EELA Phase-III
by M/s. Siddhashila Developers · Punawale, PuneAlso near Chinchwadgaon
Possession: EELA Phase-III is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100024257. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about EELA Phase-III?
How the possession date of EELA Phase-III has moved
30 June 2022
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT52100012123)
Reason the builder gave MahaRERA:
“We could not be able to complete the remaining floors of the said project in time due to following reasons. (i) Covid 19 pandemic has impacted all sectors of country including Real Estates from time to time. Covid 19 has affected the Sales…” Read the full reason
“We could not be able to complete the remaining floors of the said project in time due to following reasons. (i) Covid 19 pandemic has impacted all sectors of country including Real Estates from time to time. Covid 19 has affected the Sales in real estate sector immensely. (ii) All the units in the said commercial building are built on the basis of requirements of prospective client/purchaser/s. presently all the Units in 2nd floor and above are unsold and in the bare shell form. On the basis of requirements of prospective client/purchaser/s same shall be converted to the furnished product.…”31 December 2023
Extended at the builder's request (MahaRERA application EXT52100018004)
Reason the builder gave MahaRERA:
“1. We are promoters of Eela Phase III- constructed by us on the land bearing S No. 34/2/1, Punawale. 2. Said project is registered on the Maharera Web Portal, under ReRA Act 2016 and rules made thereunder as on 08/09/2021 and is bearing pro…” Read the full reason
“1. We are promoters of Eela Phase III- constructed by us on the land bearing S No. 34/2/1, Punawale. 2. Said project is registered on the Maharera Web Portal, under ReRA Act 2016 and rules made thereunder as on 08/09/2021 and is bearing project registration no. as (P52100024257). 3. That said 1st registration was valid from 29/01/2020 till 30/06/2022. 4. Thereafter due to Covid, ReRA registration of said project was further extended till 31/12/2022. 5. We have received completion certificate in respect of said Project as on 29/03/2023 and as such we were in the process of taking further ext…”
Source: EELA Phase-III’s extension records on MahaRERA (P52100024257), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on EELA Phase-III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100024257
- Status
- Completed
- Builder
- M/s. Siddhashila Developers
- Location
- Punawale, Pune · 411033
- Project type
- Commercial
- Registered on
- 29 Jan 2020
- Completion date at registration
- June 2022
- Latest completion date
- December 2023
- Delay so far
- 18 months
- Homes
- 68
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of EELA Phase-III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| THEIA BUSINESS PARK | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on EELA Phase-III every month.
EELA Phase-III: buildings, flats and land, as filed on MahaRERA
- Buildings: THEIA BUSINESS PARK (10 floors)
- Land: 4,261 sq m (about 1.1 acres) · sanctioned built-up 4,305 sq m · recreational space 2,324 sq m
- Boundaries filed include: Marunji Road
The builder’s record and reviews
Siddhashila Developers (a group of 7 linked companies) has 10 projects on MahaRERA since 2020, this one included. Of the 7 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 5 months); 4 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA.
Read Google reviews of EELA Phase-III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
EELA Phase-III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about EELA Phase-III
What is the possession date of EELA Phase-III?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for EELA Phase-III in Punawale, Pune is 31 December 2023 — 18 months later than 30 June 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for EELA Phase-III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date EELA Phase-III's builder has filed on MahaRERA, the official one, is 31 December 2023, already 18 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of EELA Phase-III extended?
According to GharKundli's check of MahaRERA records (updated November 2026), EELA Phase-III's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2022, giving the reason "We could not be able to complete the remaining floors of the said project in time due to following reasons. (i) Covid 19 pandemic has impacted all sectors of country including Real Estates from time to time. Covid 19 has affected the Sales in real estate sector immensely. (ii) All the units in the said commercial building are built on the basis of requirements of prospective client/purchaser/s. presently all the Units in 2nd floor and above are unsold and in the bare shell form. On the basis of requirements of prospective client/purchaser/s same shall be converted to the furnished product.…"; to 31 December 2023, giving the reason "1. We are promoters of Eela Phase III- constructed by us on the land bearing S No. 34/2/1, Punawale. 2. Said project is registered on the Maharera Web Portal, under ReRA Act 2016 and rules made thereunder as on 08/09/2021 and is bearing project registration no. as (P52100024257). 3. That said 1st registration was valid from 29/01/2020 till 30/06/2022. 4. Thereafter due to Covid, ReRA registration of said project was further extended till 31/12/2022. 5. We have received completion certificate in respect of said Project as on 29/03/2023 and as such we were in the process of taking further ext…".
What is the RERA number of EELA Phase-III?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of EELA Phase-III in Punawale, Pune is P52100024257.
Is EELA Phase-III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), EELA Phase-III is registered as P52100024257 and its status is "Completed".
What is the construction status of EELA Phase-III?
According to GharKundli's check of MahaRERA records (updated November 2026), EELA Phase-III's status on MahaRERA is "Completed". As filed by the builder, slab work on THEIA BUSINESS PARK is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does EELA Phase-III have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is EELA Phase-III safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), EELA Phase-III is registered on MahaRERA as P52100024257, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if EELA Phase-III's possession date changes?
The latest dates are on EELA Phase-III's MahaRERA page (P52100024257). GharKundli's Kundli Watch sends a free WhatsApp update on EELA Phase-III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does EELA Phase-III have?
According to GharKundli's check of MahaRERA records (updated November 2026), EELA Phase-III has one building filed: THEIA BUSINESS PARK with 10 floors.
How big is the land of EELA Phase-III?
According to GharKundli's check of MahaRERA records (updated November 2026), EELA Phase-III stands on 4,261 sq m of land (about 1.1 acres), with 4,305 sq m of sanctioned built-up area and 2,324 sq m of recreational open space.
What is the track record of EELA Phase-III's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Siddhashila Developers (a group of 7 linked companies) has 10 projects on MahaRERA since 2020, this one included. Of the 7 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 5 months); 4 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of EELA Phase-III?
Google Maps has reviews of EELA Phase-III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is EELA Phase-III?
EELA Phase-III by M/s. Siddhashila Developers is in Punawale, Pune (pincode 411033), near Chinchwadgaon, Maharashtra, and is registered on MahaRERA as P52100024257, per GharKundli's check of MahaRERA records. Its boundaries filed there include Marunji Road.
How many homes are in EELA Phase-III?
According to GharKundli's check of MahaRERA records (updated November 2026), EELA Phase-III has 68 homes in 1 tower registered on MahaRERA.
When was EELA Phase-III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), EELA Phase-III was registered on MahaRERA on 29 January 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on EELA Phase-III?
No court cases are listed for EELA Phase-III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of EELA Phase-III?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/s. Siddhashila Developers, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of EELA Phase-III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 411033
- GANGA AMBER PH II
- AISHWARYAM INSIGNIA
- RAMAN STELLAR
- Nirman Serenopolis
- ROHAN HARITA PHASE 4
- Millennium Samriddhi
- KOHINOOR UPTOWN AVENUE
- West World
Other projects by M/s. Siddhashila Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.