EMERALD WOODS 2
by SHREHIT DEVELOPERS · Tarapur Road Boisar, Palghar
Possession date of EMERALD WOODS 2: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000051317, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about EMERALD WOODS 2?
How the possession date of EMERALD WOODS 2 has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: EMERALD WOODS 2’s extension records on MahaRERA (P99000051317), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on EMERALD WOODS 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- EMERALD WOODSP99000029318
- MahaRERA registration
- P99000051317
- Status
- Registered and active
- Builder
- SHREHIT DEVELOPERS
- Location
- Tarapur Road Boisar, Palghar · 401502
- Project type
- Residential / Group Housing
- Registered on
- 8 Jun 2023
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 105
- Sold or booked
- 61%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of EMERALD WOODS 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 3 | 100% | 100% | 100% | 100% |
| BUILDING NO 2 | 100% | 100% | 100% | 95% |
| BUILDING NO 4 A WING AND B WING | 100% | 55% | 5% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 3: covers 8 floors
- BUILDING NO 2: covers 8 floors
- BUILDING NO 4 A WING AND B WING: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on EMERALD WOODS 2 every month.
EMERALD WOODS 2: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 3 (8 floors, 26 units) · BUILDING NO 2 (8 floors, 28 units) · BUILDING NO 4 A WING AND B WING (8 floors, 51 units)
- Car parking: 27 covered, 11 open
- Land: 7,200 sq m (about 1.8 acres) · sanctioned built-up 9,262 sq m · recreational space 739 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of EMERALD WOODS 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
EMERALD WOODS 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about EMERALD WOODS 2
What is the possession date of EMERALD WOODS 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for EMERALD WOODS 2 in Tarapur Road Boisar, Palghar is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for EMERALD WOODS 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date EMERALD WOODS 2's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of EMERALD WOODS 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of EMERALD WOODS 2 in Tarapur Road Boisar, Palghar is P99000051317.
Is EMERALD WOODS 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), EMERALD WOODS 2 is registered as P99000051317 and its status is "Registered and active".
What is the construction status of EMERALD WOODS 2?
According to GharKundli's check of MahaRERA records (updated November 2026), EMERALD WOODS 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 55% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does EMERALD WOODS 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is EMERALD WOODS 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), EMERALD WOODS 2 is registered on MahaRERA as P99000051317, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does EMERALD WOODS 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: EMERALD WOODS (P99000029318). Check that your agreement names the registration of your own wing.
How can I get updates if EMERALD WOODS 2's possession date changes?
The latest dates are on EMERALD WOODS 2's MahaRERA page (P99000051317). GharKundli's Kundli Watch sends a free WhatsApp update on EMERALD WOODS 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does EMERALD WOODS 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), EMERALD WOODS 2 has 3 buildings filed: BUILDING NO 3 with 8 floors and 26 units; BUILDING NO 2 with 8 floors and 28 units; BUILDING NO 4 A WING AND B WING with 8 floors and 51 units.
How much parking does EMERALD WOODS 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 27 covered and 11 open car parking spaces for EMERALD WOODS 2.
How big is the land of EMERALD WOODS 2?
According to GharKundli's check of MahaRERA records (updated November 2026), EMERALD WOODS 2 stands on 7,200 sq m of land (about 1.8 acres), with 9,262 sq m of sanctioned built-up area and 739 sq m of recreational open space.
Where can I read reviews of EMERALD WOODS 2?
Google Maps has reviews of EMERALD WOODS 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is EMERALD WOODS 2?
EMERALD WOODS 2 by SHREHIT DEVELOPERS is in Tarapur Road Boisar, Palghar (pincode 401502), Maharashtra, and is registered on MahaRERA as P99000051317, per GharKundli's check of MahaRERA records.
How many homes are in EMERALD WOODS 2?
According to GharKundli's check of MahaRERA records (updated November 2026), EMERALD WOODS 2 has 105 homes in 3 towers registered on MahaRERA, and 61% of them are sold or booked.
When was EMERALD WOODS 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), EMERALD WOODS 2 was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on EMERALD WOODS 2?
No court cases are listed for EMERALD WOODS 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of EMERALD WOODS 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREHIT DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of EMERALD WOODS 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Palghar →
Other projects in pincode 401502
- AAKASH COMPLEX
- SOLITAIRE HEIGHT
- Whitehill Residential
- NISARG -BUILDING NO.2
- ASTER HANS HERITAGE
- Bhakti Avenue
- Aarambh
- Elite Residency
Other projects by SHREHIT DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.