Mahalaxmi City Phase III
by Gruhlamxi Life Space Private Limited · Bokhara, NagpurAlso near Mouza - Bhokara, Godhani
Possession: Mahalaxmi City Phase III is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500003127. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Mahalaxmi City Phase III?
How the possession date of Mahalaxmi City Phase III has moved
20 November 2020
Completion date given when the project was registered
19 November 2021
Extended at the builder's request (MahaRERA application EXT50500008701)
Reason the builder gave MahaRERA:
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of…” Read the full reason
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant an extension of one year due to force majeure and do the needful.”31 December 2022
Extended at the builder's request (MahaRERA application EXT50500012042)
Reason the builder gave MahaRERA:
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of…” Read the full reason
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of the project due to Pandemic COVID-19. The project work is at finishing stage with considering the situation and shortfall in manpower we request you to kindly grant an extension till 31.12.2022 due to force majeure and do the needful.”
Source: Mahalaxmi City Phase III’s extension records on MahaRERA (P50500003127), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mahalaxmi City Phase III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500003127
- Status
- Completed
- Builder
- Gruhlamxi Life Space Private Limited
- Location
- Bokhara, Nagpur · 441111
- Project type
- Residential / Group Housing
- Registered on
- 4 Aug 2017
- Completion date at registration
- November 2020
- Latest completion date
- December 2022
- Delay so far
- 25 months
- Homes
- 28
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Mahalaxmi City Phase III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Block No 17 B2 | 95% | 95% | 7% | 0% |
| Block No 17B2 | 95% | 95% | 7% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahalaxmi City Phase III every month.
Mahalaxmi City Phase III: buildings, flats and land, as filed on MahaRERA
- Buildings: Block No 17 B2 (9 floors) · Block No 17B2 (9 floors)
- Land: 435 sq m (about 0.1 acres) · sanctioned built-up 1,125 sq m · recreational space 5,244 sq m
- Boundaries filed include: Outer Ring Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Mahalaxmi City Phase III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mahalaxmi City Phase III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mahalaxmi City Phase III
What is the possession date of Mahalaxmi City Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mahalaxmi City Phase III in Bokhara, Nagpur is 31 December 2022 — 25 months later than 20 November 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Mahalaxmi City Phase III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahalaxmi City Phase III's builder has filed on MahaRERA, the official one, is 31 December 2022, already 25 months later than the 20 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mahalaxmi City Phase III extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase III's builder applied to MahaRERA to extend the completion date 2 times: to 19 November 2021, giving the reason "Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant an extension of one year due to force majeure and do the needful."; to 31 December 2022, giving the reason "Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of the project due to Pandemic COVID-19. The project work is at finishing stage with considering the situation and shortfall in manpower we request you to kindly grant an extension till 31.12.2022 due to force majeure and do the needful.".
What is the RERA number of Mahalaxmi City Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mahalaxmi City Phase III in Bokhara, Nagpur is P50500003127.
Is Mahalaxmi City Phase III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase III is registered as P50500003127 and its status is "Completed".
What is the construction status of Mahalaxmi City Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase III's status on MahaRERA is "Completed". As filed by the builder, slab work is 95% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Mahalaxmi City Phase III have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Mahalaxmi City Phase III safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase III is registered on MahaRERA as P50500003127, its MahaRERA status is "Completed", its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Mahalaxmi City Phase III's possession date changes?
The latest dates are on Mahalaxmi City Phase III's MahaRERA page (P50500003127). GharKundli's Kundli Watch sends a free WhatsApp update on Mahalaxmi City Phase III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mahalaxmi City Phase III have?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase III has 2 buildings filed: Block No 17 B2 with 9 floors; Block No 17B2 with 9 floors.
How big is the land of Mahalaxmi City Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase III stands on 435 sq m of land (about 0.1 acres), with 1,125 sq m of sanctioned built-up area and 5,244 sq m of recreational open space.
Where can I read reviews of Mahalaxmi City Phase III?
Google Maps has reviews of Mahalaxmi City Phase III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mahalaxmi City Phase III?
Mahalaxmi City Phase III by Gruhlamxi Life Space Private Limited is in Bokhara, Nagpur (pincode 441111), near Mouza - Bhokara, Godhani, Maharashtra, and is registered on MahaRERA as P50500003127, per GharKundli's check of MahaRERA records. Its boundaries filed there include Outer Ring Road.
How many homes are in Mahalaxmi City Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase III has 28 homes in 2 towers registered on MahaRERA.
When was Mahalaxmi City Phase III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase III was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Mahalaxmi City Phase III?
No court cases are listed for Mahalaxmi City Phase III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Mahalaxmi City Phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Gruhlamxi Life Space Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Mahalaxmi City Phase III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nagpur (Rural)
- Mahalaxmi City Phase IV
- DEV BHUMI
- Shree Nagari 3
- DWARKA NAGARI
- LAKE SHORE OASIS-TWIN DUPLEX
- Royal Dream City-2
- SHIV SOLITAIRE
- SWASTIK IMPERIAL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.