SHREE GANESH COMPLEX

by MSD SHIVAY ENTERPRISE LLP · Mykhop, Palghar

Possession date of SHREE GANESH COMPLEX: 30 April 2027, moved from 7 September 2022 (51 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000025438, and currently active. Its completion date has moved from September 2022 to April 2027: 51 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHREE GANESH COMPLEX?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREE GANESH COMPLEX has moved

  1. 7 September 2022

    Completion date given when the project was registered

  2. 30 September 2024

    Extended at the builder's request (MahaRERA application EXT99000013530)

    Reason the builder gave MahaRERA: “Due to global pandemic Covid 19 lockdown the work could not be completed within the state time and therefore need further extension till 30-09-2024 to complete the work. thanking you”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT99000027134)

    Reason the builder gave MahaRERA:
    “Dear Sir, Due to Post Covid Effect and market slow down we are not able sale our inventory, till date we have manage to sale only 3 units therby causing the slow down of construction works. therefore, your goodeself is requested to provide…” Read the full reason“Dear Sir, Due to Post Covid Effect and market slow down we are not able sale our inventory, till date we have manage to sale only 3 units therby causing the slow down of construction works. therefore, your goodeself is requested to provide further time till 31-12-2026. Thanking you, yours faithfully”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHREE GANESH COMPLEX’s extension records on MahaRERA (P99000025438), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREE GANESH COMPLEX

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000025438
Status
Registered and active
Builder
MSD SHIVAY ENTERPRISE LLP
Location
Mykhop, Palghar · 401401
Project type
Residential / Group Housing
Registered on
30 May 2020
Completion date at registration
September 2022
Latest completion date
April 2027
Delay so far
51 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
30
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHREE GANESH COMPLEX, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE GANESH COMPLEX100%30%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE GANESH COMPLEX every month.

SHREE GANESH COMPLEX: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE GANESH COMPLEX (5 floors)
  • Land: 3,360 sq m (about 0.8 acres) · recreational space 399 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHREE GANESH COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREE GANESH COMPLEX: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREE GANESH COMPLEX

What is the possession date of SHREE GANESH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE GANESH COMPLEX in Mykhop, Palghar is 30 April 2027 — 51 months later than 7 September 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHREE GANESH COMPLEX?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE GANESH COMPLEX's builder has filed on MahaRERA, the official one, is 30 April 2027, already 51 months later than the 7 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREE GANESH COMPLEX extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE GANESH COMPLEX's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2024, giving the reason "Due to global pandemic Covid 19 lockdown the work could not be completed within the state time and therefore need further extension till 30-09-2024 to complete the work. thanking you"; to 31 December 2026, giving the reason "Dear Sir, Due to Post Covid Effect and market slow down we are not able sale our inventory, till date we have manage to sale only 3 units therby causing the slow down of construction works. therefore, your goodeself is requested to provide further time till 31-12-2026. Thanking you, yours faithfully". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHREE GANESH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREE GANESH COMPLEX in Mykhop, Palghar is P99000025438.

Is SHREE GANESH COMPLEX registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE GANESH COMPLEX is registered as P99000025438 and its status is "Registered and active".

What is the construction status of SHREE GANESH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE GANESH COMPLEX's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE GANESH COMPLEX is 30% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does SHREE GANESH COMPLEX have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHREE GANESH COMPLEX safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE GANESH COMPLEX is registered on MahaRERA as P99000025438, its completion date has moved 51 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREE GANESH COMPLEX's possession date changes?

The latest dates are on SHREE GANESH COMPLEX's MahaRERA page (P99000025438). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE GANESH COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREE GANESH COMPLEX have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE GANESH COMPLEX has one building filed: SHREE GANESH COMPLEX with 5 floors.

How big is the land of SHREE GANESH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE GANESH COMPLEX stands on 3,360 sq m of land (about 0.8 acres) and 399 sq m of recreational open space.

Where can I read reviews of SHREE GANESH COMPLEX?

Google Maps has reviews of SHREE GANESH COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREE GANESH COMPLEX?

SHREE GANESH COMPLEX by MSD SHIVAY ENTERPRISE LLP is in Mykhop, Palghar (pincode 401401), Maharashtra, and is registered on MahaRERA as P99000025438, per GharKundli's check of MahaRERA records.

How many homes are in SHREE GANESH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE GANESH COMPLEX has 30 homes in 1 tower registered on MahaRERA.

When was SHREE GANESH COMPLEX registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE GANESH COMPLEX was registered on MahaRERA on 30 May 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREE GANESH COMPLEX?

No court cases are listed for SHREE GANESH COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHREE GANESH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MSD SHIVAY ENTERPRISE LLP.

All projects with possession due in 2027 in Palghar →

Other projects in Palghar

All 15 projects in Kelwa (401401) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.