Gprs Marathe Complex

by GPRS REALTY · Boisar, Palghar 401501Registered on MahaRERA as “MARATHE COMPLEX”

What’s in the report? →

Possession date of Gprs Marathe Complex (MahaRERA P99000024943): 30 April 2027. It has 38 homes, 58% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000024943, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P99000024943, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Gprs Marathe Complex?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Gprs Marathe Complex has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Gprs Marathe Complex’s extension records on MahaRERA (P99000024943), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Gprs Marathe Complex

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000024943
Status
Registered and active
Builder
GPRS REALTY
Location
Boisar, Palghar · 401501
Project type
Residential / Group Housing
Registered on
12 Mar 2020
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
38
Sold or booked
58%
Towers
14
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Gprs Marathe Complex, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1100%100%100%100%
BUILDING NO 2100%100%90%90%
BUILIDNG NO 3100%100%65%10%
BUILDING NO 4100%100%100%90%
BUILDING NO 5100%100%100%100%
BUILDING NO 6100%100%100%100%
BUILDING NO 7A100%100%90%90%
BUILDING NO 7B100%100%90%90%
BUILDING NO 7C100%100%90%90%
BUILDING NO 7D100%100%90%90%
BUILDING NO 7E100%100%90%90%
BUILDING NO 7F100%100%90%90%
BUILDING NO 7G100%100%100%90%
BUILDING NO 7H100%100%100%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gprs Marathe Complex every 1–2 months.

Gprs Marathe Complex: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 1 (6 floors) · BUILDING NO 2 (6 floors) · BUILIDNG NO 3 (4 floors) · BUILDING NO 4 (4 floors) · BUILDING NO 5 (4 floors) · BUILDING NO 6 (4 floors) · BUILDING NO 7A (5 floors) · BUILDING NO 7B (5 floors) · and 6 more
  • Car parking: 8 covered
  • Land: 8,460 sq m (about 2.1 acres) · sanctioned built-up 6,852 sq m · recreational space 846 sq m
  • Boundaries filed include: 9M WIDE APPROVED LAYOUT ROAD
  • Land, as filed: CTS NO 76/5
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Gprs Marathe Complex →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gprs Marathe Complex: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Gprs Marathe Complex

What is the possession date of Gprs Marathe Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Gprs Marathe Complex in Boisar, Palghar is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Gprs Marathe Complex?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gprs Marathe Complex's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Gprs Marathe Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Gprs Marathe Complex in Boisar, Palghar is P99000024943.

Is Gprs Marathe Complex registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Gprs Marathe Complex is registered as P99000024943 and its status is "Registered and active".

What is the current construction status of Gprs Marathe Complex? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Gprs Marathe Complex's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 14 towers. GharKundli's full report compares construction progress with the deadline.

Does Gprs Marathe Complex have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Gprs Marathe Complex safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Gprs Marathe Complex is registered on MahaRERA as P99000024943, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Gprs Marathe Complex?

Gprs Marathe Complex is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Gprs Marathe Complex?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Gprs Marathe Complex: gharkundli.com/tools/property-cost-calculator

Has Gprs Marathe Complex received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Gprs Marathe Complex is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Gprs Marathe Complex uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Gprs Marathe Complex was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Gprs Marathe Complex's possession date changes?

The latest dates are on Gprs Marathe Complex's MahaRERA page (P99000024943). GharKundli's Kundli Watch sends a free WhatsApp update on Gprs Marathe Complex every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gprs Marathe Complex have?

According to GharKundli's check of MahaRERA records (updated November 2026), Gprs Marathe Complex has 14 buildings filed: BUILDING NO 1 with 6 floors; BUILDING NO 2 with 6 floors; BUILIDNG NO 3 with 4 floors; BUILDING NO 4 with 4 floors; BUILDING NO 5 with 4 floors; BUILDING NO 6 with 4 floors; and 8 more.

How much parking does Gprs Marathe Complex have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 8 covered car parking spaces for Gprs Marathe Complex.

How big is the land of Gprs Marathe Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), Gprs Marathe Complex stands on 8,460 sq m of land (about 2.1 acres), with 6,852 sq m of sanctioned built-up area and 846 sq m of recreational open space.

What are the reviews of Gprs Marathe Complex?

Google Maps has reviews of Gprs Marathe Complex written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Gprs Marathe Complex?

Gprs Marathe Complex by GPRS REALTY is in Boisar, Palghar, pincode 401501, Maharashtra, and is registered on MahaRERA as P99000024943, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9M WIDE APPROVED LAYOUT ROAD. Its land is filed as CTS NO 76/5. GharKundli lists all 180 MahaRERA projects in Boisar (401501).

How many flats are in Gprs Marathe Complex, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), Gprs Marathe Complex has 38 homes in 14 towers registered on MahaRERA, and 58% of them are sold or booked.

When was Gprs Marathe Complex registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Gprs Marathe Complex was registered on MahaRERA on 12 March 2020. GharKundli did not find a title report on the land on file there.

Does Gprs Marathe Complex have any legal issues or court cases?

No court cases are listed for Gprs Marathe Complex on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Gprs Marathe Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GPRS REALTY, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in Boisar (401501)

All 180 projects in Boisar (401501) →

Other projects by GPRS REALTY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.