Skip to content
GharKundli

GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2

by SHIVANI ENTERPRISES · Nallasopara West, Palghar

Possession date of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2: 30 September 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000046065, and currently active. Its completion date is now September 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 has moved

  1. 31 May 2027

    Completion date given when the project was registered

  2. 30 September 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2’s extension records on MahaRERA (P99000046065), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000046065
Status
Registered and active
Builder
SHIVANI ENTERPRISES
Location
Nallasopara West, Palghar · 401203
Project type
Residential / Group Housing
Registered on
15 Jun 2022
Completion date at registration
May 2027
Latest completion date
September 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
95
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 every month.

GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 (11 floors)
  • Land: 4,672 sq m (about 1.2 acres) · sanctioned built-up 4,672 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2

What is the possession date of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 in Nallasopara West, Palghar is 30 September 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2's builder has filed on MahaRERA, the official one, is 30 September 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 in Nallasopara West, Palghar is P99000046065.

Is GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 is registered as P99000046065 and its status is "Registered and active".

What is the construction status of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 is registered on MahaRERA as P99000046065, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2's possession date changes?

The latest dates are on GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2's MahaRERA page (P99000046065). GharKundli's Kundli Watch sends a free WhatsApp update on GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 has one building filed: GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 with 11 floors.

How big is the land of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 stands on 4,672 sq m of land (about 1.2 acres), with 4,672 sq m of sanctioned built-up area.

Where can I read reviews of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

Google Maps has reviews of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 by SHIVANI ENTERPRISES is in Nallasopara West, Palghar (pincode 401203), Maharashtra, and is registered on MahaRERA as P99000046065, per GharKundli's check of MahaRERA records.

How many homes are in GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 has 95 homes in 1 tower registered on MahaRERA.

When was GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

No court cases are listed for GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHIVANI ENTERPRISES, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in pincode 401203

All 166 projects in Nallasopara West (401203) →

Other projects by SHIVANI ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.