Skip to content
GharKundli

MARIGOLD VILLAS

by SHRI NARAYANI DEVELOPERS · Kaivalyadham, Pune

Possession date of MARIGOLD VILLAS: 31 July 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100052739, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about MARIGOLD VILLAS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MARIGOLD VILLAS has moved

  1. 31 March 2028

    Completion date given when the project was registered

  2. 31 July 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MARIGOLD VILLAS’s extension records on MahaRERA (P52100052739), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MARIGOLD VILLAS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100052739
Status
Registered and active
Builder
SHRI NARAYANI DEVELOPERS
Location
Kaivalyadham, Pune · 410403
Project type
Residential / Group Housing
Registered on
22 Sep 2023
Completion date at registration
March 2028
Latest completion date
July 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
35
Sold or booked
14%
Towers
35
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MARIGOLD VILLAS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TYPE -A TENAMENT NO - 02100%100%100%100%
TYPE - A TENAMENT NO - 03100%100%100%100%
TYPE -A TENAMENT NO - 04100%100%100%100%
TYPE - B TENAMENT NO - 05100%100%100%0%
TYPE - B TENAMENT NO - 06100%100%100%0%
TYPE - B TENAMENT NO - 07100%100%100%0%
TYPE - C TENAMENT NO - 08100%0%0%0%
TYPE - C TENAMENT NO - 09100%100%100%100%
TYPE -C TENAMENT NO - 10100%100%100%100%
TYPE - D TENEMENT NO - 11100%100%0%0%
TYPE - D TENTAMENT NO - 12100%100%50%0%
TYPE - E TENTAMENT NO - 13100%100%0%0%
TYPE - E TENTAMENT NO - 14100%100%50%0%
TYPE - E TENTAMENT NO - 15100%100%50%0%
TYPE - F TENTAMENT NO - 16100%100%0%0%
TYPE - F TENTAMENT NO - 17100%100%0%0%
TYPE - C TENTAMENT NO - 18100%100%80%0%
TYPE - C TENTAMENT NO - 19100%100%70%0%
TYPE - C TENTAMENT NO - 20100%100%50%0%
TYPE - G TENTAMENT NO - 21100%100%50%0%
TYPE - G TENTAMENT N0 - 22100%100%50%0%
TYPE - G TENTAMENT NO -23100%100%50%0%
TYPE - G TENTAMENT NO - 24100%100%50%0%
TYPE -H TENTAMENT NO - 250%0%0%0%
TYPE - H TENTAMENT NO - 260%0%0%0%
TYPE - H TENTAMENT NO - 270%0%0%0%
TYPE - H TENTAMENT NO - 280%0%0%0%
TYPE - A TENTAMENT NO -290%0%0%0%
TYPE - A TENAMENT NO - 300%0%0%0%
TYPE - A TENAMENT NO - 310%0%0%0%

Showing 30 of 35 towers.

Commencement certificate (CC), as filed on MahaRERA

  • TYPE -A TENAMENT NO - 02: covers 1 floors
  • TYPE - A TENAMENT NO - 03: covers 1 floors
  • TYPE -A TENAMENT NO - 04: covers 1 floors
  • TYPE - B TENAMENT NO - 05: covers 1 floors
  • TYPE - B TENAMENT NO - 06: covers 1 floors
  • TYPE - B TENAMENT NO - 07: covers 1 floors
  • TYPE - C TENAMENT NO - 08: covers 1 floors
  • TYPE - C TENAMENT NO - 09: covers 1 floors
  • TYPE -C TENAMENT NO - 10: covers 1 floors
  • TYPE - D TENEMENT NO - 11: covers 1 floors
  • TYPE - D TENTAMENT NO - 12: covers 1 floors
  • TYPE - E TENTAMENT NO - 13: covers 1 floors
  • TYPE - E TENTAMENT NO - 14: covers 1 floors
  • TYPE - E TENTAMENT NO - 15: covers 1 floors
  • TYPE - F TENTAMENT NO - 16: covers 1 floors
  • TYPE - F TENTAMENT NO - 17: covers 1 floors
  • TYPE - C TENTAMENT NO - 18: covers 1 floors
  • TYPE - C TENTAMENT NO - 19: covers 1 floors
  • TYPE - C TENTAMENT NO - 20: covers 1 floors
  • TYPE - G TENTAMENT NO - 21: covers 1 floors
  • TYPE - G TENTAMENT N0 - 22: covers 1 floors
  • TYPE - G TENTAMENT NO -23: covers 1 floors
  • TYPE - G TENTAMENT NO - 24: covers 1 floors
  • TYPE -H TENTAMENT NO - 25: covers 1 floors
  • TYPE - H TENTAMENT NO - 26: covers 1 floors
  • TYPE - H TENTAMENT NO - 27: covers 1 floors
  • TYPE - H TENTAMENT NO - 28: covers 1 floors
  • TYPE - A TENTAMENT NO -29: covers 1 floors
  • TYPE - A TENAMENT NO - 30: covers 1 floors
  • TYPE - A TENAMENT NO - 31: covers 1 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MARIGOLD VILLAS every month.

MARIGOLD VILLAS: buildings, flats and land, as filed on MahaRERA

  • Buildings: TYPE -A TENAMENT NO - 02 (1 floors, 1 units) · TYPE - A TENAMENT NO - 03 (1 floors, 1 units) · TYPE -A TENAMENT NO - 04 (1 floors, 1 units) · TYPE - B TENAMENT NO - 05 (1 floors, 1 units) · TYPE - B TENAMENT NO - 06 (1 floors, 1 units) · TYPE - B TENAMENT NO - 07 (1 floors, 1 units) · TYPE - C TENAMENT NO - 08 (1 floors, 1 units) · TYPE - C TENAMENT NO - 09 (1 floors, 1 units) · and 22 more
  • Car parking: 35 open
  • Land: 13,900 sq m (about 3.4 acres) · sanctioned built-up 5,136 sq m
  • Boundaries filed include: MUMBAI PUNE EXPRESS HIGHWAY, PARSI COLONY

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MARIGOLD VILLAS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MARIGOLD VILLAS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MARIGOLD VILLAS

What is the possession date of MARIGOLD VILLAS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MARIGOLD VILLAS in Kaivalyadham, Pune is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MARIGOLD VILLAS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MARIGOLD VILLAS's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of MARIGOLD VILLAS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MARIGOLD VILLAS in Kaivalyadham, Pune is P52100052739.

Is MARIGOLD VILLAS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MARIGOLD VILLAS is registered as P52100052739 and its status is "Registered and active".

What is the construction status of MARIGOLD VILLAS?

According to GharKundli's check of MahaRERA records (updated November 2026), MARIGOLD VILLAS's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does MARIGOLD VILLAS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is MARIGOLD VILLAS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MARIGOLD VILLAS is registered on MahaRERA as P52100052739, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MARIGOLD VILLAS's possession date changes?

The latest dates are on MARIGOLD VILLAS's MahaRERA page (P52100052739). GharKundli's Kundli Watch sends a free WhatsApp update on MARIGOLD VILLAS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MARIGOLD VILLAS have?

According to GharKundli's check of MahaRERA records (updated November 2026), MARIGOLD VILLAS has 30 buildings filed: TYPE -A TENAMENT NO - 02 with 1 floors and 1 units; TYPE - A TENAMENT NO - 03 with 1 floors and 1 units; TYPE -A TENAMENT NO - 04 with 1 floors and 1 units; TYPE - B TENAMENT NO - 05 with 1 floors and 1 units; TYPE - B TENAMENT NO - 06 with 1 floors and 1 units; TYPE - B TENAMENT NO - 07 with 1 floors and 1 units; and 24 more.

How much parking does MARIGOLD VILLAS have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 35 open car parking spaces for MARIGOLD VILLAS.

How big is the land of MARIGOLD VILLAS?

According to GharKundli's check of MahaRERA records (updated November 2026), MARIGOLD VILLAS stands on 13,900 sq m of land (about 3.4 acres), with 5,136 sq m of sanctioned built-up area.

Where can I read reviews of MARIGOLD VILLAS?

Google Maps has reviews of MARIGOLD VILLAS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MARIGOLD VILLAS?

MARIGOLD VILLAS by SHRI NARAYANI DEVELOPERS is in Kaivalyadham, Pune (pincode 410403), Maharashtra, and is registered on MahaRERA as P52100052739, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUMBAI PUNE EXPRESS HIGHWAY, PARSI COLONY.

How many homes are in MARIGOLD VILLAS?

According to GharKundli's check of MahaRERA records (updated November 2026), MARIGOLD VILLAS has 35 homes in 35 towers registered on MahaRERA, and 14% of them are sold or booked.

When was MARIGOLD VILLAS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MARIGOLD VILLAS was registered on MahaRERA on 22 September 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on MARIGOLD VILLAS?

No court cases are listed for MARIGOLD VILLAS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of MARIGOLD VILLAS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHRI NARAYANI DEVELOPERS.

All projects with possession due in 2028 in Pune →

Other projects in Mawal

All 3 projects in Kaivalyadham (410403) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.