by SUPREME VISION VENTURES · Baner, Pune

Possession: 7SKYE is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100032077. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about 7SKYE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 7SKYE has moved

  1. 31 March 2023

    Completion date given when the project was registered

  2. 30 September 2023

    Extended at the builder's request (MahaRERA application EXT52100014032)

    Reason the builder gave MahaRERA:
    “I, Mrs. Jayashri Eknath Kshirsagar, Partner of M/s. Supreme Vision Ventures, hereby apply for extension/ renewal of registration of the project 7 Skye’ registered with the regulatory authority vide project registration Certificate bearing M…” Read the full reason“I, Mrs. Jayashri Eknath Kshirsagar, Partner of M/s. Supreme Vision Ventures, hereby apply for extension/ renewal of registration of the project 7 Skye’ registered with the regulatory authority vide project registration Certificate bearing Maha RERA No. P52100032077, which expires on 31st March 2023. We would like to extend the project completion date from 31st March 2023 to 30th September 2023 due to following reasons: 1. To apply for final completion and occupancy certificate , we have to apply to various local departments to get there NOC. This process is very time consuming and tedious.…”

Source: 7SKYE’s extension records on MahaRERA (P52100032077), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 7SKYE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100032077
Status
Completed
Builder
SUPREME VISION VENTURES
Location
Baner, Pune · 411045
Project type
Residential / Group Housing
Registered on
3 Dec 2021
Completion date at registration
March 2023
Latest completion date
September 2023
Delay so far
6 months
Homes
14
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of 7SKYE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
7SKYE100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 7SKYE every month.

7SKYE: buildings, flats and land, as filed on MahaRERA

  • Buildings: 7SKYE (8 floors)
  • Land: 560 sq m (about 0.1 acres) · sanctioned built-up 1,702 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of 7SKYE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

7SKYE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 7SKYE

What is the possession date of 7SKYE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 7SKYE in Baner, Pune is 30 September 2023 — 6 months later than 31 March 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for 7SKYE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 7SKYE's builder has filed on MahaRERA, the official one, is 30 September 2023, already 6 months later than the 31 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 7SKYE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), 7SKYE's builder applied to MahaRERA to extend the completion date once: to 30 September 2023, giving the reason "I, Mrs. Jayashri Eknath Kshirsagar, Partner of M/s. Supreme Vision Ventures, hereby apply for extension/ renewal of registration of the project 7 Skye’ registered with the regulatory authority vide project registration Certificate bearing Maha RERA No. P52100032077, which expires on 31st March 2023. We would like to extend the project completion date from 31st March 2023 to 30th September 2023 due to following reasons: 1. To apply for final completion and occupancy certificate , we have to apply to various local departments to get there NOC. This process is very time consuming and tedious.…".

What is the RERA number of 7SKYE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 7SKYE in Baner, Pune is P52100032077.

Is 7SKYE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 7SKYE is registered as P52100032077 and its status is "Completed".

What is the construction status of 7SKYE?

According to GharKundli's check of MahaRERA records (updated November 2026), 7SKYE's status on MahaRERA is "Completed". As filed by the builder, slab work on 7SKYE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does 7SKYE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is 7SKYE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), 7SKYE is registered on MahaRERA as P52100032077, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 7SKYE's possession date changes?

The latest dates are on 7SKYE's MahaRERA page (P52100032077). GharKundli's Kundli Watch sends a free WhatsApp update on 7SKYE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 7SKYE have?

According to GharKundli's check of MahaRERA records (updated November 2026), 7SKYE has one building filed: 7SKYE with 8 floors.

How big is the land of 7SKYE?

According to GharKundli's check of MahaRERA records (updated November 2026), 7SKYE stands on 560 sq m of land (about 0.1 acres), with 1,702 sq m of sanctioned built-up area.

Where can I read reviews of 7SKYE?

Google Maps has reviews of 7SKYE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 7SKYE?

7SKYE by SUPREME VISION VENTURES is in Baner, Pune (pincode 411045), Maharashtra, and is registered on MahaRERA as P52100032077, per GharKundli's check of MahaRERA records.

How many homes are in 7SKYE?

According to GharKundli's check of MahaRERA records (updated November 2026), 7SKYE has 14 homes in 1 tower registered on MahaRERA.

When was 7SKYE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 7SKYE was registered on MahaRERA on 3 December 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on 7SKYE?

No court cases are listed for 7SKYE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of 7SKYE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SUPREME VISION VENTURES.

Other projects in Baner

All 425 projects in Baner (411045) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.