Possession: NIRVANA HOMES is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100013565. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about NIRVANA HOMES?
How the possession date of NIRVANA HOMES has moved
20 October 2020
Completion date given when the project was registered
20 October 2021
Extended at the builder's request (MahaRERA application EXT52100006262)
Reason the builder gave MahaRERA:
“Due to lockdown on account of Covid-19 pandemic, availability of workers became issue and still it is not fully resolved as Pune has become the hub for CORONA with highest no of infected patients. Hence we are still facing difficulties in g…” Read the full reason
“Due to lockdown on account of Covid-19 pandemic, availability of workers became issue and still it is not fully resolved as Pune has become the hub for CORONA with highest no of infected patients. Hence we are still facing difficulties in getting required labourers, workers to complete our project in time. Also the process of getting required NOCs and completion certificates will take further time as Local Government Offices are not working to its 100% capacity. As a result, project cannot be completed before 20th Oct, 2020 in any case and hence extension. In view of above facts, we hereby…”22 July 2022
Extended at the builder's request (MahaRERA application EXT52100011754)
Reason the builder gave MahaRERA: “Increase in Floor Space Index (FSI) Area.”
Source: NIRVANA HOMES’s extension records on MahaRERA (P52100013565), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NIRVANA HOMES
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100013565
- Status
- Completed
- Builder
- Fortune Elite
- Location
- Pimpri, Pune · 412101
- Project type
- Residential / Group Housing
- Registered on
- 13 Oct 2017
- Completion date at registration
- October 2020
- Latest completion date
- July 2022
- Delay so far
- 21 months
- Homes
- 32
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of NIRVANA HOMES, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NIRVANA HOMES | 100% | 100% | 85% | 80% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRVANA HOMES every month.
NIRVANA HOMES: buildings, flats and land, as filed on MahaRERA
- Buildings: NIRVANA HOMES (2 floors)
- Land: 1,209 sq m (about 0.3 acres) · sanctioned built-up 387 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of NIRVANA HOMES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NIRVANA HOMES: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NIRVANA HOMES
What is the possession date of NIRVANA HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NIRVANA HOMES in Pimpri, Pune is 22 July 2022 — 21 months later than 20 October 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for NIRVANA HOMES?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRVANA HOMES's builder has filed on MahaRERA, the official one, is 22 July 2022, already 21 months later than the 20 October 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NIRVANA HOMES extended?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA HOMES's builder applied to MahaRERA to extend the completion date 2 times: to 20 October 2021, giving the reason "Due to lockdown on account of Covid-19 pandemic, availability of workers became issue and still it is not fully resolved as Pune has become the hub for CORONA with highest no of infected patients. Hence we are still facing difficulties in getting required labourers, workers to complete our project in time. Also the process of getting required NOCs and completion certificates will take further time as Local Government Offices are not working to its 100% capacity. As a result, project cannot be completed before 20th Oct, 2020 in any case and hence extension. In view of above facts, we hereby…"; to 22 July 2022, giving the reason "Increase in Floor Space Index (FSI) Area.".
What is the RERA number of NIRVANA HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NIRVANA HOMES in Pimpri, Pune is P52100013565.
Is NIRVANA HOMES registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA HOMES is registered as P52100013565 and its status is "Completed".
What is the construction status of NIRVANA HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA HOMES's status on MahaRERA is "Completed". As filed by the builder, slab work on NIRVANA HOMES is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does NIRVANA HOMES have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is NIRVANA HOMES safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA HOMES is registered on MahaRERA as P52100013565, its MahaRERA status is "Completed", its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NIRVANA HOMES's possession date changes?
The latest dates are on NIRVANA HOMES's MahaRERA page (P52100013565). GharKundli's Kundli Watch sends a free WhatsApp update on NIRVANA HOMES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NIRVANA HOMES have?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA HOMES has one building filed: NIRVANA HOMES with 2 floors.
How big is the land of NIRVANA HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA HOMES stands on 1,209 sq m of land (about 0.3 acres), with 387 sq m of sanctioned built-up area.
Where can I read reviews of NIRVANA HOMES?
Google Maps has reviews of NIRVANA HOMES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NIRVANA HOMES?
NIRVANA HOMES by Fortune Elite is in Pimpri, Pune (pincode 412101), Maharashtra, and is registered on MahaRERA as P52100013565, per GharKundli's check of MahaRERA records.
How many homes are in NIRVANA HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA HOMES has 32 homes in 1 tower registered on MahaRERA.
When was NIRVANA HOMES registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA HOMES was registered on MahaRERA on 13 October 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on NIRVANA HOMES?
No court cases are listed for NIRVANA HOMES on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of NIRVANA HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Fortune Elite.
Check it yourself on MahaRERA
- How to check the possession date of NIRVANA HOMES
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pimpri
- PRASUN SRISHTI
- Skyway Elite
- Mahindra Citadel Phase 1
- The Central Park Phase - IV Tower D4
- Godrej Emerald Waters
- Pradhan Mantri Awas Yojana-Pimpri R. No 77
- Palaash Padam
- METRO VRUNDAVAN B BUILDING
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.