NARAYAN HEIGHTS
by N.S.REALTY · Nilemore, Palghar
Possession date of NARAYAN HEIGHTS: 30 August 2028, moved from 30 April 2026 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000032307, and currently active. Its completion date has moved from April 2026 to August 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about NARAYAN HEIGHTS?
How the possession date of NARAYAN HEIGHTS has moved
30 April 2026
Completion date given when the project was registered
30 April 2028
Extended at the builder's request (MahaRERA application EXT99000012941)
Reason the builder gave MahaRERA: “WE HAVE OBTAINED NEW COMMENCEMENT CERTIFICATE AS ON 21/07/2022.THEREFOR WE REQUEST YOU PLEASE GRANT ME EXTENSION UPTO 30/04/2028.”
30 August 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: NARAYAN HEIGHTS’s extension records on MahaRERA (P99000032307), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NARAYAN HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000032307
- Status
- Registered and active
- Builder
- N.S.REALTY
- Location
- Nilemore, Palghar · 401303
- Project type
- Others
- Registered on
- 29 Dec 2021
- Completion date at registration
- April 2026
- Latest completion date
- August 2028
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 134
- Sold or booked
- 70%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of NARAYAN HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NARAYAN HEIGHTS | 100% | 100% | 43% | 20% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NARAYAN HEIGHTS every month.
NARAYAN HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: NARAYAN HEIGHTS (15 floors)
- Land: 501 sq m (about 0.1 acres) · sanctioned built-up 5,490 sq m · recreational space 1,098 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of NARAYAN HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NARAYAN HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NARAYAN HEIGHTS
What is the possession date of NARAYAN HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NARAYAN HEIGHTS in Nilemore, Palghar is 30 August 2028 — 24 months later than 30 April 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for NARAYAN HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NARAYAN HEIGHTS's builder has filed on MahaRERA, the official one, is 30 August 2028, already 24 months later than the 30 April 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NARAYAN HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), NARAYAN HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 30 April 2028, giving the reason "WE HAVE OBTAINED NEW COMMENCEMENT CERTIFICATE AS ON 21/07/2022.THEREFOR WE REQUEST YOU PLEASE GRANT ME EXTENSION UPTO 30/04/2028.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of NARAYAN HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NARAYAN HEIGHTS in Nilemore, Palghar is P99000032307.
Is NARAYAN HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NARAYAN HEIGHTS is registered as P99000032307 and its status is "Registered and active".
What is the construction status of NARAYAN HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), NARAYAN HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NARAYAN HEIGHTS is 100% done and internal work 43%. GharKundli's full report compares construction progress with the deadline.
Does NARAYAN HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is NARAYAN HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), NARAYAN HEIGHTS is registered on MahaRERA as P99000032307, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NARAYAN HEIGHTS's possession date changes?
The latest dates are on NARAYAN HEIGHTS's MahaRERA page (P99000032307). GharKundli's Kundli Watch sends a free WhatsApp update on NARAYAN HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NARAYAN HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated November 2026), NARAYAN HEIGHTS has one building filed: NARAYAN HEIGHTS with 15 floors.
How big is the land of NARAYAN HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), NARAYAN HEIGHTS stands on 501 sq m of land (about 0.1 acres), with 5,490 sq m of sanctioned built-up area and 1,098 sq m of recreational open space.
Where can I read reviews of NARAYAN HEIGHTS?
Google Maps has reviews of NARAYAN HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NARAYAN HEIGHTS?
NARAYAN HEIGHTS by N.S.REALTY is in Nilemore, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000032307, per GharKundli's check of MahaRERA records.
How many homes are in NARAYAN HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), NARAYAN HEIGHTS has 134 homes in 1 tower registered on MahaRERA, and 70% of them are sold or booked.
When was NARAYAN HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NARAYAN HEIGHTS was registered on MahaRERA on 29 December 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on NARAYAN HEIGHTS?
No court cases are listed for NARAYAN HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of NARAYAN HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is N.S.REALTY.
Check it yourself on MahaRERA
- How to check the possession date of NARAYAN HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Palghar →
Other projects in Nilemore
- STAR LEGACY
- SHREE ANANT TOWER BUILDING NO 1
- VIMAL'S RAMJANKI CHSL
- BABA SAI PALCE CO-OP-HSG LTD
- RAMESH HEIGHTS PHASE 1
- RUTURAJ CLASSIC
- DEEPANJALI CHS LTD.
- ANGEL NISHI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.