MORYA RESIDENCY
by N G REALTY · Thergaon, Pune
Possession date of MORYA RESIDENCY: 31 December 2022, moved from 31 July 2019 (41 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100006984. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2022) has passed.
What do you want to know about MORYA RESIDENCY?
How the possession date of MORYA RESIDENCY has moved
31 July 2019
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT52100008649)
Reason the builder gave MahaRERA: “Due to retirement of one of the Partner and further due to Covid-19, project could not be completed as expected . Almost 80% of the work is completed and expected to finish the project very soon”
31 December 2022
Extended at the builder's request (MahaRERA application EXT52100011346)
Reason the builder gave MahaRERA: “DUE TO COVID SITUATION IN AND AROUND PUNE CITY AND NON AVAILABLITY OF REQUIRED RESOURCES THE WORK COULD NOT BE COMPLETED AS EXPECTED”
Source: MORYA RESIDENCY’s extension records on MahaRERA (P52100006984), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MORYA RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100006984
- Status
- Lapsed (registration period ended)
- Builder
- N G REALTY
- Location
- Thergaon, Pune · 410507
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- July 2019
- Latest completion date
- December 2022
- Delay so far
- 41 months
- Homes
- 11
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of MORYA RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MORYA RESIDENCY | 100% | 6% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MORYA RESIDENCY every month.
MORYA RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: MORYA RESIDENCY (6 floors)
- Land: 300 sq m (about 0.1 acres) · sanctioned built-up 357 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MORYA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MORYA RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MORYA RESIDENCY
What is the possession date of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MORYA RESIDENCY in Thergaon, Pune is 31 December 2022 — 41 months later than 31 July 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for MORYA RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MORYA RESIDENCY's builder has filed on MahaRERA, the official one, is 31 December 2022, already 41 months later than the 31 July 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MORYA RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), MORYA RESIDENCY's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "Due to retirement of one of the Partner and further due to Covid-19, project could not be completed as expected . Almost 80% of the work is completed and expected to finish the project very soon"; to 31 December 2022, giving the reason "DUE TO COVID SITUATION IN AND AROUND PUNE CITY AND NON AVAILABLITY OF REQUIRED RESOURCES THE WORK COULD NOT BE COMPLETED AS EXPECTED".
What is the RERA number of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MORYA RESIDENCY in Thergaon, Pune is P52100006984.
Is MORYA RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MORYA RESIDENCY is registered as P52100006984 and its status is "Lapsed (registration period ended)".
What is the construction status of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), MORYA RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MORYA RESIDENCY is 6% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does MORYA RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is MORYA RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MORYA RESIDENCY is registered on MahaRERA as P52100006984, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 41 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MORYA RESIDENCY's possession date changes?
The latest dates are on MORYA RESIDENCY's MahaRERA page (P52100006984). GharKundli's Kundli Watch sends a free WhatsApp update on MORYA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MORYA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), MORYA RESIDENCY has one building filed: MORYA RESIDENCY with 6 floors.
How big is the land of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), MORYA RESIDENCY stands on 300 sq m of land (about 0.1 acres), with 357 sq m of sanctioned built-up area.
Where can I read reviews of MORYA RESIDENCY?
Google Maps has reviews of MORYA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MORYA RESIDENCY?
MORYA RESIDENCY by N G REALTY is in Thergaon, Pune (pincode 410507), Maharashtra, and is registered on MahaRERA as P52100006984, per GharKundli's check of MahaRERA records.
How many homes are in MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), MORYA RESIDENCY has 11 homes in 1 tower registered on MahaRERA.
When was MORYA RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MORYA RESIDENCY was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MORYA RESIDENCY?
No court cases are listed for MORYA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is N G REALTY.
Check it yourself on MahaRERA
- How to check the possession date of MORYA RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thergaon
- KHUSHI AANGAN
- SIGNATURE RITZ
- TALREJA BUSINESS HUB
- W P ROYAL ELEVIA
- SIGNATURE PARK BUILDING M MHADA
- MORYA SKYDALE
- ROYAL COURT
- ASHA NIWAS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.