Shelter One
by SHELTER DEVELOPERS · Ghorpade Peth, Pune 411042Also near Swargate, Pune City, Parvati
What’s in the report? →Possession date of Shelter One (MahaRERA P52100026287): 30 October 2026, and it has already passed. It has 38 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100026287. Status: Lapsed (registration period ended). Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P52100026287, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Shelter One?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shelter One has moved
30 June 2026
Completion date given when the project was registered
30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shelter One’s extension records on MahaRERA (P52100026287), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shelter One
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100026287
- Status
- Lapsed (registration period ended)
- Builder
- SHELTER DEVELOPERS
- Location
- Ghorpade Peth, Pune · 411042
- Project type
- Others
- Registered on
- 7 Sep 2020
- Completion date at registration
- June 2026
- Latest completion date
- October 2026
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 38
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shelter One, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHELTER ONE | 5% | 5% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shelter One every 1–2 months.
Shelter One: buildings, flats and land, as filed on MahaRERA
- Buildings: SHELTER ONE (5 floors)
- Land: 456 sq m (about 0.1 acres) · sanctioned built-up 1,263 sq m
- Land, as filed: CTS NO 58, 61, 62, 63 AND 64
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shelter One →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shelter One: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shelter One
What is the possession date of Shelter One?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shelter One in Ghorpade Peth, Pune is 30 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Shelter One?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shelter One's builder has filed on MahaRERA, the official one, is 30 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Shelter One?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shelter One in Ghorpade Peth, Pune is P52100026287.
Is Shelter One registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shelter One is registered as P52100026287 and its status is "Lapsed (registration period ended)".
What is the current construction status of Shelter One? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Shelter One's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHELTER ONE is 5% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Shelter One have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shelter One safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shelter One is registered on MahaRERA as P52100026287, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shelter One?
Shelter One isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shelter One?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shelter One: gharkundli.com/tools/property-cost-calculator
Has Shelter One received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shelter One isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Shelter One?
According to GharKundli's check of MahaRERA records (updated November 2026), Shelter One's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 October 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Shelter One uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shelter One was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shelter One's possession date changes?
The latest dates are on Shelter One's MahaRERA page (P52100026287). GharKundli's Kundli Watch sends a free WhatsApp update on Shelter One every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shelter One have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shelter One has one building filed: SHELTER ONE with 5 floors.
How big is the land of Shelter One?
According to GharKundli's check of MahaRERA records (updated November 2026), Shelter One stands on 456 sq m of land (about 0.1 acres), with 1,263 sq m of sanctioned built-up area.
What are the reviews of Shelter One?
Google Maps has reviews of Shelter One written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shelter One?
Shelter One by SHELTER DEVELOPERS is in Ghorpade Peth, Pune, pincode 411042 (near Swargate, Pune City, Parvati), Maharashtra, and is registered on MahaRERA as P52100026287, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 58, 61, 62, 63 AND 64. GharKundli lists all 67 MahaRERA projects in Swargate (411042).
How many flats are in Shelter One?
According to GharKundli's check of MahaRERA records (updated November 2026), Shelter One has 38 homes in 1 tower registered on MahaRERA.
When was Shelter One registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shelter One was registered on MahaRERA on 7 September 2020. GharKundli did not find a title report on the land on file there.
Does Shelter One have any legal issues or court cases?
No court cases are listed for Shelter One on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Shelter One?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHELTER DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Shelter One
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Pune →
Other projects in Swargate (411042)
- Sonigara New Kalpataru
- Tanish Moti Arcade
- Siddhi Plaza
- Manimaneck Residency
- Aarambh
- Arisya
- Apex Headquarters
- Vision Classic
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.