PARVATI HOMES
by ICONIC DEVELOPERS · Boisar, Palghar
Possession date of PARVATI HOMES: 30 November 2026, moved from 31 March 2024 (28 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000035069, and currently active. Its completion date has moved from March 2024 to November 2026: 28 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PARVATI HOMES?
How the possession date of PARVATI HOMES has moved
31 March 2024
Completion date given when the project was registered
31 July 2026
Extended at the builder's request (MahaRERA application EXT99000019617)
Reason the builder gave MahaRERA:
“I am writing to formally request an extension for the registration of our ongoing real estate project Parvati Homes, registered under MahaRERA The extension is sought due to the following reasons: Pending Sale of Units: A few units in the p…” Read the full reason
“I am writing to formally request an extension for the registration of our ongoing real estate project Parvati Homes, registered under MahaRERA The extension is sought due to the following reasons: Pending Sale of Units: A few units in the project remain unsold, and we are actively making efforts to complete the sales. However, due to market conditions and other external factors, the process has taken longer than anticipated. External Development Work: Certain external development activities, including [mention specific works such as landscaping, road construction, finishing, etc.], are stil…”30 November 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: PARVATI HOMES’s extension records on MahaRERA (P99000035069), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PARVATI HOMES
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000035069
- Status
- Registered and active
- Builder
- ICONIC DEVELOPERS
- Location
- Boisar, Palghar · 401501
- Project type
- Residential / Group Housing
- Registered on
- 4 May 2022
- Completion date at registration
- March 2024
- Latest completion date
- November 2026
- Delay so far
- 28 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 22
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of PARVATI HOMES, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PARVATI HOMES | 100% | 20% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARVATI HOMES every month.
PARVATI HOMES: buildings, flats and land, as filed on MahaRERA
- Buildings: PARVATI HOMES (6 floors)
- Land: 650 sq m (about 0.2 acres) · sanctioned built-up 650 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PARVATI HOMES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PARVATI HOMES: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PARVATI HOMES
What is the possession date of PARVATI HOMES?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PARVATI HOMES in Boisar, Palghar is 30 November 2026 — 28 months later than 31 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for PARVATI HOMES?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PARVATI HOMES's builder has filed on MahaRERA, the official one, is 30 November 2026, already 28 months later than the 31 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PARVATI HOMES extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PARVATI HOMES's builder applied to MahaRERA to extend the completion date once: to 31 July 2026, giving the reason "I am writing to formally request an extension for the registration of our ongoing real estate project Parvati Homes, registered under MahaRERA The extension is sought due to the following reasons: Pending Sale of Units: A few units in the project remain unsold, and we are actively making efforts to complete the sales. However, due to market conditions and other external factors, the process has taken longer than anticipated. External Development Work: Certain external development activities, including [mention specific works such as landscaping, road construction, finishing, etc.], are stil…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of PARVATI HOMES?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PARVATI HOMES in Boisar, Palghar is P99000035069.
Is PARVATI HOMES registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PARVATI HOMES is registered as P99000035069 and its status is "Registered and active".
What is the construction status of PARVATI HOMES?
According to GharKundli's check of MahaRERA records (updated October 2026), PARVATI HOMES's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PARVATI HOMES is 20% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does PARVATI HOMES have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PARVATI HOMES safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PARVATI HOMES is registered on MahaRERA as P99000035069, its completion date has moved 28 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PARVATI HOMES's possession date changes?
The latest dates are on PARVATI HOMES's MahaRERA page (P99000035069). GharKundli's Kundli Watch sends a free WhatsApp update on PARVATI HOMES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PARVATI HOMES have?
According to GharKundli's check of MahaRERA records (updated October 2026), PARVATI HOMES has one building filed: PARVATI HOMES with 6 floors.
How big is the land of PARVATI HOMES?
According to GharKundli's check of MahaRERA records (updated October 2026), PARVATI HOMES stands on 650 sq m of land (about 0.2 acres), with 650 sq m of sanctioned built-up area.
Where can I read reviews of PARVATI HOMES?
Google Maps has reviews of PARVATI HOMES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PARVATI HOMES?
PARVATI HOMES by ICONIC DEVELOPERS is in Boisar, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000035069, per GharKundli's check of MahaRERA records.
How many homes are in PARVATI HOMES?
According to GharKundli's check of MahaRERA records (updated October 2026), PARVATI HOMES has 22 homes in 1 tower registered on MahaRERA.
When was PARVATI HOMES registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PARVATI HOMES was registered on MahaRERA on 4 May 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on PARVATI HOMES?
No court cases are listed for PARVATI HOMES on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PARVATI HOMES?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ICONIC DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of PARVATI HOMES
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Palghar →
Other projects in pincode 401501
- Luxury Empire Township Phase I
- OM SAI COMPLEX
- MAHAVIR SAPPHIRE
- YOSH EMPIRE
- VALUE HOMES
- Shree Aadinath Park
- SHREE GALAXY
- Sai Shraddha Apartment
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.