PARAMOUNT ENCLAVE PHASE 02
by GAJANAN BUILDERS & DEVELOPERS · Palghar
Possession date of PARAMOUNT ENCLAVE PHASE 02: 30 April 2027, moved from 31 May 2024 (31 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000029540, and currently active. Its completion date has moved from May 2024 to April 2027: 31 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PARAMOUNT ENCLAVE PHASE 02?
How the possession date of PARAMOUNT ENCLAVE PHASE 02 has moved
31 May 2024
Completion date given when the project was registered
31 May 2025
Extended at the builder's request (MahaRERA application EXT99000023026)
Reason the builder gave MahaRERA: “DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON TIME”
31 December 2026
Extended at the builder's request (MahaRERA application EA18092502632)
Reason the builder gave MahaRERA: “due to some unavoidable reasons project could not be completed on time”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: PARAMOUNT ENCLAVE PHASE 02’s extension records on MahaRERA (P99000029540), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PARAMOUNT ENCLAVE PHASE 02
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000029540
- Status
- Registered and active
- Builder
- GAJANAN BUILDERS & DEVELOPERS
- Location
- Palghar · 401404
- Project type
- Others
- Registered on
- 4 Jun 2021
- Completion date at registration
- May 2024
- Latest completion date
- April 2027
- Delay so far
- 31 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 34
- Sold or booked
- 47%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of PARAMOUNT ENCLAVE PHASE 02, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 2 WING B TYPE D1 | 100% | 100% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 2 WING B TYPE D1: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARAMOUNT ENCLAVE PHASE 02 every month.
PARAMOUNT ENCLAVE PHASE 02: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 2 WING B TYPE D1 (6 floors, 43 units)
- Land: 1,288 sq m (about 0.3 acres) · sanctioned built-up 1,288 sq m · recreational space 129 sq m
The builder’s record and reviews
Gajanan Builders & Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 53 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of PARAMOUNT ENCLAVE PHASE 02 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PARAMOUNT ENCLAVE PHASE 02: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PARAMOUNT ENCLAVE PHASE 02
What is the possession date of PARAMOUNT ENCLAVE PHASE 02?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PARAMOUNT ENCLAVE PHASE 02 in Palghar is 30 April 2027 — 31 months later than 31 May 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for PARAMOUNT ENCLAVE PHASE 02?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PARAMOUNT ENCLAVE PHASE 02's builder has filed on MahaRERA, the official one, is 30 April 2027, already 31 months later than the 31 May 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PARAMOUNT ENCLAVE PHASE 02 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE PHASE 02's builder applied to MahaRERA to extend the completion date 2 times: to 31 May 2025, giving the reason "DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON TIME"; to 31 December 2026, giving the reason "due to some unavoidable reasons project could not be completed on time". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of PARAMOUNT ENCLAVE PHASE 02?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PARAMOUNT ENCLAVE PHASE 02 in Palghar is P99000029540.
Is PARAMOUNT ENCLAVE PHASE 02 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE PHASE 02 is registered as P99000029540 and its status is "Registered and active".
What is the construction status of PARAMOUNT ENCLAVE PHASE 02?
According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE PHASE 02's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 2 WING B TYPE D1 is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does PARAMOUNT ENCLAVE PHASE 02 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PARAMOUNT ENCLAVE PHASE 02 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE PHASE 02 is registered on MahaRERA as P99000029540, its completion date has moved 31 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PARAMOUNT ENCLAVE PHASE 02's possession date changes?
The latest dates are on PARAMOUNT ENCLAVE PHASE 02's MahaRERA page (P99000029540). GharKundli's Kundli Watch sends a free WhatsApp update on PARAMOUNT ENCLAVE PHASE 02 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PARAMOUNT ENCLAVE PHASE 02 have?
According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE PHASE 02 has one building filed: BUILDING NO 2 WING B TYPE D1 with 6 floors and 43 units.
How big is the land of PARAMOUNT ENCLAVE PHASE 02?
According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE PHASE 02 stands on 1,288 sq m of land (about 0.3 acres), with 1,288 sq m of sanctioned built-up area and 129 sq m of recreational open space.
What is the track record of PARAMOUNT ENCLAVE PHASE 02's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Builders & Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 53 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PARAMOUNT ENCLAVE PHASE 02?
Google Maps has reviews of PARAMOUNT ENCLAVE PHASE 02 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PARAMOUNT ENCLAVE PHASE 02?
PARAMOUNT ENCLAVE PHASE 02 by GAJANAN BUILDERS & DEVELOPERS is in Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000029540, per GharKundli's check of MahaRERA records.
How many homes are in PARAMOUNT ENCLAVE PHASE 02?
According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE PHASE 02 has 34 homes in 1 tower registered on MahaRERA, and 47% of them are sold or booked.
When was PARAMOUNT ENCLAVE PHASE 02 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PARAMOUNT ENCLAVE PHASE 02 was registered on MahaRERA on 4 June 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on PARAMOUNT ENCLAVE PHASE 02?
No court cases are listed for PARAMOUNT ENCLAVE PHASE 02 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PARAMOUNT ENCLAVE PHASE 02?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GAJANAN BUILDERS & DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PARAMOUNT ENCLAVE PHASE 02
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in pincode 401404
- VIVA SWARANGAN
- KESHAV SRUSHTI
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- V SQUARE ARCADE
- PARAMOUNT ENCLAVE PHASE - 2
- KUSUM EKDANT
- Rubicon Shinde Heritage
- K Bafna Estatess
Other projects by GAJANAN BUILDERS & DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.