Shiv Shanti Residency
by Shree Guruji Infra · tembhode naka, PalgharAlso near Palghar West, Ganesh Nagar Tembhode
Possession date of Shiv Shanti Residency: 28 February 2029, moved from 30 October 2024 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000020975, and currently active. Its completion date has moved from October 2024 to February 2029: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Shiv Shanti Residency?
How the possession date of Shiv Shanti Residency has moved
30 October 2024
Completion date given when the project was registered
31 October 2028
Extended at the builder's request (MahaRERA application EXT99000017352)
Reason the builder gave MahaRERA: “DUE TO COVID NON AVAILABILTY OF MATRIAL AND LABOUR.”
28 February 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shiv Shanti Residency’s extension records on MahaRERA (P99000020975), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shiv Shanti Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000020975
- Status
- Registered and active
- Builder
- Shree Guruji Infra
- Location
- tembhode naka, Palghar · 401404
- Project type
- Residential / Group Housing
- Registered on
- 27 May 2019
- Completion date at registration
- October 2024
- Latest completion date
- February 2029
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 130
- Sold or booked
- 40%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shiv Shanti Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO-3 TYPE-A: covers 5 floors
- BUILDING NO-2 TYPE -B: covers 5 floors
- BUILDING N0-1 TYPE-C: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shiv Shanti Residency every month.
Shiv Shanti Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO-3 TYPE-A (5 floors, 30 units) · BUILDING NO-2 TYPE -B (5 floors, 30 units) · BUILDING N0-1 TYPE-C (5 floors, 70 units)
- Car parking: 27 open
- Land: 2,500 sq m (about 0.6 acres) · sanctioned built-up 5,888 sq m · recreational space 250 sq m
- Boundaries filed include: layout road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shiv Shanti Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shiv Shanti Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shiv Shanti Residency
What is the possession date of Shiv Shanti Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shiv Shanti Residency in tembhode naka, Palghar is 28 February 2029 — 48 months later than 30 October 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shiv Shanti Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shiv Shanti Residency's builder has filed on MahaRERA, the official one, is 28 February 2029, already 48 months later than the 30 October 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shiv Shanti Residency extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Shanti Residency's builder applied to MahaRERA to extend the completion date once: to 31 October 2028, giving the reason "DUE TO COVID NON AVAILABILTY OF MATRIAL AND LABOUR.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shiv Shanti Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shiv Shanti Residency in tembhode naka, Palghar is P99000020975.
Is Shiv Shanti Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Shanti Residency is registered as P99000020975 and its status is "Registered and active".
What is the construction status of Shiv Shanti Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Shanti Residency's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does Shiv Shanti Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shiv Shanti Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Shanti Residency is registered on MahaRERA as P99000020975, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shiv Shanti Residency's possession date changes?
The latest dates are on Shiv Shanti Residency's MahaRERA page (P99000020975). GharKundli's Kundli Watch sends a free WhatsApp update on Shiv Shanti Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shiv Shanti Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Shanti Residency has 3 buildings filed: BUILDING NO-3 TYPE-A with 5 floors and 30 units; BUILDING NO-2 TYPE -B with 5 floors and 30 units; BUILDING N0-1 TYPE-C with 5 floors and 70 units.
How much parking does Shiv Shanti Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 27 open car parking spaces for Shiv Shanti Residency.
How big is the land of Shiv Shanti Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Shanti Residency stands on 2,500 sq m of land (about 0.6 acres), with 5,888 sq m of sanctioned built-up area and 250 sq m of recreational open space.
Where can I read reviews of Shiv Shanti Residency?
Google Maps has reviews of Shiv Shanti Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shiv Shanti Residency?
Shiv Shanti Residency by Shree Guruji Infra is in tembhode naka, Palghar (pincode 401404), near Palghar West, Ganesh Nagar Tembhode, Maharashtra, and is registered on MahaRERA as P99000020975, per GharKundli's check of MahaRERA records. Its boundaries filed there include layout road.
How many homes are in Shiv Shanti Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Shanti Residency has 130 homes in 3 towers registered on MahaRERA, and 40% of them are sold or booked.
When was Shiv Shanti Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Shanti Residency was registered on MahaRERA on 27 May 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Shiv Shanti Residency?
No court cases are listed for Shiv Shanti Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Shiv Shanti Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shree Guruji Infra.
Check it yourself on MahaRERA
- How to check the possession date of Shiv Shanti Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Palghar →
Other projects in Palghar
- Elite Residency
- Sunshine Complex
- V SQUARE ARCADE
- Rubicon Shinde Heritage
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.