by SHREE GANESH ASSOCIATES · Near Char Rasta, PalgharAlso near Palghar East, Palghar West

Possession date of PALGHAR ONE: 21 January 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000054232, and currently active. Its completion date is now January 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about PALGHAR ONE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PALGHAR ONE has moved

  1. 21 September 2028

    Completion date given when the project was registered

  2. 21 January 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PALGHAR ONE’s extension records on MahaRERA (P99000054232), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PALGHAR ONE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 3 court cases, and how it ended
  • Construction pace against the January 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000054232
Status
Registered and active
Builder
SHREE GANESH ASSOCIATES
Location
Near Char Rasta, Palghar · 401404
Project type
Commercial
Registered on
9 Jan 2024
Completion date at registration
September 2028
Latest completion date
January 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
33%
Towers
1
Complaints on MahaRERA
2
Court cases listed
3
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of PALGHAR ONE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PALGHAR ONE100%100%90%75%

Commencement certificate (CC), as filed on MahaRERA

  • PALGHAR ONE: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PALGHAR ONE every month.

PALGHAR ONE: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Shree Ganesh Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project.

Read Google reviews of PALGHAR ONE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PALGHAR ONE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PALGHAR ONE

What is the possession date of PALGHAR ONE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PALGHAR ONE in Near Char Rasta, Palghar is 21 January 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PALGHAR ONE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PALGHAR ONE's builder has filed on MahaRERA, the official one, is 21 January 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of PALGHAR ONE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PALGHAR ONE in Near Char Rasta, Palghar is P99000054232.

Is PALGHAR ONE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PALGHAR ONE is registered as P99000054232 and its status is "Registered and active".

What is the construction status of PALGHAR ONE?

According to GharKundli's check of MahaRERA records (updated October 2026), PALGHAR ONE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PALGHAR ONE is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does PALGHAR ONE have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PALGHAR ONE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PALGHAR ONE is registered on MahaRERA as P99000054232, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PALGHAR ONE's possession date changes?

The latest dates are on PALGHAR ONE's MahaRERA page (P99000054232). GharKundli's Kundli Watch sends a free WhatsApp update on PALGHAR ONE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PALGHAR ONE have?

According to GharKundli's check of MahaRERA records (updated October 2026), PALGHAR ONE has one building filed: PALGHAR ONE with 11 floors and 197 units.

How big is the land of PALGHAR ONE?

According to GharKundli's check of MahaRERA records (updated October 2026), PALGHAR ONE stands on 7,889 sq m of land (about 1.9 acres), with 11,066 sq m of sanctioned built-up area.

What is the track record of PALGHAR ONE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Ganesh Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of PALGHAR ONE?

Google Maps has reviews of PALGHAR ONE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PALGHAR ONE?

PALGHAR ONE by SHREE GANESH ASSOCIATES is in Near Char Rasta, Palghar (pincode 401404), near Palghar East, Palghar West, Maharashtra, and is registered on MahaRERA as P99000054232, per GharKundli's check of MahaRERA records.

How many homes are in PALGHAR ONE?

According to GharKundli's check of MahaRERA records (updated October 2026), PALGHAR ONE has 0 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.

When was PALGHAR ONE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PALGHAR ONE was registered on MahaRERA on 9 January 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on PALGHAR ONE?

3 court cases are listed for PALGHAR ONE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of PALGHAR ONE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE GANESH ASSOCIATES, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2029 in Palghar →

Other projects in Palghar

All 413 projects in Palghar (401404) →

Other projects by SHREE GANESH ASSOCIATES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.