BML ML Tower
by BML Builders · Padgha, Pune 421101Registered on MahaRERA as “ML Tower”
What’s in the report? →Possession date of BML ML Tower (MahaRERA P52100053327): 13 May 2027, moved from 13 July 2026 (6 months later). It has 20 homes, 72% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100053327, and currently active. Its completion date has moved from July 2026 to May 2027: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100053327, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about BML ML Tower?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of BML ML Tower has moved
13 July 2026
Completion date given when the project was registered
13 January 2027
Extended at the builder's request (MahaRERA application EA12072621731)
13 May 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: BML ML Tower’s extension records on MahaRERA (P52100053327), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BML ML Tower
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100053327
- Status
- Registered and active
- Builder
- BML Builders
- Location
- Padgha, Pune · 421101
- Project type
- Mixed
- Registered on
- 27 Oct 2023
- Completion date at registration
- July 2026
- Latest completion date
- May 2027
- Delay so far
- 6 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 20
- Sold or booked
- 72%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of BML ML Tower, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A Building | 100% | 100% | 92% | 70% |
Commencement certificate (CC), as filed on MahaRERA
- A Building: covers 12 (BP + LGP + UG + 9 Floors)
Latest CC order on MahaRERA: dated 20/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BML ML Tower every 1–2 months.
BML ML Tower: buildings, flats and land, as filed on MahaRERA
- Buildings: A Building (12 floors, 53 units)
- Car parking: 36 covered
- Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 4,277 sq m
- Land, as filed: Survey No. 97/1A/1A/15 Ravet Pune 412101
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of BML ML Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BML ML Tower: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about BML ML Tower
What is the possession date of BML ML Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BML ML Tower in Padgha, Pune is 13 May 2027 — 6 months later than 13 July 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 6 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for BML ML Tower?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BML ML Tower's builder has filed on MahaRERA, the official one, is 13 May 2027, already 6 months later than the 13 July 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BML ML Tower extended?
According to GharKundli's check of MahaRERA records (updated October 2026), BML ML Tower's builder applied to MahaRERA to extend the completion date once: to 13 January 2027. MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of BML ML Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BML ML Tower in Padgha, Pune is P52100053327.
Is BML ML Tower registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BML ML Tower is registered as P52100053327 and its status is "Registered and active".
What is the current construction status of BML ML Tower? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), BML ML Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A Building is 100% done and internal work 92%. GharKundli's full report compares construction progress with the deadline.
Does BML ML Tower have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is BML ML Tower safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BML ML Tower is registered on MahaRERA as P52100053327, its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in BML ML Tower?
BML ML Tower is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in BML ML Tower?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in BML ML Tower: gharkundli.com/tools/property-cost-calculator
Has BML ML Tower received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), BML ML Tower is still under construction, with 13 May 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has BML ML Tower uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for BML ML Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if BML ML Tower's possession date changes?
The latest dates are on BML ML Tower's MahaRERA page (P52100053327). GharKundli's Kundli Watch sends a free WhatsApp update on BML ML Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BML ML Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), BML ML Tower has one building filed: A Building with 12 floors and 53 units.
How much parking does BML ML Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 36 covered car parking spaces for BML ML Tower.
How big is the land of BML ML Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), BML ML Tower stands on 1,000 sq m of land (about 0.2 acres), with 4,277 sq m of sanctioned built-up area.
What are the reviews of BML ML Tower?
Google Maps has reviews of BML ML Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of BML ML Tower?
BML ML Tower by BML Builders is in Padgha, Pune, pincode 421101, Maharashtra, and is registered on MahaRERA as P52100053327, per GharKundli's check of MahaRERA records. Its land is filed as Survey No. 97/1A/1A/15 Ravet Pune 412101. GharKundli lists all 4 MahaRERA projects in Padgha (421101).
How many flats are in BML ML Tower, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), BML ML Tower has 20 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.
When was BML ML Tower registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BML ML Tower was registered on MahaRERA on 27 October 2023. GharKundli did not find a title report on the land on file there.
Does BML ML Tower have any legal issues or court cases?
No court cases are listed for BML ML Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of BML ML Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BML Builders.
Check it yourself on MahaRERA
- How to check the possession date of BML ML Tower
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Haveli
All 4 projects in Padgha (421101) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.