Evergreen Woods
by ANKUR MAYFLOWER ASSOCIATES · Andheri East, MumbaiAlso near Andheri West, Mogra, Malad East
Possession: Evergreen Woods is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008167. Status: Completed. 14 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Evergreen Woods?
How the possession date of Evergreen Woods has moved
30 June 2020
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51800005329)
Reason the builder gave MahaRERA: “Delay in Approvals”
30 December 2021
Revised completion date on MahaRERA
Source: Evergreen Woods’s extension records on MahaRERA (P51800008167), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Evergreen Woods
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 14 complaints, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008167
- Status
- Completed
- Builder
- ANKUR MAYFLOWER ASSOCIATES
- Location
- Andheri East, Mumbai · 400069
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- June 2020
- Latest completion date
- December 2021
- Delay so far
- 18 months
- Homes
- 77
- Towers
- 2
- Complaints on MahaRERA
- 14
- Court cases listed
- 0
- Appeals at the tribunal
- 6
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Evergreen Woods, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RESIDENTIAL | 100% | 100% | 100% | 100% |
| EVERGREEN WOODS 2 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Evergreen Woods every month.
Evergreen Woods: buildings, flats and land, as filed on MahaRERA
- Buildings: RESIDENTIAL (17 floors) · EVERGREEN WOODS 2 (2 floors)
- Land: 1,006 sq m (about 0.2 acres) · sanctioned built-up 2,285 sq m · recreational space 267 sq m
- Boundaries filed include: Private Road, Andheri-Kurla Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Ankur Mayflower Associates has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 lapsed. 14 complaints on MahaRERA across 1 project.
Read Google reviews of Evergreen Woods →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Evergreen Woods: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Evergreen Woods
What is the possession date of Evergreen Woods?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Evergreen Woods in Andheri East, Mumbai is 30 December 2021 — 18 months later than 30 June 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Evergreen Woods?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Evergreen Woods's builder has filed on MahaRERA, the official one, is 30 December 2021, already 18 months later than the 30 June 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Evergreen Woods extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Evergreen Woods's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "Delay in Approvals".
What is the RERA number of Evergreen Woods?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Evergreen Woods in Andheri East, Mumbai is P51800008167.
Is Evergreen Woods registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Evergreen Woods is registered as P51800008167 and its status is "Completed".
What is the construction status of Evergreen Woods?
According to GharKundli's check of MahaRERA records (updated November 2026), Evergreen Woods's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Evergreen Woods have complaints on MahaRERA?
14 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Evergreen Woods safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Evergreen Woods is registered on MahaRERA as P51800008167, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 14 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Evergreen Woods's possession date changes?
The latest dates are on Evergreen Woods's MahaRERA page (P51800008167). GharKundli's Kundli Watch sends a free WhatsApp update on Evergreen Woods every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Evergreen Woods have?
According to GharKundli's check of MahaRERA records (updated November 2026), Evergreen Woods has 2 buildings filed: RESIDENTIAL with 17 floors; EVERGREEN WOODS 2 with 2 floors.
How big is the land of Evergreen Woods?
According to GharKundli's check of MahaRERA records (updated November 2026), Evergreen Woods stands on 1,006 sq m of land (about 0.2 acres), with 2,285 sq m of sanctioned built-up area and 267 sq m of recreational open space.
What is the track record of Evergreen Woods's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Ankur Mayflower Associates has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 lapsed. 14 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Evergreen Woods?
Google Maps has reviews of Evergreen Woods written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 14 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Evergreen Woods?
Evergreen Woods by ANKUR MAYFLOWER ASSOCIATES is in Andheri East, Mumbai (pincode 400069), near Andheri West, Mogra, Malad East, Maharashtra, and is registered on MahaRERA as P51800008167, per GharKundli's check of MahaRERA records. Its boundaries filed there include Private Road, Andheri-Kurla Road.
How many homes are in Evergreen Woods?
According to GharKundli's check of MahaRERA records (updated November 2026), Evergreen Woods has 77 homes in 2 towers registered on MahaRERA.
When was Evergreen Woods registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Evergreen Woods was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Evergreen Woods?
No court cases are listed for Evergreen Woods on MahaRERA, and 6 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Evergreen Woods?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ANKUR MAYFLOWER ASSOCIATES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Evergreen Woods
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400069
- Nityanand Nagar Vibhag IV Cooperative Housing Society Limited
- Commercial Project Andheri
- AMEY APARTMENTS
- AARHAM
- Sajay Business Hub
- Sankirt Jasmine
- Mass Marquise
- Shri Shankarpuri
Other projects by ANKUR MAYFLOWER ASSOCIATES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.