BHAKTI APARTMENT PHASE II
by SARYU BUILDERS & DEVELOPERS · Nearby Genesis Industrial Estate, Palghar
Possession date of BHAKTI APARTMENT PHASE II: 30 April 2027, moved from 30 September 2022 (51 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000024120, and currently active. Its completion date has moved from September 2022 to April 2027: 51 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about BHAKTI APARTMENT PHASE II?
How the possession date of BHAKTI APARTMENT PHASE II has moved
30 September 2022
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT99000016598)
Reason the builder gave MahaRERA: “DUE TO PANDEMIC AND LOCKDOWN THE PROJECT COULD NOT BE COMPLETED ON TIME”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: BHAKTI APARTMENT PHASE II’s extension records on MahaRERA (P99000024120), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BHAKTI APARTMENT PHASE II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000024120
- Status
- Registered and active
- Builder
- SARYU BUILDERS & DEVELOPERS
- Location
- Nearby Genesis Industrial Estate, Palghar · 401501
- Project type
- Others
- Registered on
- 21 Jan 2020
- Completion date at registration
- September 2022
- Latest completion date
- April 2027
- Delay so far
- 51 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 12
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of BHAKTI APARTMENT PHASE II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 1 WING B TYPE B1b | 100% | 100% | 95% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 1 WING B TYPE B1b: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BHAKTI APARTMENT PHASE II every month.
BHAKTI APARTMENT PHASE II: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 1 WING B TYPE B1b (2 floors, 24 units)
- Land: 853 sq m (about 0.2 acres) · sanctioned built-up 635 sq m · recreational space 85 sq m
The builder’s record and reviews
Saryu Builders And Developers has 3 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 33 months late). No complaints on MahaRERA.
Read Google reviews of BHAKTI APARTMENT PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BHAKTI APARTMENT PHASE II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BHAKTI APARTMENT PHASE II
What is the possession date of BHAKTI APARTMENT PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BHAKTI APARTMENT PHASE II in Nearby Genesis Industrial Estate, Palghar is 30 April 2027 — 51 months later than 30 September 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for BHAKTI APARTMENT PHASE II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BHAKTI APARTMENT PHASE II's builder has filed on MahaRERA, the official one, is 30 April 2027, already 51 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BHAKTI APARTMENT PHASE II extended?
According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI APARTMENT PHASE II's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "DUE TO PANDEMIC AND LOCKDOWN THE PROJECT COULD NOT BE COMPLETED ON TIME". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of BHAKTI APARTMENT PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BHAKTI APARTMENT PHASE II in Nearby Genesis Industrial Estate, Palghar is P99000024120.
Is BHAKTI APARTMENT PHASE II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI APARTMENT PHASE II is registered as P99000024120 and its status is "Registered and active".
What is the construction status of BHAKTI APARTMENT PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI APARTMENT PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 1 WING B TYPE B1b is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does BHAKTI APARTMENT PHASE II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is BHAKTI APARTMENT PHASE II safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI APARTMENT PHASE II is registered on MahaRERA as P99000024120, its completion date has moved 51 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BHAKTI APARTMENT PHASE II's possession date changes?
The latest dates are on BHAKTI APARTMENT PHASE II's MahaRERA page (P99000024120). GharKundli's Kundli Watch sends a free WhatsApp update on BHAKTI APARTMENT PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BHAKTI APARTMENT PHASE II have?
According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI APARTMENT PHASE II has one building filed: BUILDING NO 1 WING B TYPE B1b with 2 floors and 24 units.
How big is the land of BHAKTI APARTMENT PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI APARTMENT PHASE II stands on 853 sq m of land (about 0.2 acres), with 635 sq m of sanctioned built-up area and 85 sq m of recreational open space.
What is the track record of BHAKTI APARTMENT PHASE II's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Saryu Builders And Developers has 3 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 33 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of BHAKTI APARTMENT PHASE II?
Google Maps has reviews of BHAKTI APARTMENT PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BHAKTI APARTMENT PHASE II?
BHAKTI APARTMENT PHASE II by SARYU BUILDERS & DEVELOPERS is in Nearby Genesis Industrial Estate, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000024120, per GharKundli's check of MahaRERA records.
How many homes are in BHAKTI APARTMENT PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI APARTMENT PHASE II has 12 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was BHAKTI APARTMENT PHASE II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI APARTMENT PHASE II was registered on MahaRERA on 21 January 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on BHAKTI APARTMENT PHASE II?
No court cases are listed for BHAKTI APARTMENT PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of BHAKTI APARTMENT PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SARYU BUILDERS & DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of BHAKTI APARTMENT PHASE II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Palghar
- Elite Residency
- Sunshine Complex
- V SQUARE ARCADE
- Rubicon Shinde Heritage
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.