by MEGHASWANA CONSTRUCTIONS · Talegaon Dabhade, Pune 410507Also near Talegaon G HRegistered on MahaRERA as “25 KARAT MOONSTONE”

What’s in the report? →

Possession date of Meghaswana 25 Karat Moonstone (MahaRERA P52100024150): 30 June 2023, and it has already passed. It has 50 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100024150. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100024150, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2023) has passed.

What do you want to know about Meghaswana 25 Karat Moonstone?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Meghaswana 25 Karat Moonstone

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100024150
Status
Lapsed (registration period ended)
Builder
MEGHASWANA CONSTRUCTIONS
Location
Talegaon Dabhade, Pune · 410507
Project type
Residential / Group Housing
Registered on
23 Jan 2020
Completion date at registration
June 2023
Latest completion date
June 2023
Homes
50
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of Meghaswana 25 Karat Moonstone, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
25 KARAT MOONSTONE100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Meghaswana 25 Karat Moonstone every 1–2 months.

Meghaswana 25 Karat Moonstone: buildings, flats and land, as filed on MahaRERA

  • Land: 1,709 sq m (about 0.4 acres) · sanctioned built-up 1,709 sq m
  • Land, as filed: PLOT NO 1 AND 2 CTS 2206
  • Map: Get directions

The builder’s record and reviews

Meghaswana Constructions (a group of 5 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 25 months); 4 still being built, 2 past the promised date (typically 46 months late); 3 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Meghaswana 25 Karat Moonstone →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Meghaswana 25 Karat Moonstone: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Meghaswana 25 Karat Moonstone

What is the possession date of Meghaswana 25 Karat Moonstone?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Meghaswana 25 Karat Moonstone in Talegaon Dabhade, Pune is 30 June 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Meghaswana 25 Karat Moonstone?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Meghaswana 25 Karat Moonstone's builder has filed on MahaRERA, the official one, is 30 June 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Meghaswana 25 Karat Moonstone?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Meghaswana 25 Karat Moonstone in Talegaon Dabhade, Pune is P52100024150.

Is Meghaswana 25 Karat Moonstone registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Meghaswana 25 Karat Moonstone is registered as P52100024150 and its status is "Lapsed (registration period ended)".

What is the current construction status of Meghaswana 25 Karat Moonstone? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Meghaswana 25 Karat Moonstone's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on 25 KARAT MOONSTONE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Meghaswana 25 Karat Moonstone have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Meghaswana 25 Karat Moonstone safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Meghaswana 25 Karat Moonstone is registered on MahaRERA as P52100024150, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Meghaswana 25 Karat Moonstone?

Meghaswana 25 Karat Moonstone isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Meghaswana 25 Karat Moonstone?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Meghaswana 25 Karat Moonstone: gharkundli.com/tools/property-cost-calculator

Has Meghaswana 25 Karat Moonstone received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Meghaswana 25 Karat Moonstone isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Meghaswana 25 Karat Moonstone?

According to GharKundli's check of MahaRERA records (updated November 2026), Meghaswana 25 Karat Moonstone's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Meghaswana 25 Karat Moonstone uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Meghaswana 25 Karat Moonstone was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Meghaswana 25 Karat Moonstone's possession date changes?

The latest dates are on Meghaswana 25 Karat Moonstone's MahaRERA page (P52100024150). GharKundli's Kundli Watch sends a free WhatsApp update on Meghaswana 25 Karat Moonstone every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Meghaswana 25 Karat Moonstone?

According to GharKundli's check of MahaRERA records (updated November 2026), Meghaswana 25 Karat Moonstone stands on 1,709 sq m of land (about 0.4 acres), with 1,709 sq m of sanctioned built-up area.

What is the track record of Meghaswana 25 Karat Moonstone's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Meghaswana Constructions (a group of 5 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 25 months); 4 still being built, 2 past the promised date (typically 46 months late); 3 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Meghaswana 25 Karat Moonstone?

Google Maps has reviews of Meghaswana 25 Karat Moonstone written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Meghaswana 25 Karat Moonstone?

Meghaswana 25 Karat Moonstone by MEGHASWANA CONSTRUCTIONS is in Talegaon Dabhade, Pune, pincode 410507 (near Talegaon G H), Maharashtra, and is registered on MahaRERA as P52100024150, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 1 AND 2 CTS 2206. GharKundli lists all 236 MahaRERA projects in Talegaon G H (410507).

How many flats are in Meghaswana 25 Karat Moonstone?

According to GharKundli's check of MahaRERA records (updated November 2026), Meghaswana 25 Karat Moonstone has 50 homes in 1 tower registered on MahaRERA.

When was Meghaswana 25 Karat Moonstone registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Meghaswana 25 Karat Moonstone was registered on MahaRERA on 23 January 2020. GharKundli did not find a title report on the land on file there.

Does Meghaswana 25 Karat Moonstone have any legal issues or court cases?

No court cases are listed for Meghaswana 25 Karat Moonstone on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Meghaswana 25 Karat Moonstone?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MEGHASWANA CONSTRUCTIONS, which has 7 other projects registered on MahaRERA.

Other projects in Talegaon G H (410507)

All 236 projects in Talegaon G H (410507) →

Other projects by MEGHASWANA CONSTRUCTIONS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.