Prajyot Apartment
by M/s. Pratiksha Associates · Khodaram Baug, Palghar
Possession date of Prajyot Apartment: 30 June 2027, moved from 30 January 2024 (41 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000024447, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Prajyot Apartment?
How the possession date of Prajyot Apartment has moved
30 January 2024
Completion date given when the project was registered
29 January 2025
Extended at the builder's request (MahaRERA application EXT99000019827)
Reason the builder gave MahaRERA: “Due to material and labour issue”
30 September 2025
Extended at the builder's request (MahaRERA application EXT99000027542)
Reason the builder gave MahaRERA:
“1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Still the project progress was on track but in between due to some issues with our labour contra…” Read the full reason
“1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 3. But rest assured,now the is completed and OC will be obtained. 4. Hence,we request you to consider our request & justification & grant extension to our said project as it takes three to six months to obtain OC from Collector Office,Palghar after application. 5. Also,we are uploading the PERTChart/work completion s…”30 June 2027
Extended at the builder's request (MahaRERA application EA02012619251)
Reason the builder gave MahaRERA:
“1. The Project is already completed. 2. Also, we have applied for OC to Collector Palghar, the file was forwarded to Town Planning and Valuation Department. 3. ADTP (Assistant Director Town Planning) and Collector have asked for Environment…” Read the full reason
“1. The Project is already completed. 2. Also, we have applied for OC to Collector Palghar, the file was forwarded to Town Planning and Valuation Department. 3. ADTP (Assistant Director Town Planning) and Collector have asked for Environment Clearance based on BUA (Built-Up Area) of layout that is 37000 Sq. M. 4. We have been trying to explain the authority that obtaining EC for entire layout is not possible technically. Attaching the Layout Calculation Data Sheet by licensed Architect herewith 5. Hence the OC is stuck in some legal/compliance related issues which will take some time to get…”
Source: Prajyot Apartment’s extension records on MahaRERA (P99000024447), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Prajyot Apartment
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000024447
- Status
- Registered and active
- Builder
- M/s. Pratiksha Associates
- Location
- Khodaram Baug, Palghar · 401501
- Project type
- Residential / Group Housing
- Registered on
- 13 Feb 2020
- Completion date at registration
- January 2024
- Latest completion date
- June 2027
- Delay so far
- 41 months
- Homes
- 40
- Sold or booked
- 70%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Prajyot Apartment, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Prajyot Apartment | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Prajyot Apartment: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prajyot Apartment every month.
Prajyot Apartment: buildings, flats and land, as filed on MahaRERA
- Buildings: Prajyot Apartment (6 floors, 40 units)
- Car parking: 1 covered
- Land: 3,295 sq m (about 0.8 acres) · sanctioned built-up 3,116 sq m · recreational space 250 sq m
- Boundaries filed include: D J Nagar
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Prajyot Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Prajyot Apartment: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Prajyot Apartment
What is the possession date of Prajyot Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Prajyot Apartment in Khodaram Baug, Palghar is 30 June 2027 — 41 months later than 30 January 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Prajyot Apartment?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Prajyot Apartment's builder has filed on MahaRERA, the official one, is 30 June 2027, already 41 months later than the 30 January 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Prajyot Apartment extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Prajyot Apartment's builder applied to MahaRERA to extend the completion date 3 times: to 29 January 2025, giving the reason "Due to material and labour issue"; to 30 September 2025, giving the reason "1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 3. But rest assured,now the is completed and OC will be obtained. 4. Hence,we request you to consider our request & justification & grant extension to our said project as it takes three to six months to obtain OC from Collector Office,Palghar after application. 5. Also,we are uploading the PERTChart/work completion s…"; to 30 June 2027, giving the reason "1. The Project is already completed. 2. Also, we have applied for OC to Collector Palghar, the file was forwarded to Town Planning and Valuation Department. 3. ADTP (Assistant Director Town Planning) and Collector have asked for Environment Clearance based on BUA (Built-Up Area) of layout that is 37000 Sq. M. 4. We have been trying to explain the authority that obtaining EC for entire layout is not possible technically. Attaching the Layout Calculation Data Sheet by licensed Architect herewith 5. Hence the OC is stuck in some legal/compliance related issues which will take some time to get…".
What is the RERA number of Prajyot Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Prajyot Apartment in Khodaram Baug, Palghar is P99000024447.
Is Prajyot Apartment registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Prajyot Apartment is registered as P99000024447 and its status is "Registered and active".
What is the construction status of Prajyot Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Prajyot Apartment's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Prajyot Apartment is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Prajyot Apartment have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Prajyot Apartment safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Prajyot Apartment is registered on MahaRERA as P99000024447, its completion date has moved 41 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Prajyot Apartment's possession date changes?
The latest dates are on Prajyot Apartment's MahaRERA page (P99000024447). GharKundli's Kundli Watch sends a free WhatsApp update on Prajyot Apartment every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Prajyot Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), Prajyot Apartment has one building filed: Prajyot Apartment with 6 floors and 40 units.
How much parking does Prajyot Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for Prajyot Apartment.
How big is the land of Prajyot Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Prajyot Apartment stands on 3,295 sq m of land (about 0.8 acres), with 3,116 sq m of sanctioned built-up area and 250 sq m of recreational open space.
Where can I read reviews of Prajyot Apartment?
Google Maps has reviews of Prajyot Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Prajyot Apartment?
Prajyot Apartment by M/s. Pratiksha Associates is in Khodaram Baug, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000024447, per GharKundli's check of MahaRERA records. Its boundaries filed there include D J Nagar.
How many homes are in Prajyot Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Prajyot Apartment has 40 homes in 1 tower registered on MahaRERA, and 70% of them are sold or booked.
When was Prajyot Apartment registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Prajyot Apartment was registered on MahaRERA on 13 February 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on Prajyot Apartment?
No court cases are listed for Prajyot Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Prajyot Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. Pratiksha Associates.
Check it yourself on MahaRERA
- How to check the possession date of Prajyot Apartment
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Palghar
- Elite Residency
- Sunshine Complex
- Rubicon Shinde Heritage
- V SQUARE ARCADE
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.