PARSHV ELITE PHASE I

by PARSHV HOMES · Birwadi, Palghar

Possession date of PARSHV ELITE PHASE I: 31 May 2024, moved from 30 May 2022 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P99000022512. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (May 2024) has passed.

What do you want to know about PARSHV ELITE PHASE I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PARSHV ELITE PHASE I has moved

  1. 30 May 2022

    Completion date given when the project was registered

  2. 28 February 2023

    Extended at the builder's request (MahaRERA application EXT99000011916)

    Reason the builder gave MahaRERA: “WE HAVE NOT RECEIVED THE OCCUPATION CERTIFICATE AND OUR SALE IS ALSO VERY SLOW THAT'S WHY WE WANT TO EXTEND OUR RERA CERTIFICATE.”
  3. 30 May 2023

    Extended at the builder's request (MahaRERA application EXT99000013969)

    Reason the builder gave MahaRERA: “WE HAVE APPLIED FOR OCCUPATION CERTIFICATE BUT STILL WE HAVE NOT RECEIVED THE O.C AND OUR SOME FLATS ARE STILL PENDING FOR SALE.SO WE WANT TO EXTEND OUR RERA FOR 1 YEAR.”
  4. 31 May 2024

    Extended at the builder's request (MahaRERA application EXT99000016619)

    Reason the builder gave MahaRERA: “WE WANT TO EXTEND OUR RERA CERTIFICATE DUE TO STILL FLATS ARE PENDING TO SALE AND STILL WE HAVE NOT RECEIVED OCCUPATION CERTIFICATE.”

Source: PARSHV ELITE PHASE I’s extension records on MahaRERA (P99000022512), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PARSHV ELITE PHASE I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000022512
Status
Lapsed (registration period ended)
Builder
PARSHV HOMES
Location
Birwadi, Palghar · 401404
Project type
Others
Registered on
30 Sep 2019
Completion date at registration
May 2022
Latest completion date
May 2024
Delay so far
24 months
Homes
81
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of PARSHV ELITE PHASE I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING100%100%100%0%
B WING100%100%100%0%
C WING100%100%100%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARSHV ELITE PHASE I every month.

PARSHV ELITE PHASE I: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING (5 floors) · B WING (5 floors) · C WING (5 floors)
  • Land: 2,849 sq m (about 0.7 acres) · sanctioned built-up 5,940 sq m · recreational space 6,000 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PARSHV ELITE PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PARSHV ELITE PHASE I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PARSHV ELITE PHASE I

What is the possession date of PARSHV ELITE PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PARSHV ELITE PHASE I in Birwadi, Palghar is 31 May 2024 — 24 months later than 30 May 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PARSHV ELITE PHASE I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PARSHV ELITE PHASE I's builder has filed on MahaRERA, the official one, is 31 May 2024, already 24 months later than the 30 May 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PARSHV ELITE PHASE I extended?

According to GharKundli's check of MahaRERA records (updated November 2026), PARSHV ELITE PHASE I's builder applied to MahaRERA to extend the completion date 3 times: to 28 February 2023, giving the reason "WE HAVE NOT RECEIVED THE OCCUPATION CERTIFICATE AND OUR SALE IS ALSO VERY SLOW THAT'S WHY WE WANT TO EXTEND OUR RERA CERTIFICATE."; to 30 May 2023, giving the reason "WE HAVE APPLIED FOR OCCUPATION CERTIFICATE BUT STILL WE HAVE NOT RECEIVED THE O.C AND OUR SOME FLATS ARE STILL PENDING FOR SALE.SO WE WANT TO EXTEND OUR RERA FOR 1 YEAR."; to 31 May 2024, giving the reason "WE WANT TO EXTEND OUR RERA CERTIFICATE DUE TO STILL FLATS ARE PENDING TO SALE AND STILL WE HAVE NOT RECEIVED OCCUPATION CERTIFICATE.".

What is the RERA number of PARSHV ELITE PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PARSHV ELITE PHASE I in Birwadi, Palghar is P99000022512.

Is PARSHV ELITE PHASE I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PARSHV ELITE PHASE I is registered as P99000022512 and its status is "Lapsed (registration period ended)".

What is the construction status of PARSHV ELITE PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), PARSHV ELITE PHASE I's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does PARSHV ELITE PHASE I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is PARSHV ELITE PHASE I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PARSHV ELITE PHASE I is registered on MahaRERA as P99000022512, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PARSHV ELITE PHASE I's possession date changes?

The latest dates are on PARSHV ELITE PHASE I's MahaRERA page (P99000022512). GharKundli's Kundli Watch sends a free WhatsApp update on PARSHV ELITE PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PARSHV ELITE PHASE I have?

According to GharKundli's check of MahaRERA records (updated November 2026), PARSHV ELITE PHASE I has 3 buildings filed: A WING with 5 floors; B WING with 5 floors; C WING with 5 floors.

How big is the land of PARSHV ELITE PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), PARSHV ELITE PHASE I stands on 2,849 sq m of land (about 0.7 acres), with 5,940 sq m of sanctioned built-up area and 6,000 sq m of recreational open space.

Where can I read reviews of PARSHV ELITE PHASE I?

Google Maps has reviews of PARSHV ELITE PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PARSHV ELITE PHASE I?

PARSHV ELITE PHASE I by PARSHV HOMES is in Birwadi, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000022512, per GharKundli's check of MahaRERA records.

How many homes are in PARSHV ELITE PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), PARSHV ELITE PHASE I has 81 homes in 3 towers registered on MahaRERA.

When was PARSHV ELITE PHASE I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PARSHV ELITE PHASE I was registered on MahaRERA on 30 September 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on PARSHV ELITE PHASE I?

No court cases are listed for PARSHV ELITE PHASE I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PARSHV ELITE PHASE I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PARSHV HOMES.

Other projects in Palghar

All 366 projects in Palghar (401404) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.