Mahalaxmi City Phase IV
by Gruhlaxmi LIfe Space Private Limited · Bokhara, Nagpur
Possession: Mahalaxmi City Phase IV is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500002498. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Mahalaxmi City Phase IV?
How the possession date of Mahalaxmi City Phase IV has moved
20 November 2020
Completion date given when the project was registered
19 November 2021
Extended at the builder's request (MahaRERA application EXT50500008700)
Reason the builder gave MahaRERA:
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of…” Read the full reason
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant extension of one year due to force majeure and do the needful”31 December 2022
Extended at the builder's request (MahaRERA application EXT50500012040)
Reason the builder gave MahaRERA:
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of…” Read the full reason
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant extension till 31.12.2022 due to force majeure and do the needful.”
Source: Mahalaxmi City Phase IV’s extension records on MahaRERA (P50500002498), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mahalaxmi City Phase IV
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Mahalaxmi City Phase IP50500002523
- Mahalaxmi City Phase IIP50500002647
- Mahalaxmi City Phase IIIP50500003127 · possession 31 Dec 2022
- Mahalaxmi City Phase VP50500017428 · possession 31 Dec 2022
- MahaRERA registration
- P50500002498
- Status
- Completed
- Builder
- Gruhlaxmi LIfe Space Private Limited
- Location
- Bokhara, Nagpur · 441111
- Project type
- Residential / Group Housing
- Registered on
- 1 Aug 2017
- Completion date at registration
- November 2020
- Latest completion date
- December 2022
- Delay so far
- 25 months
- Homes
- 28
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Mahalaxmi City Phase IV, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Block 17 B3 | 95% | 95% | 0% | 0% |
| Block 17B3 | 95% | 95% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahalaxmi City Phase IV every month.
Mahalaxmi City Phase IV: buildings, flats and land, as filed on MahaRERA
- Buildings: Block 17 B3 (9 floors) · Block 17B3 (9 floors)
- Land: 590 sq m (about 0.1 acres) · sanctioned built-up 1,213 sq m · recreational space 5,244 sq m
- Boundaries filed include: Outer Ring Road
The builder’s record and reviews
Gruhlaxmi Life Space has 5 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 19 months). No complaints on MahaRERA.
Read Google reviews of Mahalaxmi City Phase IV →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mahalaxmi City Phase IV: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mahalaxmi City Phase IV
What is the possession date of Mahalaxmi City Phase IV?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mahalaxmi City Phase IV in Bokhara, Nagpur is 31 December 2022 — 25 months later than 20 November 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Mahalaxmi City Phase IV?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahalaxmi City Phase IV's builder has filed on MahaRERA, the official one, is 31 December 2022, already 25 months later than the 20 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mahalaxmi City Phase IV extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase IV's builder applied to MahaRERA to extend the completion date 2 times: to 19 November 2021, giving the reason "Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant extension of one year due to force majeure and do the needful"; to 31 December 2022, giving the reason "Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies is observed in compliance which is under rectification. We feel regret for the delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant extension till 31.12.2022 due to force majeure and do the needful.".
What is the RERA number of Mahalaxmi City Phase IV?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mahalaxmi City Phase IV in Bokhara, Nagpur is P50500002498.
Is Mahalaxmi City Phase IV registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase IV is registered as P50500002498 and its status is "Completed".
What is the construction status of Mahalaxmi City Phase IV?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase IV's status on MahaRERA is "Completed". As filed by the builder, slab work is 95% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Mahalaxmi City Phase IV have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Mahalaxmi City Phase IV safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase IV is registered on MahaRERA as P50500002498, its MahaRERA status is "Completed", its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Mahalaxmi City Phase IV have other wings or phases?
Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: Mahalaxmi City Phase I (P50500002523); Mahalaxmi City Phase II (P50500002647); Mahalaxmi City Phase III (P50500003127, possession 31 Dec 2022); Mahalaxmi City Phase V (P50500017428, possession 31 Dec 2022). Check that your agreement names the registration of your own wing.
How can I get updates if Mahalaxmi City Phase IV's possession date changes?
The latest dates are on Mahalaxmi City Phase IV's MahaRERA page (P50500002498). GharKundli's Kundli Watch sends a free WhatsApp update on Mahalaxmi City Phase IV every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mahalaxmi City Phase IV have?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase IV has 2 buildings filed: Block 17 B3 with 9 floors; Block 17B3 with 9 floors.
How big is the land of Mahalaxmi City Phase IV?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase IV stands on 590 sq m of land (about 0.1 acres), with 1,213 sq m of sanctioned built-up area and 5,244 sq m of recreational open space.
What is the track record of Mahalaxmi City Phase IV's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Gruhlaxmi Life Space has 5 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 19 months). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Mahalaxmi City Phase IV?
Google Maps has reviews of Mahalaxmi City Phase IV written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mahalaxmi City Phase IV?
Mahalaxmi City Phase IV by Gruhlaxmi LIfe Space Private Limited is in Bokhara, Nagpur (pincode 441111), Maharashtra, and is registered on MahaRERA as P50500002498, per GharKundli's check of MahaRERA records. Its boundaries filed there include Outer Ring Road.
How many homes are in Mahalaxmi City Phase IV?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase IV has 28 homes in 2 towers registered on MahaRERA.
When was Mahalaxmi City Phase IV registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase IV was registered on MahaRERA on 1 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Mahalaxmi City Phase IV?
No court cases are listed for Mahalaxmi City Phase IV on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Mahalaxmi City Phase IV?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Gruhlaxmi LIfe Space Private Limited, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mahalaxmi City Phase IV
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nagpur (Rural)
- Mahalaxmi City Phase III
- DEV BHUMI
- DWARKA NAGARI
- Shree Nagari 3
- LAKE SHORE OASIS-TWIN DUPLEX
- Royal Dream City-2
- SHIV SOLITAIRE
- SWASTIK IMPERIAL
Other projects by Gruhlaxmi LIfe Space Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.