Skip to content
GharKundli

SAI PARADISE RESIDENCY

by SAI DEVELOPERS · Ambegaon Bk, Pune

Possession date of SAI PARADISE RESIDENCY: 30 October 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100051366. Status: Lapsed (registration period ended). Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about SAI PARADISE RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI PARADISE RESIDENCY has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAI PARADISE RESIDENCY’s extension records on MahaRERA (P52100051366), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI PARADISE RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100051366
Status
Lapsed (registration period ended)
Builder
SAI DEVELOPERS
Location
Ambegaon Bk, Pune · 411046
Project type
Residential / Group Housing
Registered on
8 Jun 2023
Completion date at registration
June 2026
Latest completion date
October 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
24
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
34

Construction progress of SAI PARADISE RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI PARADISE RESIDENCY100%90%90%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI PARADISE RESIDENCY every month.

SAI PARADISE RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI PARADISE RESIDENCY (7 floors)
  • Land: 500 sq m (about 0.1 acres) · sanctioned built-up 548 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI PARADISE RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI PARADISE RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI PARADISE RESIDENCY

What is the possession date of SAI PARADISE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI PARADISE RESIDENCY in Ambegaon Bk, Pune is 30 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SAI PARADISE RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI PARADISE RESIDENCY's builder has filed on MahaRERA, the official one, is 30 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SAI PARADISE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI PARADISE RESIDENCY in Ambegaon Bk, Pune is P52100051366.

Is SAI PARADISE RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI PARADISE RESIDENCY is registered as P52100051366 and its status is "Lapsed (registration period ended)".

What is the construction status of SAI PARADISE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI PARADISE RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI PARADISE RESIDENCY is 90% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does SAI PARADISE RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAI PARADISE RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI PARADISE RESIDENCY is registered on MahaRERA as P52100051366, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI PARADISE RESIDENCY's possession date changes?

The latest dates are on SAI PARADISE RESIDENCY's MahaRERA page (P52100051366). GharKundli's Kundli Watch sends a free WhatsApp update on SAI PARADISE RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI PARADISE RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI PARADISE RESIDENCY has one building filed: SAI PARADISE RESIDENCY with 7 floors.

How big is the land of SAI PARADISE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI PARADISE RESIDENCY stands on 500 sq m of land (about 0.1 acres), with 548 sq m of sanctioned built-up area.

Where can I read reviews of SAI PARADISE RESIDENCY?

Google Maps has reviews of SAI PARADISE RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI PARADISE RESIDENCY?

SAI PARADISE RESIDENCY by SAI DEVELOPERS is in Ambegaon Bk, Pune (pincode 411046), Maharashtra, and is registered on MahaRERA as P52100051366, per GharKundli's check of MahaRERA records.

How many homes are in SAI PARADISE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI PARADISE RESIDENCY has 24 homes in 1 tower registered on MahaRERA.

When was SAI PARADISE RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI PARADISE RESIDENCY was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI PARADISE RESIDENCY?

No court cases are listed for SAI PARADISE RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAI PARADISE RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAI DEVELOPERS, which has 34 other projects registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in Ambegaon Bk

All 215 projects in Katraj (411046) →

Other projects by SAI DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.