Stone Rudra Paradise
by R-Stone Design and Build Private Limited · Santacruz East, Mumbai 400055Also near Santacruz West, Vakola, AndheriRegistered on MahaRERA as “Rudra Paradise”
What’s in the report? →Possession date of Stone Rudra Paradise (MahaRERA P51800008159): 21 July 2026, moved from 31 January 2021 (66 months later), and it has already passed. It has 58 homes (2 BHK and 3 BHK, 633–1069 sq ft carpet), 61% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008159. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800008159, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Stone Rudra Paradise?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Stone Rudra Paradise has moved
31 January 2021
Completion date given when the project was registered
31 January 2022
Extended at the builder's request (MahaRERA application EXT51800009254)
Reason the builder gave MahaRERA:
“Delay in project and delay in getting approvals are attributable to MCGM and MHADA, due to no clarity on implementation of DCPR 2034 for MHADA Policy and to get finalised and also Transition MHADA Policy was not framed, as we wanted to migr…” Read the full reason
“Delay in project and delay in getting approvals are attributable to MCGM and MHADA, due to no clarity on implementation of DCPR 2034 for MHADA Policy and to get finalised and also Transition MHADA Policy was not framed, as we wanted to migrate project from one MHADA Policy to another Policy, but due to unframed Transition Policy files of the said project could not be moved for further approvals. We further state that due to outbreak of life threatening COVID-19 which had already been declared as a Pandemic by World Health Organization (WHO) and complete lockdown imposed in the country and A…”31 December 2024
Extended at the builder's request (MahaRERA application EXT51800012336)
Reason the builder gave MahaRERA:
“The project was not progressing due to some reasons that the erstwhile developer of the project M/s. Rite Developers Private Limited was unable to manage. We are the new developers of the project and have taken over the project last quarter…” Read the full reason
“The project was not progressing due to some reasons that the erstwhile developer of the project M/s. Rite Developers Private Limited was unable to manage. We are the new developers of the project and have taken over the project last quarter. Since the construction of project was stalled for quite some time now and we have re-started the construction after taking over the project, we will need 24 to 27 months' time to complete the project and then some time for getting all the NOCs and approvals including OC. We have accordingly obtained consents of buyers for the extended time.”21 July 2026
Extended at the builder's request (MahaRERA application EXT51800019382)
Reason the builder gave MahaRERA:
“Sir, The development of the project is underway, and construction of structure is completed up to 4th Upper floor. We anticipate that the completion of entire construction will take more time than compared to what we have declared at the ti…” Read the full reason
“Sir, The development of the project is underway, and construction of structure is completed up to 4th Upper floor. We anticipate that the completion of entire construction will take more time than compared to what we have declared at the time of taking over of project from the erstwhile developer. Also, due to slow sales, we are in the process of arranging funds for competing the construction work of the proposed project and the current application for extension is being submitted as part of arrangement with the lending institution. Accordingly, we have obtained consents from the Allottees…”
Source: Stone Rudra Paradise’s extension records on MahaRERA (P51800008159), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Stone Rudra Paradise
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008159
- Status
- Lapsed (registration period ended)
- Builder
- R-Stone Design and Build Private Limited
- Location
- Santacruz East, Mumbai · 400055
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- January 2021
- Latest completion date
- July 2026
- Delay so far
- 66 months
- Homes
- 58
- Sold or booked
- 61%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Stone Rudra Paradise, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Rudra Paradise | 100% | 100% | 83.81% | 42.64% |
Commencement certificate (CC), as filed on MahaRERA
- Rudra Paradise: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Stone Rudra Paradise every 1–2 months.
Stone Rudra Paradise: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 633 – 759 | 30 |
| 3 BHK | 901 – 1,069 | 28 |
| Shops | 299 – 927 | 4 |
| Office Space | 434 – 1,134 | 4 |
- Buildings: Rudra Paradise (16 floors, 66 units)
- Car parking: 38 covered
- Land: 803 sq m (about 0.2 acres) · sanctioned built-up 2,032 sq m
- Land, as filed: CTS No 116 part, 116-23, 116-24 and 116-25 A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Stone Rudra Paradise →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Stone Rudra Paradise: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Stone Rudra Paradise
What is the possession date of Stone Rudra Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Stone Rudra Paradise in Santacruz East, Mumbai is 21 July 2026 — 66 months later than 31 January 2021, the date given at registration. That date has already passed.
The date has already moved 66 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Stone Rudra Paradise?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Stone Rudra Paradise's builder has filed on MahaRERA, the official one, is 21 July 2026, already 66 months later than the 31 January 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Stone Rudra Paradise extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise's builder applied to MahaRERA to extend the completion date 3 times: to 31 January 2022, giving the reason "Delay in project and delay in getting approvals are attributable to MCGM and MHADA, due to no clarity on implementation of DCPR 2034 for MHADA Policy and to get finalised and also Transition MHADA Policy was not framed, as we wanted to migrate project from one MHADA Policy to another Policy, but due to unframed Transition Policy files of the said project could not be moved for further approvals. We further state that due to outbreak of life threatening COVID-19 which had already been declared as a Pandemic by World Health Organization (WHO) and complete lockdown imposed in the country and A…"; to 31 December 2024, giving the reason "The project was not progressing due to some reasons that the erstwhile developer of the project M/s. Rite Developers Private Limited was unable to manage. We are the new developers of the project and have taken over the project last quarter. Since the construction of project was stalled for quite some time now and we have re-started the construction after taking over the project, we will need 24 to 27 months' time to complete the project and then some time for getting all the NOCs and approvals including OC. We have accordingly obtained consents of buyers for the extended time."; to 21 July 2026, giving the reason "Sir, The development of the project is underway, and construction of structure is completed up to 4th Upper floor. We anticipate that the completion of entire construction will take more time than compared to what we have declared at the time of taking over of project from the erstwhile developer. Also, due to slow sales, we are in the process of arranging funds for competing the construction work of the proposed project and the current application for extension is being submitted as part of arrangement with the lending institution. Accordingly, we have obtained consents from the Allottees…".
What is the RERA number of Stone Rudra Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Stone Rudra Paradise in Santacruz East, Mumbai is P51800008159.
Is Stone Rudra Paradise registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise is registered as P51800008159 and its status is "Lapsed (registration period ended)".
What is the current construction status of Stone Rudra Paradise? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Rudra Paradise is 100% done and internal work 83.81%. GharKundli's full report compares construction progress with the deadline.
Does Stone Rudra Paradise have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Stone Rudra Paradise safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise is registered on MahaRERA as P51800008159, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Stone Rudra Paradise?
Stone Rudra Paradise isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Stone Rudra Paradise are 633 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Stone Rudra Paradise?
For a flat in Stone Rudra Paradise (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Stone Rudra Paradise received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 21 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Stone Rudra Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (21 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Stone Rudra Paradise a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Stone Rudra Paradise uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Stone Rudra Paradise was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Stone Rudra Paradise's possession date changes?
The latest dates are on Stone Rudra Paradise's MahaRERA page (P51800008159). GharKundli's Kundli Watch sends a free WhatsApp update on Stone Rudra Paradise every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Stone Rudra Paradise have?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise has one building filed: Rudra Paradise with 16 floors and 66 units.
What are the flat sizes (carpet area) in Stone Rudra Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Stone Rudra Paradise: 2 BHK: 633 to 759 sq ft carpet (30 homes); 3 BHK: 901 to 1069 sq ft carpet (28 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Stone Rudra Paradise have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 38 covered car parking spaces for Stone Rudra Paradise.
How big is the land of Stone Rudra Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise stands on 803 sq m of land (about 0.2 acres), with 2,032 sq m of sanctioned built-up area.
What are the reviews of Stone Rudra Paradise?
Google Maps has reviews of Stone Rudra Paradise written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Stone Rudra Paradise?
Stone Rudra Paradise by R-Stone Design and Build Private Limited is in Santacruz East, Mumbai, pincode 400055 (near Santacruz West, Vakola, Andheri), Maharashtra, and is registered on MahaRERA as P51800008159, per GharKundli's check of MahaRERA records. Its land is filed as CTS No 116 part, 116-23, 116-24 and 116-25 A. GharKundli lists all 112 MahaRERA projects in Santacruz East (400055).
How many flats are in Stone Rudra Paradise, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise has 58 homes in 1 tower registered on MahaRERA, and 61% of them are sold or booked.
When was Stone Rudra Paradise registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Stone Rudra Paradise was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Does Stone Rudra Paradise have any legal issues or court cases?
No court cases are listed for Stone Rudra Paradise on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Stone Rudra Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is R-Stone Design and Build Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Stone Rudra Paradise
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Santacruz East (400055)
- Pruthi Annexe
- 7th Avenue
- Miraya Residency
- Silver heights
- Ekta Sra CHS
- Mayfair Arth
- Space Grandeur
- Crystal Avenue
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.