AJIT SHANTI INDUSTRIAL PARK

by AAMGAON 1 INFRA PRIVATE LIMITED · Village Achhad, Palghar

Possession date of AJIT SHANTI INDUSTRIAL PARK: 30 January 2027, moved from 31 March 2026 (6 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000080604, and currently active. Its completion date has moved from March 2026 to January 2027: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AJIT SHANTI INDUSTRIAL PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AJIT SHANTI INDUSTRIAL PARK has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 30 September 2026

    Extended at the builder's request (MahaRERA application EA25032620368)

    Reason the builder gave MahaRERA:
    “The delay in firefighting equipment work was due to design revisions required for regulatory compliance, delays in procurement of approved materials, and extended timelines for statutory approvals and inspections from the fire authorities.…” Read the full reason“The delay in firefighting equipment work was due to design revisions required for regulatory compliance, delays in procurement of approved materials, and extended timelines for statutory approvals and inspections from the fire authorities. Additionally, coordination with other ongoing construction activities impacted the installation schedule. Given the circumstances, we kindly request an extension until 30-09-2026, to complete the project and fulfil all regulatory requirements.”
  3. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: AJIT SHANTI INDUSTRIAL PARK’s extension records on MahaRERA (P99000080604), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AJIT SHANTI INDUSTRIAL PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000080604
Status
Registered and active
Builder
AAMGAON 1 INFRA PRIVATE LIMITED
Location
Village Achhad, Palghar · 401606
Project type
Mixed
Registered on
19 Jun 2025
Completion date at registration
March 2026
Latest completion date
January 2027
Delay so far
6 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
0%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of AJIT SHANTI INDUSTRIAL PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1100%100%95%70%
BUILDING NO 2100%100%90%70%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING NO 1: covers 2 floors
  • BUILDING NO 2: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AJIT SHANTI INDUSTRIAL PARK every month.

AJIT SHANTI INDUSTRIAL PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 1 (2 floors, 18 units) · BUILDING NO 2 (2 floors, 5 units)
  • Car parking: 13 covered
  • Land: 4,530 sq m (about 1.1 acres) · sanctioned built-up 3,540 sq m
  • Boundaries filed include: INTERNAL LAYOUT ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AJIT SHANTI INDUSTRIAL PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AJIT SHANTI INDUSTRIAL PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AJIT SHANTI INDUSTRIAL PARK

What is the possession date of AJIT SHANTI INDUSTRIAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AJIT SHANTI INDUSTRIAL PARK in Village Achhad, Palghar is 30 January 2027 — 6 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for AJIT SHANTI INDUSTRIAL PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AJIT SHANTI INDUSTRIAL PARK's builder has filed on MahaRERA, the official one, is 30 January 2027, already 6 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AJIT SHANTI INDUSTRIAL PARK extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AJIT SHANTI INDUSTRIAL PARK's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "The delay in firefighting equipment work was due to design revisions required for regulatory compliance, delays in procurement of approved materials, and extended timelines for statutory approvals and inspections from the fire authorities. Additionally, coordination with other ongoing construction activities impacted the installation schedule. Given the circumstances, we kindly request an extension until 30-09-2026, to complete the project and fulfil all regulatory requirements.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of AJIT SHANTI INDUSTRIAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AJIT SHANTI INDUSTRIAL PARK in Village Achhad, Palghar is P99000080604.

Is AJIT SHANTI INDUSTRIAL PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AJIT SHANTI INDUSTRIAL PARK is registered as P99000080604 and its status is "Registered and active".

What is the construction status of AJIT SHANTI INDUSTRIAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), AJIT SHANTI INDUSTRIAL PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does AJIT SHANTI INDUSTRIAL PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is AJIT SHANTI INDUSTRIAL PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AJIT SHANTI INDUSTRIAL PARK is registered on MahaRERA as P99000080604, its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AJIT SHANTI INDUSTRIAL PARK's possession date changes?

The latest dates are on AJIT SHANTI INDUSTRIAL PARK's MahaRERA page (P99000080604). GharKundli's Kundli Watch sends a free WhatsApp update on AJIT SHANTI INDUSTRIAL PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AJIT SHANTI INDUSTRIAL PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), AJIT SHANTI INDUSTRIAL PARK has 2 buildings filed: BUILDING NO 1 with 2 floors and 18 units; BUILDING NO 2 with 2 floors and 5 units.

How much parking does AJIT SHANTI INDUSTRIAL PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 13 covered car parking spaces for AJIT SHANTI INDUSTRIAL PARK.

How big is the land of AJIT SHANTI INDUSTRIAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), AJIT SHANTI INDUSTRIAL PARK stands on 4,530 sq m of land (about 1.1 acres), with 3,540 sq m of sanctioned built-up area.

Where can I read reviews of AJIT SHANTI INDUSTRIAL PARK?

Google Maps has reviews of AJIT SHANTI INDUSTRIAL PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AJIT SHANTI INDUSTRIAL PARK?

AJIT SHANTI INDUSTRIAL PARK by AAMGAON 1 INFRA PRIVATE LIMITED is in Village Achhad, Palghar (pincode 401606), Maharashtra, and is registered on MahaRERA as P99000080604, per GharKundli's check of MahaRERA records. Its boundaries filed there include INTERNAL LAYOUT ROAD.

How many homes are in AJIT SHANTI INDUSTRIAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), AJIT SHANTI INDUSTRIAL PARK has 0 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was AJIT SHANTI INDUSTRIAL PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AJIT SHANTI INDUSTRIAL PARK was registered on MahaRERA on 19 June 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on AJIT SHANTI INDUSTRIAL PARK?

No court cases are listed for AJIT SHANTI INDUSTRIAL PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AJIT SHANTI INDUSTRIAL PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AAMGAON 1 INFRA PRIVATE LIMITED.

All projects with possession due in 2027 in Palghar →

Other projects in Talasari

All 5 projects in Talasari (401606) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.