AKSHAY RESIDENCY A BUILDING
by RAJENDRA RAMANLAL LUNAKD · Infotech Park (Hinjawadi), Pune
Possession date of AKSHAY RESIDENCY A BUILDING: 31 December 2022, moved from 30 June 2022 (6 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100029532. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2022) has passed.
What do you want to know about AKSHAY RESIDENCY A BUILDING?
How the possession date of AKSHAY RESIDENCY A BUILDING has moved
30 June 2022
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT52100012036)
Reason the builder gave MahaRERA:
“I am the promoter of abovementioned housing Project located at S. No.40/2 P, at Wakad, Tal. Mulshi, Dist. Pune-411057. The said project is consisting of one building. Due to water scarcity and unavoidable material procurement issues in the…” Read the full reason
“I am the promoter of abovementioned housing Project located at S. No.40/2 P, at Wakad, Tal. Mulshi, Dist. Pune-411057. The said project is consisting of one building. Due to water scarcity and unavoidable material procurement issues in the area, the Building could not be completed within the commited date of completion i.e. 30.06.2022 as provided by us in Affidavit Form-B for registration. Therefore, I humbly request to allow the me extension for completion of this project till 31.12.2022.”
Source: AKSHAY RESIDENCY A BUILDING’s extension records on MahaRERA (P52100029532), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AKSHAY RESIDENCY A BUILDING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100029532
- Status
- Lapsed (registration period ended)
- Builder
- RAJENDRA RAMANLAL LUNAKD
- Location
- Infotech Park (Hinjawadi), Pune · 411057
- Project type
- Residential / Group Housing
- Registered on
- 4 Jun 2021
- Completion date at registration
- June 2022
- Latest completion date
- December 2022
- Delay so far
- 6 months
- Homes
- 20
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of AKSHAY RESIDENCY A BUILDING, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A BUILDING | 100% | 100% | 100% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AKSHAY RESIDENCY A BUILDING every month.
AKSHAY RESIDENCY A BUILDING: buildings, flats and land, as filed on MahaRERA
- Buildings: A BUILDING (6 floors)
- Land: 751 sq m (about 0.2 acres) · sanctioned built-up 1,140 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AKSHAY RESIDENCY A BUILDING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AKSHAY RESIDENCY A BUILDING: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AKSHAY RESIDENCY A BUILDING
What is the possession date of AKSHAY RESIDENCY A BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for AKSHAY RESIDENCY A BUILDING in Infotech Park (Hinjawadi), Pune is 31 December 2022 — 6 months later than 30 June 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for AKSHAY RESIDENCY A BUILDING?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AKSHAY RESIDENCY A BUILDING's builder has filed on MahaRERA, the official one, is 31 December 2022, already 6 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AKSHAY RESIDENCY A BUILDING extended?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAY RESIDENCY A BUILDING's builder applied to MahaRERA to extend the completion date once: to 31 December 2022, giving the reason "I am the promoter of abovementioned housing Project located at S. No.40/2 P, at Wakad, Tal. Mulshi, Dist. Pune-411057. The said project is consisting of one building. Due to water scarcity and unavoidable material procurement issues in the area, the Building could not be completed within the commited date of completion i.e. 30.06.2022 as provided by us in Affidavit Form-B for registration. Therefore, I humbly request to allow the me extension for completion of this project till 31.12.2022.".
What is the RERA number of AKSHAY RESIDENCY A BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of AKSHAY RESIDENCY A BUILDING in Infotech Park (Hinjawadi), Pune is P52100029532.
Is AKSHAY RESIDENCY A BUILDING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAY RESIDENCY A BUILDING is registered as P52100029532 and its status is "Lapsed (registration period ended)".
What is the construction status of AKSHAY RESIDENCY A BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAY RESIDENCY A BUILDING's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on A BUILDING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does AKSHAY RESIDENCY A BUILDING have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is AKSHAY RESIDENCY A BUILDING safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAY RESIDENCY A BUILDING is registered on MahaRERA as P52100029532, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AKSHAY RESIDENCY A BUILDING's possession date changes?
The latest dates are on AKSHAY RESIDENCY A BUILDING's MahaRERA page (P52100029532). GharKundli's Kundli Watch sends a free WhatsApp update on AKSHAY RESIDENCY A BUILDING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AKSHAY RESIDENCY A BUILDING have?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAY RESIDENCY A BUILDING has one building filed: A BUILDING with 6 floors.
How big is the land of AKSHAY RESIDENCY A BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAY RESIDENCY A BUILDING stands on 751 sq m of land (about 0.2 acres), with 1,140 sq m of sanctioned built-up area.
Where can I read reviews of AKSHAY RESIDENCY A BUILDING?
Google Maps has reviews of AKSHAY RESIDENCY A BUILDING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AKSHAY RESIDENCY A BUILDING?
AKSHAY RESIDENCY A BUILDING by RAJENDRA RAMANLAL LUNAKD is in Infotech Park (Hinjawadi), Pune (pincode 411057), Maharashtra, and is registered on MahaRERA as P52100029532, per GharKundli's check of MahaRERA records.
How many homes are in AKSHAY RESIDENCY A BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAY RESIDENCY A BUILDING has 20 homes in 1 tower registered on MahaRERA.
When was AKSHAY RESIDENCY A BUILDING registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAY RESIDENCY A BUILDING was registered on MahaRERA on 4 June 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on AKSHAY RESIDENCY A BUILDING?
No court cases are listed for AKSHAY RESIDENCY A BUILDING on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of AKSHAY RESIDENCY A BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAJENDRA RAMANLAL LUNAKD, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of AKSHAY RESIDENCY A BUILDING
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 411057
- CASA IMPERIA
- Signature Park Phase - I
- Abharan
- Menlo Estella
- WESTGATE BUSINESS PARK
- SKY WORLD
- VYOMORA PHASE 1
- TRUSPACE PRIMA ALTIORA
Other projects by RAJENDRA RAMANLAL LUNAKD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.