PARASNATH NAGARI

by SHREENATH ENTERPRISES · Umroli, Palghar

Possession date of PARASNATH NAGARI: 30 September 2027, moved from 30 March 2026 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000026724, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about PARASNATH NAGARI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PARASNATH NAGARI has moved

  1. 30 March 2026

    Completion date given when the project was registered

  2. 30 September 2027

    Extended at the builder's request (MahaRERA application EA06052620850)

    Reason the builder gave MahaRERA:
    “We, Shreenath Enterprises, hereby declare the following with respect to the project “PARASNATH NAGARI” bearing registration number P99000026724 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have…” Read the full reason“We, Shreenath Enterprises, hereby declare the following with respect to the project “PARASNATH NAGARI” bearing registration number P99000026724 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the all the buildings. Currently, we are undertaking the Pending finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for t…”

Source: PARASNATH NAGARI’s extension records on MahaRERA (P99000026724), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PARASNATH NAGARI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000026724
Status
Registered and active
Builder
SHREENATH ENTERPRISES
Location
Umroli, Palghar · 401404
Project type
Residential / Group Housing
Registered on
21 Oct 2020
Completion date at registration
March 2026
Latest completion date
September 2027
Delay so far
18 months
Homes
54
Sold or booked
56%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
11

Construction progress of PARASNATH NAGARI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PARASNATH NAGARI WING - A100%100%100%0%
PARASNATH NAGARI WING - B100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • PARASNATH NAGARI WING - A: covers 4 floors
  • PARASNATH NAGARI WING - B: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARASNATH NAGARI every month.

PARASNATH NAGARI: buildings, flats and land, as filed on MahaRERA

  • Buildings: PARASNATH NAGARI WING - A (7 floors, 28 units) · PARASNATH NAGARI WING - B (7 floors, 34 units)
  • Land: 1,844 sq m (about 0.5 acres) · sanctioned built-up 2,455 sq m · recreational space 495 sq m

The builder’s record and reviews

Shreenath Enterprises (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 still being built, 3 past the promised date (typically 39 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of PARASNATH NAGARI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PARASNATH NAGARI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PARASNATH NAGARI

What is the possession date of PARASNATH NAGARI?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PARASNATH NAGARI in Umroli, Palghar is 30 September 2027 — 18 months later than 30 March 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for PARASNATH NAGARI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PARASNATH NAGARI's builder has filed on MahaRERA, the official one, is 30 September 2027, already 18 months later than the 30 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PARASNATH NAGARI extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PARASNATH NAGARI's builder applied to MahaRERA to extend the completion date once: to 30 September 2027, giving the reason "We, Shreenath Enterprises, hereby declare the following with respect to the project “PARASNATH NAGARI” bearing registration number P99000026724 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the all the buildings. Currently, we are undertaking the Pending finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for t…".

What is the RERA number of PARASNATH NAGARI?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PARASNATH NAGARI in Umroli, Palghar is P99000026724.

Is PARASNATH NAGARI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PARASNATH NAGARI is registered as P99000026724 and its status is "Registered and active".

What is the construction status of PARASNATH NAGARI?

According to GharKundli's check of MahaRERA records (updated October 2026), PARASNATH NAGARI's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does PARASNATH NAGARI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is PARASNATH NAGARI safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PARASNATH NAGARI is registered on MahaRERA as P99000026724, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does PARASNATH NAGARI have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: PARASNATH NAGARI (P99000027533, possession 30 Apr 2028). Check that your agreement names the registration of your own wing.

How can I get updates if PARASNATH NAGARI's possession date changes?

The latest dates are on PARASNATH NAGARI's MahaRERA page (P99000026724). GharKundli's Kundli Watch sends a free WhatsApp update on PARASNATH NAGARI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PARASNATH NAGARI have?

According to GharKundli's check of MahaRERA records (updated October 2026), PARASNATH NAGARI has 2 buildings filed: PARASNATH NAGARI WING - A with 7 floors and 28 units; PARASNATH NAGARI WING - B with 7 floors and 34 units.

How big is the land of PARASNATH NAGARI?

According to GharKundli's check of MahaRERA records (updated October 2026), PARASNATH NAGARI stands on 1,844 sq m of land (about 0.5 acres), with 2,455 sq m of sanctioned built-up area and 495 sq m of recreational open space.

What is the track record of PARASNATH NAGARI's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Enterprises (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 still being built, 3 past the promised date (typically 39 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of PARASNATH NAGARI?

Google Maps has reviews of PARASNATH NAGARI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PARASNATH NAGARI?

PARASNATH NAGARI by SHREENATH ENTERPRISES is in Umroli, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000026724, per GharKundli's check of MahaRERA records.

How many homes are in PARASNATH NAGARI?

According to GharKundli's check of MahaRERA records (updated October 2026), PARASNATH NAGARI has 54 homes in 2 towers registered on MahaRERA, and 56% of them are sold or booked.

When was PARASNATH NAGARI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PARASNATH NAGARI was registered on MahaRERA on 21 October 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on PARASNATH NAGARI?

No court cases are listed for PARASNATH NAGARI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of PARASNATH NAGARI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREENATH ENTERPRISES, which has 11 other projects registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in Umroli

All 384 projects in Palghar (401404) →

Other projects by SHREENATH ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.