Possession: Ganesh Apartment (MahaRERA P99000026221) is marked completed on MahaRERA. It has 9 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000026221. Status: Completed.

Source: MahaRERA website — records for P99000026221, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Ganesh Apartment?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ganesh Apartment has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 31 January 2022

    Extended at the builder's request (MahaRERA application EXT99000010562)

    Reason the builder gave MahaRERA:
    “To MahaRERA, I Mr. Vishnu Govind Patil proprietor of M/s. Ganesh Developers do hereby apply for extension of project expiry date upto 31/01/2022. I was unable to complete the project due to lockdown imposed several times due to panademic CO…” Read the full reason“To MahaRERA, I Mr. Vishnu Govind Patil proprietor of M/s. Ganesh Developers do hereby apply for extension of project expiry date upto 31/01/2022. I was unable to complete the project due to lockdown imposed several times due to panademic COVID-19. Kindly consider my request for the application of extension of Project Date.”
  3. 31 July 2022

    Revised completion date on MahaRERA

Source: Ganesh Apartment’s extension records on MahaRERA (P99000026221), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ganesh Apartment

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000026221
Status
Completed
Builder
VISHNU GOVIND PATIL
Location
Saphale West, Palghar · 401404
Project type
Residential / Group Housing
Registered on
30 Aug 2020
Completion date at registration
June 2021
Latest completion date
July 2022
Delay so far
13 months
Homes
9
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Ganesh Apartment, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GANESH APARTMENT100%100%100%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ganesh Apartment every 1–2 months.

Ganesh Apartment: buildings, flats and land, as filed on MahaRERA

  • Buildings: GANESH APARTMENT (4 floors)
  • Land: 314 sq m (about 0.1 acres)
  • Land, as filed: GUT NO. 182/8, PLOT NO. 10
  • Map: Get directions

The builder’s record and reviews

Vishnu Govind Patil has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 7 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Ganesh Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ganesh Apartment: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ganesh Apartment

What is the possession date of Ganesh Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ganesh Apartment in Saphale West, Palghar is 31 July 2022 — 13 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Ganesh Apartment?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ganesh Apartment's builder has filed on MahaRERA, the official one, is 31 July 2022, already 13 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ganesh Apartment extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment's builder applied to MahaRERA to extend the completion date once: to 31 January 2022, giving the reason "To MahaRERA, I Mr. Vishnu Govind Patil proprietor of M/s. Ganesh Developers do hereby apply for extension of project expiry date upto 31/01/2022. I was unable to complete the project due to lockdown imposed several times due to panademic COVID-19. Kindly consider my request for the application of extension of Project Date.".

What is the RERA number of Ganesh Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ganesh Apartment in Saphale West, Palghar is P99000026221.

Is Ganesh Apartment registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment is registered as P99000026221 and its status is "Completed".

What is the current construction status of Ganesh Apartment? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment's status on MahaRERA is "Completed". As filed by the builder, slab work on GANESH APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Ganesh Apartment have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Ganesh Apartment safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment is registered on MahaRERA as P99000026221, its MahaRERA status is "Completed", its completion date has moved 13 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ganesh Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Ganesh Apartment?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Ganesh Apartment: gharkundli.com/tools/property-cost-calculator

Has Ganesh Apartment received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Ganesh Apartment completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment is marked completed on MahaRERA, and the completion date filed there is 31 July 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Ganesh Apartment uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Ganesh Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ganesh Apartment's possession date changes?

The latest dates are on Ganesh Apartment's MahaRERA page (P99000026221). GharKundli's Kundli Watch sends a free WhatsApp update on Ganesh Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ganesh Apartment have?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment has one building filed: GANESH APARTMENT with 4 floors.

How big is the land of Ganesh Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment stands on 314 sq m of land (about 0.1 acres).

What is the track record of Ganesh Apartment's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishnu Govind Patil has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 7 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Ganesh Apartment?

Google Maps has reviews of Ganesh Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ganesh Apartment?

Ganesh Apartment by VISHNU GOVIND PATIL is in Saphale West, Palghar, pincode 401404, Maharashtra, and is registered on MahaRERA as P99000026221, per GharKundli's check of MahaRERA records. Its land is filed as GUT NO. 182/8, PLOT NO. 10. GharKundli lists all 621 MahaRERA projects in Palghar (401404).

How many flats are in Ganesh Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment has 9 homes in 1 tower registered on MahaRERA.

When was Ganesh Apartment registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ganesh Apartment was registered on MahaRERA on 30 August 2020. GharKundli did not find a title report on the land on file there.

Does Ganesh Apartment have any legal issues or court cases?

No court cases are listed for Ganesh Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Ganesh Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VISHNU GOVIND PATIL, which has 1 other project registered on MahaRERA.

Other projects in Palghar (401404)

All 621 projects in Palghar (401404) →

Other projects by VISHNU GOVIND PATIL

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.