Casa Terraza Phase-3

by R AND J BUILDLINE LLP · Diwanman, PalgharAlso near Vasai West, Navghar, Bassein Road

Possession date of Casa Terraza Phase-3: 30 June 2028, moved from 31 December 2025 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000031526, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Casa Terraza Phase-3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Casa Terraza Phase-3 has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 December 2026

    Extended at the builder's request (MahaRERA application EXT99000018237)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 30 June 2028

    Extended at the builder's request (MahaRERA application EA16022619858)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. request a short extension of time due to temporary constraints in labour availability, along with a few other essential construction-related req…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. request a short extension of time due to temporary constraints in labour availability, along with a few other essential construction-related requirements that are still in progress. These unforeseen factors have resulted in a slight delay in completing the remaining minor works, despite consistent efforts to adhere to the original schedule. Granting additional time would enable proper arrangement of labour resources and completion of all pending activities with due care, ensuring that the work is…”

Source: Casa Terraza Phase-3’s extension records on MahaRERA (P99000031526), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Casa Terraza Phase-3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the June 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000031526
Status
Registered and active
Builder
R AND J BUILDLINE LLP
Location
Diwanman, Palghar · 401202
Project type
Residential / Group Housing
Registered on
25 Oct 2021
Completion date at registration
December 2025
Latest completion date
June 2028
Delay so far
30 months
Homes
134
Sold or booked
31%
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of Casa Terraza Phase-3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing - D100%61%20%0%
NA0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing - D: covers 14 (Ground + 13 Upper floors)
  • NA: covers 0 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Casa Terraza Phase-3 every month.

Casa Terraza Phase-3: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Parshwa Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Casa Terraza Phase-3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Casa Terraza Phase-3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Casa Terraza Phase-3

What is the possession date of Casa Terraza Phase-3?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Casa Terraza Phase-3 in Diwanman, Palghar is 30 June 2028 — 30 months later than 31 December 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Casa Terraza Phase-3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Casa Terraza Phase-3's builder has filed on MahaRERA, the official one, is 30 June 2028, already 30 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Casa Terraza Phase-3 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Casa Terraza Phase-3's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2026, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 June 2028, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. request a short extension of time due to temporary constraints in labour availability, along with a few other essential construction-related requirements that are still in progress. These unforeseen factors have resulted in a slight delay in completing the remaining minor works, despite consistent efforts to adhere to the original schedule. Granting additional time would enable proper arrangement of labour resources and completion of all pending activities with due care, ensuring that the work is…".

What is the RERA number of Casa Terraza Phase-3?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Casa Terraza Phase-3 in Diwanman, Palghar is P99000031526.

Is Casa Terraza Phase-3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Casa Terraza Phase-3 is registered as P99000031526 and its status is "Registered and active".

What is the construction status of Casa Terraza Phase-3?

According to GharKundli's check of MahaRERA records (updated October 2026), Casa Terraza Phase-3's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 61% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Casa Terraza Phase-3 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Casa Terraza Phase-3 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Casa Terraza Phase-3 is registered on MahaRERA as P99000031526, its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Casa Terraza Phase-3 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: CASA TERRAZA Wing C (P99000011668). Check that your agreement names the registration of your own wing.

How can I get updates if Casa Terraza Phase-3's possession date changes?

The latest dates are on Casa Terraza Phase-3's MahaRERA page (P99000031526). GharKundli's Kundli Watch sends a free WhatsApp update on Casa Terraza Phase-3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Casa Terraza Phase-3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Casa Terraza Phase-3 has one building filed: Wing - D with 24 floors and 134 units.

How big is the land of Casa Terraza Phase-3?

According to GharKundli's check of MahaRERA records (updated October 2026), Casa Terraza Phase-3 stands on 4,353 sq m of land (about 1.1 acres), with 6,040 sq m of sanctioned built-up area and 653 sq m of recreational open space.

What is the track record of Casa Terraza Phase-3's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Parshwa Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Casa Terraza Phase-3?

Google Maps has reviews of Casa Terraza Phase-3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Casa Terraza Phase-3?

Casa Terraza Phase-3 by R AND J BUILDLINE LLP is in Diwanman, Palghar (pincode 401202), near Vasai West, Navghar, Bassein Road, Maharashtra, and is registered on MahaRERA as P99000031526, per GharKundli's check of MahaRERA records.

How many homes are in Casa Terraza Phase-3?

According to GharKundli's check of MahaRERA records (updated October 2026), Casa Terraza Phase-3 has 134 homes in 2 towers registered on MahaRERA, and 31% of them are sold or booked.

When was Casa Terraza Phase-3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Casa Terraza Phase-3 was registered on MahaRERA on 25 October 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Casa Terraza Phase-3?

No court cases are listed for Casa Terraza Phase-3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Casa Terraza Phase-3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is R AND J BUILDLINE LLP.

All projects with possession due in 2028 in Palghar →

Other projects in Vasai

All 105 projects in Bassein Road (401202) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.