Skip to content
GharKundli

NAVKAR CITY PHASE I PART 6

by NAVKAR ESTATE AND HOMES PVT LTD · Naigaon East, Palghar

Possession date of NAVKAR CITY PHASE I PART 6: 30 October 2028, moved from 30 June 2027 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000050162, and currently active. Its completion date has moved from June 2027 to October 2028: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NAVKAR CITY PHASE I PART 6?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NAVKAR CITY PHASE I PART 6 has moved

  1. 30 June 2027

    Completion date given when the project was registered

  2. 30 June 2028

    Extended at the builder's request (MahaRERA application EA02062621204)

    Reason the builder gave MahaRERA: “123”
  3. 30 October 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NAVKAR CITY PHASE I PART 6’s extension records on MahaRERA (P99000050162), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NAVKAR CITY PHASE I PART 6

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000050162
Status
Registered and active
Builder
NAVKAR ESTATE AND HOMES PVT LTD
Location
Naigaon East, Palghar · 401208
Project type
Residential / Group Housing
Registered on
21 Mar 2023
Completion date at registration
June 2027
Latest completion date
October 2028
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
273
Sold or booked
53%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of NAVKAR CITY PHASE I PART 6, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Navkar Harmony - G Type100%75%30%12%

Commencement certificate (CC), as filed on MahaRERA

  • Navkar Harmony - G Type: covers 24 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NAVKAR CITY PHASE I PART 6 every month.

NAVKAR CITY PHASE I PART 6: buildings, flats and land, as filed on MahaRERA

  • Buildings: Navkar Harmony - G Type (25 floors, 273 units)
  • Land: 3,300 sq m (about 0.8 acres) · sanctioned built-up 15,470 sq m · recreational space 660 sq m

The builder’s record and reviews

Navkar Estate And Homes (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 11 still being built, 7 past the promised date (typically 22 months late). 2 complaints on MahaRERA across 2 projects.

Read Google reviews of NAVKAR CITY PHASE I PART 6 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NAVKAR CITY PHASE I PART 6: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NAVKAR CITY PHASE I PART 6

What is the possession date of NAVKAR CITY PHASE I PART 6?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NAVKAR CITY PHASE I PART 6 in Naigaon East, Palghar is 30 October 2028 — 12 months later than 30 June 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for NAVKAR CITY PHASE I PART 6?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NAVKAR CITY PHASE I PART 6's builder has filed on MahaRERA, the official one, is 30 October 2028, already 12 months later than the 30 June 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NAVKAR CITY PHASE I PART 6 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NAVKAR CITY PHASE I PART 6's builder applied to MahaRERA to extend the completion date once: to 30 June 2028, giving the reason "123". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of NAVKAR CITY PHASE I PART 6?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NAVKAR CITY PHASE I PART 6 in Naigaon East, Palghar is P99000050162.

Is NAVKAR CITY PHASE I PART 6 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NAVKAR CITY PHASE I PART 6 is registered as P99000050162 and its status is "Registered and active".

What is the construction status of NAVKAR CITY PHASE I PART 6?

According to GharKundli's check of MahaRERA records (updated October 2026), NAVKAR CITY PHASE I PART 6's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Navkar Harmony - G Type is 75% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.

Does NAVKAR CITY PHASE I PART 6 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is NAVKAR CITY PHASE I PART 6 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NAVKAR CITY PHASE I PART 6 is registered on MahaRERA as P99000050162, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does NAVKAR CITY PHASE I PART 6 have other wings or phases?

Yes. MahaRERA lists 14 other registrations of the same project, each with its own possession date: NAVKAR CITY PHASE I PART 1 (P99000011999); Navkar City Phase I Part 2 (P99000010920, possession 31 Dec 2026); NAVKAR CITY Phase I part 3 (P99000004573); Navkar City Phase-I-Part-4 (P99000008528, possession 31 Dec 2026); Navkar City Phase I Part 5 (P99000034105, possession 30 Oct 2027); Navkar City - Phase I - Part 8 (P99000033433, possession 30 Oct 2027); and 8 more. Check that your agreement names the registration of your own wing.

How can I get updates if NAVKAR CITY PHASE I PART 6's possession date changes?

The latest dates are on NAVKAR CITY PHASE I PART 6's MahaRERA page (P99000050162). GharKundli's Kundli Watch sends a free WhatsApp update on NAVKAR CITY PHASE I PART 6 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NAVKAR CITY PHASE I PART 6 have?

According to GharKundli's check of MahaRERA records (updated October 2026), NAVKAR CITY PHASE I PART 6 has one building filed: Navkar Harmony - G Type with 25 floors and 273 units.

How big is the land of NAVKAR CITY PHASE I PART 6?

According to GharKundli's check of MahaRERA records (updated October 2026), NAVKAR CITY PHASE I PART 6 stands on 3,300 sq m of land (about 0.8 acres), with 15,470 sq m of sanctioned built-up area and 660 sq m of recreational open space.

What is the track record of NAVKAR CITY PHASE I PART 6's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Estate And Homes (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 11 still being built, 7 past the promised date (typically 22 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NAVKAR CITY PHASE I PART 6?

Google Maps has reviews of NAVKAR CITY PHASE I PART 6 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NAVKAR CITY PHASE I PART 6?

NAVKAR CITY PHASE I PART 6 by NAVKAR ESTATE AND HOMES PVT LTD is in Naigaon East, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000050162, per GharKundli's check of MahaRERA records.

How many homes are in NAVKAR CITY PHASE I PART 6?

According to GharKundli's check of MahaRERA records (updated October 2026), NAVKAR CITY PHASE I PART 6 has 273 homes in 1 tower registered on MahaRERA, and 53% of them are sold or booked.

When was NAVKAR CITY PHASE I PART 6 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NAVKAR CITY PHASE I PART 6 was registered on MahaRERA on 21 March 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on NAVKAR CITY PHASE I PART 6?

No court cases are listed for NAVKAR CITY PHASE I PART 6 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NAVKAR CITY PHASE I PART 6?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NAVKAR ESTATE AND HOMES PVT LTD, which has 9 other projects registered on MahaRERA.

All projects with possession due in 2028 in Palghar →

Other projects in Naigaon East

All 245 projects in Vasai East IE (401208) →

Other projects by NAVKAR ESTATE AND HOMES PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.