Ace Almighty Delta Tower

by M/S. ACE ALMIGHTY (Jhamtani) · Tathawade, Pune 411033Also near Wakad, Near Bhumkar Chowk, vinode nagar

What’s in the report? →

Possession date of Ace Almighty Delta Tower (MahaRERA P52100022574): 30 December 2023, and it has already passed. It has 52 homes, 97% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100022574. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100022574, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about Ace Almighty Delta Tower?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Ace Almighty Delta Tower

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100022574
Status
Lapsed (registration period ended)
Builder
M/S. ACE ALMIGHTY
Location
Tathawade, Pune · 411033
Project type
Others
Registered on
7 Oct 2019
Completion date at registration
December 2023
Latest completion date
December 2023
Homes
52
Sold or booked
97%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Ace Almighty Delta Tower, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
F BUILDING DELTA TOWER AND SIGMA TOWER100%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • F BUILDING DELTA TOWER AND SIGMA TOWER: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ace Almighty Delta Tower every 1–2 months.

Ace Almighty Delta Tower: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Jhamtani Realty (a group of 11 linked companies) has 37 projects on MahaRERA since 2017, this one included. Of the 36 GharKundli has checked: 19 finished, 16 within the promised date and 3 needed more time (typically 6 months); 14 still being built, 2 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 5 projects.

Read Google reviews of Ace Almighty Delta Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ace Almighty Delta Tower: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ace Almighty Delta Tower

What is the possession date of Ace Almighty Delta Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ace Almighty Delta Tower in Tathawade, Pune is 30 December 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Ace Almighty Delta Tower?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ace Almighty Delta Tower's builder has filed on MahaRERA, the official one, is 30 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Ace Almighty Delta Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ace Almighty Delta Tower in Tathawade, Pune is P52100022574.

Is Ace Almighty Delta Tower registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ace Almighty Delta Tower is registered as P52100022574 and its status is "Lapsed (registration period ended)".

What is the current construction status of Ace Almighty Delta Tower? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Ace Almighty Delta Tower's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on F BUILDING DELTA TOWER AND SIGMA TOWER is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Ace Almighty Delta Tower have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Ace Almighty Delta Tower safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Ace Almighty Delta Tower is registered on MahaRERA as P52100022574, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ace Almighty Delta Tower?

Ace Almighty Delta Tower isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ace Almighty Delta Tower?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Ace Almighty Delta Tower: gharkundli.com/tools/property-cost-calculator

Has Ace Almighty Delta Tower received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Ace Almighty Delta Tower isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Ace Almighty Delta Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), Ace Almighty Delta Tower's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Ace Almighty Delta Tower uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Ace Almighty Delta Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ace Almighty Delta Tower's possession date changes?

The latest dates are on Ace Almighty Delta Tower's MahaRERA page (P52100022574). GharKundli's Kundli Watch sends a free WhatsApp update on Ace Almighty Delta Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ace Almighty Delta Tower have?

According to GharKundli's check of MahaRERA records (updated November 2026), Ace Almighty Delta Tower has one building filed: F BUILDING DELTA TOWER AND SIGMA TOWER with 14 floors and 77 units.

How big is the land of Ace Almighty Delta Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), Ace Almighty Delta Tower stands on 2,941 sq m of land (about 0.7 acres), with 2,196 sq m of sanctioned built-up area and 294 sq m of recreational open space.

What is the track record of Ace Almighty Delta Tower's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Jhamtani Realty (a group of 11 linked companies) has 37 projects on MahaRERA since 2017, this one included. Of the 36 GharKundli has checked: 19 finished, 16 within the promised date and 3 needed more time (typically 6 months); 14 still being built, 2 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Ace Almighty Delta Tower?

Google Maps has reviews of Ace Almighty Delta Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ace Almighty Delta Tower?

Ace Almighty Delta Tower by M/S. ACE ALMIGHTY (Jhamtani) is in Tathawade, Pune, pincode 411033 (near Wakad, Near Bhumkar Chowk, vinode nagar), Maharashtra, and is registered on MahaRERA as P52100022574, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 86/6 AND 86/7. GharKundli lists all 613 MahaRERA projects in Chinchwadgaon (411033).

How many flats are in Ace Almighty Delta Tower, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), Ace Almighty Delta Tower has 52 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.

When was Ace Almighty Delta Tower registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ace Almighty Delta Tower was registered on MahaRERA on 7 October 2019. GharKundli did not find a title report on the land on file there.

Does Ace Almighty Delta Tower have any legal issues or court cases?

No court cases are listed for Ace Almighty Delta Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Ace Almighty Delta Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S. ACE ALMIGHTY, the company Jhamtani files this project under, which has 2 other projects registered on MahaRERA.

Other projects in Chinchwadgaon (411033)

All 613 projects in Chinchwadgaon (411033) →

Other projects by M/S. ACE ALMIGHTY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.