PRITHVI ANAND KUBER COMPLEX

by Prithvi Anand Housing and Land Developers · Near St. John College, PalgharAlso near Vevoor

Possession date of PRITHVI ANAND KUBER COMPLEX: 31 July 2026, moved from 30 June 2025 (13 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P99000025647. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about PRITHVI ANAND KUBER COMPLEX?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PRITHVI ANAND KUBER COMPLEX has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 31 July 2026

    Extended at the builder's request (MahaRERA application EA28072502215)

    Reason the builder gave MahaRERA:
    “We respectfully request an extension of the RERA registration for our project, currently valid until 30/06/2025, to a revised completion date of 31/07/2026. We had already obtained a part Occupancy Certificate for fully completed Building N…” Read the full reason“We respectfully request an extension of the RERA registration for our project, currently valid until 30/06/2025, to a revised completion date of 31/07/2026. We had already obtained a part Occupancy Certificate for fully completed Building No.3 on dated 15/12/2023, the copy of which is attached with this application. Further we are also in the submission process of an application for Occupancy Certificate to Palghar Municipal Council for our completed Building No.1 & 2, for time being we are attaching a copy of 100% Architect Completion certificate for both the building, please find the same…”

Source: PRITHVI ANAND KUBER COMPLEX’s extension records on MahaRERA (P99000025647), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PRITHVI ANAND KUBER COMPLEX

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000025647
Status
Lapsed (registration period ended)
Builder
Prithvi Anand Housing and Land Developers
Location
Near St. John College, Palghar · 401404
Project type
Residential / Group Housing
Registered on
1 Jul 2020
Completion date at registration
June 2025
Latest completion date
July 2026
Delay so far
13 months
Homes
357
Sold or booked
100%
Towers
4
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of PRITHVI ANAND KUBER COMPLEX, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building no 1 Prithvi Anand Nav100%100%100%100%
Building no 2 Prithvi Anand Hans100%100%100%100%
Building no 3 Prithvi Anand PATI100%100%100%100%
Building No 4 Type G100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Building no 1 Prithvi Anand Nav: covers 12 floors
  • Building no 2 Prithvi Anand Hans: covers 10 floors
  • Building no 3 Prithvi Anand PATI: covers 8 floors
  • Building No 4 Type G: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRITHVI ANAND KUBER COMPLEX every month.

PRITHVI ANAND KUBER COMPLEX: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building no 1 Prithvi Anand Nav (12 floors, 146 units) · Building no 2 Prithvi Anand Hans (10 floors, 123 units) · Building no 3 Prithvi Anand PATI (8 floors, 97 units) · Building No 4 Type G (6 floors, 42 units)
  • Land: 13,680 sq m (about 3.4 acres) · sanctioned built-up 19,969 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Prithvi Anand Housing And Land Developers has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 14 months); 1 still being built, none past the promised date yet; 1 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of PRITHVI ANAND KUBER COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PRITHVI ANAND KUBER COMPLEX: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PRITHVI ANAND KUBER COMPLEX

What is the possession date of PRITHVI ANAND KUBER COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PRITHVI ANAND KUBER COMPLEX in Near St. John College, Palghar is 31 July 2026 — 13 months later than 30 June 2025, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PRITHVI ANAND KUBER COMPLEX?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PRITHVI ANAND KUBER COMPLEX's builder has filed on MahaRERA, the official one, is 31 July 2026, already 13 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PRITHVI ANAND KUBER COMPLEX extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PRITHVI ANAND KUBER COMPLEX's builder applied to MahaRERA to extend the completion date once: to 31 July 2026, giving the reason "We respectfully request an extension of the RERA registration for our project, currently valid until 30/06/2025, to a revised completion date of 31/07/2026. We had already obtained a part Occupancy Certificate for fully completed Building No.3 on dated 15/12/2023, the copy of which is attached with this application. Further we are also in the submission process of an application for Occupancy Certificate to Palghar Municipal Council for our completed Building No.1 & 2, for time being we are attaching a copy of 100% Architect Completion certificate for both the building, please find the same…".

What is the RERA number of PRITHVI ANAND KUBER COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PRITHVI ANAND KUBER COMPLEX in Near St. John College, Palghar is P99000025647.

Is PRITHVI ANAND KUBER COMPLEX registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PRITHVI ANAND KUBER COMPLEX is registered as P99000025647 and its status is "Lapsed (registration period ended)".

What is the construction status of PRITHVI ANAND KUBER COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), PRITHVI ANAND KUBER COMPLEX's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does PRITHVI ANAND KUBER COMPLEX have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PRITHVI ANAND KUBER COMPLEX safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PRITHVI ANAND KUBER COMPLEX is registered on MahaRERA as P99000025647, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 13 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does PRITHVI ANAND KUBER COMPLEX have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Prithvi Anand Kuber Complex Phase 2 (P99000052067, possession 31 Dec 2027). Check that your agreement names the registration of your own wing.

How can I get updates if PRITHVI ANAND KUBER COMPLEX's possession date changes?

The latest dates are on PRITHVI ANAND KUBER COMPLEX's MahaRERA page (P99000025647). GharKundli's Kundli Watch sends a free WhatsApp update on PRITHVI ANAND KUBER COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PRITHVI ANAND KUBER COMPLEX have?

According to GharKundli's check of MahaRERA records (updated October 2026), PRITHVI ANAND KUBER COMPLEX has 4 buildings filed: Building no 1 Prithvi Anand Nav with 12 floors and 146 units; Building no 2 Prithvi Anand Hans with 10 floors and 123 units; Building no 3 Prithvi Anand PATI with 8 floors and 97 units; Building No 4 Type G with 6 floors and 42 units.

How big is the land of PRITHVI ANAND KUBER COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), PRITHVI ANAND KUBER COMPLEX stands on 13,680 sq m of land (about 3.4 acres), with 19,969 sq m of sanctioned built-up area.

What is the track record of PRITHVI ANAND KUBER COMPLEX's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Prithvi Anand Housing And Land Developers has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 14 months); 1 still being built, none past the promised date yet; 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of PRITHVI ANAND KUBER COMPLEX?

Google Maps has reviews of PRITHVI ANAND KUBER COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PRITHVI ANAND KUBER COMPLEX?

PRITHVI ANAND KUBER COMPLEX by Prithvi Anand Housing and Land Developers is in Near St. John College, Palghar (pincode 401404), near Vevoor, Maharashtra, and is registered on MahaRERA as P99000025647, per GharKundli's check of MahaRERA records.

How many homes are in PRITHVI ANAND KUBER COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), PRITHVI ANAND KUBER COMPLEX has 357 homes in 4 towers registered on MahaRERA, and 100% of them are sold or booked.

When was PRITHVI ANAND KUBER COMPLEX registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PRITHVI ANAND KUBER COMPLEX was registered on MahaRERA on 1 July 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on PRITHVI ANAND KUBER COMPLEX?

No court cases are listed for PRITHVI ANAND KUBER COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of PRITHVI ANAND KUBER COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Prithvi Anand Housing and Land Developers, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2026 in Palghar →

Other projects in Palghar

All 419 projects in Palghar (401404) →

Other projects by Prithvi Anand Housing and Land Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.