Gote Parin Empire
by Gote Bhilare Associates · Dhayri, Pune 411041Also near Narhe, Ganesh NagarRegistered on MahaRERA as “Parin Empire”
What’s in the report? →Possession date of Gote Parin Empire (MahaRERA P52100001226): 31 December 2026, moved from 28 February 2022 (58 months later). It has 72 homes, 100% sold or booked. 2 complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100001226, and currently active.
Source: MahaRERA website — records for P52100001226, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Gote Parin Empire?
1 tribunal appeal MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Gote Parin Empire has moved
28 February 2022
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA21082622323)
Reason the builder gave MahaRERA: “The construction of the said project was fully completed and the Full Occupation Certificate has been duly obtained. We required an extension for completion Of project.”
Source: Gote Parin Empire’s extension records on MahaRERA (P52100001226), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gote Parin Empire
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100001226
- Status
- Registered and active
- Builder
- Gote Bhilare Associates
- Location
- Dhayri, Pune · 411041
- Project type
- Residential / Group Housing
- Registered on
- 27 Jul 2017
- Completion date at registration
- February 2022
- Latest completion date
- December 2026
- Delay so far
- 58 months
- Homes
- 72
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Gote Parin Empire, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A - Wing | 100% | 9% | 20% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A - Wing: covers 13 floors
Latest CC order on MahaRERA: dated 22/06/2021.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gote Parin Empire every 1–2 months.
Gote Parin Empire: buildings, flats and land, as filed on MahaRERA
- Buildings: A - Wing (13 floors, 72 units)
- Car parking: 63 covered, 14 open
- Land: 3,000 sq m (about 0.7 acres) · sanctioned built-up 3,021 sq m · recreational space 277 sq m
- Land, as filed: 22/19
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Gote Parin Empire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gote Parin Empire: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Gote Parin Empire
What is the possession date of Gote Parin Empire?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gote Parin Empire in Dhayri, Pune is 31 December 2026 — 58 months later than 28 February 2022, the date given at registration.
The date has already moved 58 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Gote Parin Empire?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gote Parin Empire's builder has filed on MahaRERA, the official one, is 31 December 2026, already 58 months later than the 28 February 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gote Parin Empire extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Gote Parin Empire's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The construction of the said project was fully completed and the Full Occupation Certificate has been duly obtained. We required an extension for completion Of project.".
What is the RERA number of Gote Parin Empire?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gote Parin Empire in Dhayri, Pune is P52100001226.
Is Gote Parin Empire registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gote Parin Empire is registered as P52100001226 and its status is "Registered and active".
What is the current construction status of Gote Parin Empire? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Gote Parin Empire's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A - Wing is 9% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.
Does Gote Parin Empire have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
2 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →
Is Gote Parin Empire safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Gote Parin Empire is registered on MahaRERA as P52100001226, its completion date has moved 58 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Gote Parin Empire?
Gote Parin Empire is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Gote Parin Empire?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Gote Parin Empire: gharkundli.com/tools/property-cost-calculator
Has Gote Parin Empire received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Gote Parin Empire is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Gote Parin Empire uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Gote Parin Empire was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Gote Parin Empire's possession date changes?
The latest dates are on Gote Parin Empire's MahaRERA page (P52100001226). GharKundli's Kundli Watch sends a free WhatsApp update on Gote Parin Empire every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gote Parin Empire have?
According to GharKundli's check of MahaRERA records (updated October 2026), Gote Parin Empire has one building filed: A - Wing with 13 floors and 72 units.
How much parking does Gote Parin Empire have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 63 covered and 14 open car parking spaces for Gote Parin Empire.
How big is the land of Gote Parin Empire?
According to GharKundli's check of MahaRERA records (updated October 2026), Gote Parin Empire stands on 3,000 sq m of land (about 0.7 acres), with 3,021 sq m of sanctioned built-up area and 277 sq m of recreational open space.
What are the reviews of Gote Parin Empire?
Google Maps has reviews of Gote Parin Empire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Gote Parin Empire?
Gote Parin Empire by Gote Bhilare Associates is in Dhayri, Pune, pincode 411041 (near Narhe, Ganesh Nagar), Maharashtra, and is registered on MahaRERA as P52100001226, per GharKundli's check of MahaRERA records. Its land is filed as 22/19. GharKundli lists all 263 MahaRERA projects in Dhayari (411041).
How many flats are in Gote Parin Empire, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Gote Parin Empire has 72 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Gote Parin Empire registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gote Parin Empire was registered on MahaRERA on 27 July 2017. GharKundli did not find a title report on the land on file there.
Does Gote Parin Empire have any legal issues or court cases?
No court cases are listed for Gote Parin Empire on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Gote Parin Empire?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Gote Bhilare Associates.
Check it yourself on MahaRERA
- How to check the possession date of Gote Parin Empire
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Pune →
Other projects in Dhayari (411041)
- Venkatesh Hillside Plot 2 Building 2
- Venkatesh Hillside Building C
- Swa Kutumb
- Pratham Vihar Phase I
- Yash Ganga Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.