ANANT APARTMENT
by ANANTA DEVELOPERS · Allyali, Palghar
Possession date of ANANT APARTMENT: 30 April 2027, moved from 30 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000026731, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ANANT APARTMENT?
How the possession date of ANANT APARTMENT has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT99000013985)
Reason the builder gave MahaRERA: “DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON TIME”
31 December 2026
Extended at the builder's request (MahaRERA application EXT99000022966)
Reason the builder gave MahaRERA: “DUE TO COVID AND LOCKDOWN PROJECT COULD NOT BE COMPLETED ON TIME”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ANANT APARTMENT’s extension records on MahaRERA (P99000026731), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ANANT APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000026731
- Status
- Registered and active
- Builder
- ANANTA DEVELOPERS
- Location
- Allyali, Palghar · 401404
- Project type
- Others
- Registered on
- 21 Oct 2020
- Completion date at registration
- December 2022
- Latest completion date
- April 2027
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Sold or booked
- 53%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of ANANT APARTMENT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ANANT APARTMENT A WING | 100% | 90% | 90% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- ANANT APARTMENT A WING: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANANT APARTMENT every month.
ANANT APARTMENT: buildings, flats and land, as filed on MahaRERA
- Buildings: ANANT APARTMENT A WING (6 floors, 34 units)
- Land: 920 sq m (about 0.2 acres) · sanctioned built-up 920 sq m · recreational space 92 sq m
The builder’s record and reviews
Ananta Developers has 3 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 36 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of ANANT APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ANANT APARTMENT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ANANT APARTMENT
What is the possession date of ANANT APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANANT APARTMENT in Allyali, Palghar is 30 April 2027 — 48 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ANANT APARTMENT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ANANT APARTMENT's builder has filed on MahaRERA, the official one, is 30 April 2027, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ANANT APARTMENT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANT APARTMENT's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2023, giving the reason "DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON TIME"; to 31 December 2026, giving the reason "DUE TO COVID AND LOCKDOWN PROJECT COULD NOT BE COMPLETED ON TIME". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ANANT APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ANANT APARTMENT in Allyali, Palghar is P99000026731.
Is ANANT APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANT APARTMENT is registered as P99000026731 and its status is "Registered and active".
What is the construction status of ANANT APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANT APARTMENT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ANANT APARTMENT A WING is 90% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does ANANT APARTMENT have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ANANT APARTMENT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANT APARTMENT is registered on MahaRERA as P99000026731, its completion date has moved 48 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ANANT APARTMENT's possession date changes?
The latest dates are on ANANT APARTMENT's MahaRERA page (P99000026731). GharKundli's Kundli Watch sends a free WhatsApp update on ANANT APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ANANT APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANT APARTMENT has one building filed: ANANT APARTMENT A WING with 6 floors and 34 units.
How big is the land of ANANT APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANT APARTMENT stands on 920 sq m of land (about 0.2 acres), with 920 sq m of sanctioned built-up area and 92 sq m of recreational open space.
What is the track record of ANANT APARTMENT's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ananta Developers has 3 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 36 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ANANT APARTMENT?
Google Maps has reviews of ANANT APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ANANT APARTMENT?
ANANT APARTMENT by ANANTA DEVELOPERS is in Allyali, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000026731, per GharKundli's check of MahaRERA records.
How many homes are in ANANT APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANT APARTMENT has 30 homes in 1 tower registered on MahaRERA, and 53% of them are sold or booked.
When was ANANT APARTMENT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANT APARTMENT was registered on MahaRERA on 21 October 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on ANANT APARTMENT?
No court cases are listed for ANANT APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ANANT APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ANANTA DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ANANT APARTMENT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Palghar
- Elite Residency
- Sunshine Complex
- V SQUARE ARCADE
- Rubicon Shinde Heritage
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Other projects by ANANTA DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.