Jash Apartment
by SHRI SAI CONSTRUCTION · Padghe, Palghar 421101
What’s in the report? →Possession date of Jash Apartment (MahaRERA P99000022810): 30 April 2028, moved from 30 March 2022 (69 months later). It has 46 homes, 23% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000022810, and currently active. Its completion date has moved from March 2022 to April 2028: 69 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P99000022810, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Jash Apartment?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Jash Apartment has moved
30 March 2022
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT99000011817)
Reason the builder gave MahaRERA: “DUE TO COVID-19 SHORTAGE OF LABOUR AND MATERIAL ON TIME LEAD US TO EXTEND THE PROJECT TIMELINE”
31 December 2027
Extended at the builder's request (MahaRERA application EA04102518021)
Reason the builder gave MahaRERA: “DUE TO SLOW MOVING MARKET IN PALGHAR AREA. AND SLOW AND LOW COLLECTION FROM PROJECT COMPARED TO PROGRESS OF THE PROJECT. IT WILL VERY DIFFICULT TO COMPLETE THE PROJECT IN GIVEN TIME.. SO WE REQUIRE MORE TIME TO COMPLETE THE SAME”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Jash Apartment’s extension records on MahaRERA (P99000022810), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Jash Apartment
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000022810
- Status
- Registered and active
- Builder
- SHRI SAI CONSTRUCTION
- Location
- Padghe, Palghar · 421101
- Project type
- Others
- Registered on
- 30 Oct 2019
- Completion date at registration
- March 2022
- Latest completion date
- April 2028
- Delay so far
- 69 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 46
- Sold or booked
- 23%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Jash Apartment, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| JASH APARTMENT | 100% | 100% | 95% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- JASH APARTMENT: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jash Apartment every 1–2 months.
Jash Apartment: buildings, flats and land, as filed on MahaRERA
- Buildings: JASH APARTMENT (4 floors, 53 units)
- Land: 2,602 sq m (about 0.6 acres) · sanctioned built-up 1,823 sq m
- Land, as filed: GUT NO 150
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Jash Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Jash Apartment: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Jash Apartment
What is the possession date of Jash Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Jash Apartment in Padghe, Palghar is 30 April 2028 — 69 months later than 30 March 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 69 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Jash Apartment?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Jash Apartment's builder has filed on MahaRERA, the official one, is 30 April 2028, already 69 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Jash Apartment extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Jash Apartment's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "DUE TO COVID-19 SHORTAGE OF LABOUR AND MATERIAL ON TIME LEAD US TO EXTEND THE PROJECT TIMELINE"; to 31 December 2027, giving the reason "DUE TO SLOW MOVING MARKET IN PALGHAR AREA. AND SLOW AND LOW COLLECTION FROM PROJECT COMPARED TO PROGRESS OF THE PROJECT. IT WILL VERY DIFFICULT TO COMPLETE THE PROJECT IN GIVEN TIME.. SO WE REQUIRE MORE TIME TO COMPLETE THE SAME". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Jash Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Jash Apartment in Padghe, Palghar is P99000022810.
Is Jash Apartment registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Jash Apartment is registered as P99000022810 and its status is "Registered and active".
What is the current construction status of Jash Apartment? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Jash Apartment's status on MahaRERA is "Registered and active". As filed by the builder, slab work on JASH APARTMENT is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Jash Apartment have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Jash Apartment safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Jash Apartment is registered on MahaRERA as P99000022810, its completion date has moved 69 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Jash Apartment?
Jash Apartment is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Jash Apartment?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Jash Apartment: gharkundli.com/tools/property-cost-calculator
Has Jash Apartment received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Jash Apartment is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Jash Apartment uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Jash Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Jash Apartment's possession date changes?
The latest dates are on Jash Apartment's MahaRERA page (P99000022810). GharKundli's Kundli Watch sends a free WhatsApp update on Jash Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Jash Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), Jash Apartment has one building filed: JASH APARTMENT with 4 floors and 53 units.
How big is the land of Jash Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Jash Apartment stands on 2,602 sq m of land (about 0.6 acres), with 1,823 sq m of sanctioned built-up area.
What are the reviews of Jash Apartment?
Google Maps has reviews of Jash Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Jash Apartment?
Jash Apartment by SHRI SAI CONSTRUCTION is in Padghe, Palghar, pincode 421101, Maharashtra, and is registered on MahaRERA as P99000022810, per GharKundli's check of MahaRERA records. Its land is filed as GUT NO 150. GharKundli lists all 4 MahaRERA projects in Padgha (421101).
How many flats are in Jash Apartment, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Jash Apartment has 46 homes in 1 tower registered on MahaRERA, and 23% of them are sold or booked.
When was Jash Apartment registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Jash Apartment was registered on MahaRERA on 30 October 2019. GharKundli did not find a title report on the land on file there.
Does Jash Apartment have any legal issues or court cases?
No court cases are listed for Jash Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Jash Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRI SAI CONSTRUCTION, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Jash Apartment
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Padgha (421101)
- Pushpanjali
- ML Tower
- Shaligram Township
- Bhakti Apartment
- Jivdani Residency
- Shree Ganesh Apartment
- Jivdani Residency
Other projects by SHRI SAI CONSTRUCTION
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.