWAMI SAMARTH RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SWAMI SAMARTH RESIDENCY is registered on MahaRERA as P52100025793, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 13 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREE SWAMI SAMARTH RESIDENCY's possession date changes?

The latest dates are on SHREE SWAMI SAMARTH RESIDENCY's MahaRERA page (P52100025793). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE SWAMI SAMARTH RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREE SWAMI SAMARTH RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SWAMI SAMARTH RESIDENCY has one building filed: SHREE SWAMI SAMARTH RESIDENCY with 5 floors.

How big is the land of SHREE SWAMI SAMARTH RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SWAMI SAMARTH RESIDENCY stands on 1,295 sq m of land (about 0.3 acres), with 2 sq m of sanctioned built-up area and 844 sq m of recreational open space.

Where can I read reviews of SHREE SWAMI SAMARTH RESIDENCY?

Google Maps has reviews of SHREE SWAMI SAMARTH RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREE SWAMI SAMARTH RESIDENCY?

SHREE SWAMI SAMARTH RESIDENCY by ANIL VASANTRAO CHAVAN is in Kiwale, Pune (pincode 412101), near Dehu Road Cantt, Maharashtra, and is registered on MahaRERA as P52100025793, per GharKundli's check of MahaRERA records.

How many homes are in SHREE SWAMI SAMARTH RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SWAMI SAMARTH RESIDENCY has 16 homes in 1 tower registered on MahaRERA.

When was SHREE SWAMI SAMARTH RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SWAMI SAMARTH RESIDENCY was registered on MahaRERA on 16 July 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREE SWAMI SAMARTH RESIDENCY?

No court cases are listed for SHREE SWAMI SAMARTH RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHREE SWAMI SAMARTH RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ANIL VASANTRAO CHAVAN.