Mahalaxmi City Phase V
by Gruhlaxmi LIfe Space Pvt Ltd · Mahalaxmi City, Bokhara, Nagpur
Possession: Mahalaxmi City Phase V is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500017428. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Mahalaxmi City Phase V?
How the possession date of Mahalaxmi City Phase V has moved
10 November 2020
Completion date given when the project was registered
9 November 2021
Extended at the builder's request (MahaRERA application EXT50500008657)
Reason the builder gave MahaRERA:
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies are observed in compliance which is under rectification. We feel regret for delay in execution of th…” Read the full reason
“Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies are observed in compliance which is under rectification. We feel regret for delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant an extension of one year due to force majeure and do the needful.”31 December 2022
Extended at the builder's request (MahaRERA application EXT50500012037)
Reason the builder gave MahaRERA: “Request for extension under section 7(3) is attached herewith for your kind perusal. Request you to please consider the same and allow extension till 31.12.2022.”
Source: Mahalaxmi City Phase V’s extension records on MahaRERA (P50500017428), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mahalaxmi City Phase V
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Mahalaxmi City Phase IP50500002523
- Mahalaxmi City Phase IIP50500002647
- Mahalaxmi City Phase IIIP50500003127 · possession 31 Dec 2022
- Mahalaxmi City Phase IVP50500002498 · possession 31 Dec 2022
- MahaRERA registration
- P50500017428
- Status
- Completed
- Builder
- Gruhlaxmi LIfe Space Pvt Ltd
- Location
- Mahalaxmi City, Bokhara, Nagpur · 441111
- Project type
- Residential / Group Housing
- Registered on
- 13 Aug 2018
- Completion date at registration
- November 2020
- Latest completion date
- December 2022
- Delay so far
- 25 months
- Homes
- 28
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Mahalaxmi City Phase V, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Block No 17 B4 | 100% | 100% | 75% | 0% |
| Block No17B4 | 100% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahalaxmi City Phase V every month.
Mahalaxmi City Phase V: buildings, flats and land, as filed on MahaRERA
- Buildings: Block No 17 B4 (9 floors) · Block No17B4 (9 floors)
- Land: 590 sq m (about 0.1 acres) · sanctioned built-up 1,618 sq m · recreational space 5,244 sq m
- Boundaries filed include: Outer Ring Road
The builder’s record and reviews
Gruhlaxmi Life Space has 5 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 19 months). No complaints on MahaRERA.
Read Google reviews of Mahalaxmi City Phase V →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mahalaxmi City Phase V: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mahalaxmi City Phase V
What is the possession date of Mahalaxmi City Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mahalaxmi City Phase V in Mahalaxmi City, Bokhara, Nagpur is 31 December 2022 — 25 months later than 10 November 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Mahalaxmi City Phase V?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahalaxmi City Phase V's builder has filed on MahaRERA, the official one, is 31 December 2022, already 25 months later than the 10 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mahalaxmi City Phase V extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase V's builder applied to MahaRERA to extend the completion date 2 times: to 9 November 2021, giving the reason "Dear Sir/ Madam, The project is completed except for some minor finishing work and applied for Occupancy certificate but some discrepancies are observed in compliance which is under rectification. We feel regret for delay in execution of the project due to Pandemic COVID-19. With considering the Pandemic situation and shortfall in manpower we request you to kindly grant an extension of one year due to force majeure and do the needful."; to 31 December 2022, giving the reason "Request for extension under section 7(3) is attached herewith for your kind perusal. Request you to please consider the same and allow extension till 31.12.2022.".
What is the RERA number of Mahalaxmi City Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mahalaxmi City Phase V in Mahalaxmi City, Bokhara, Nagpur is P50500017428.
Is Mahalaxmi City Phase V registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase V is registered as P50500017428 and its status is "Completed".
What is the construction status of Mahalaxmi City Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase V's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Mahalaxmi City Phase V have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Mahalaxmi City Phase V safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase V is registered on MahaRERA as P50500017428, its MahaRERA status is "Completed", its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Mahalaxmi City Phase V have other wings or phases?
Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: Mahalaxmi City Phase I (P50500002523); Mahalaxmi City Phase II (P50500002647); Mahalaxmi City Phase III (P50500003127, possession 31 Dec 2022); Mahalaxmi City Phase IV (P50500002498, possession 31 Dec 2022). Check that your agreement names the registration of your own wing.
How can I get updates if Mahalaxmi City Phase V's possession date changes?
The latest dates are on Mahalaxmi City Phase V's MahaRERA page (P50500017428). GharKundli's Kundli Watch sends a free WhatsApp update on Mahalaxmi City Phase V every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mahalaxmi City Phase V have?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase V has 2 buildings filed: Block No 17 B4 with 9 floors; Block No17B4 with 9 floors.
How big is the land of Mahalaxmi City Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase V stands on 590 sq m of land (about 0.1 acres), with 1,618 sq m of sanctioned built-up area and 5,244 sq m of recreational open space.
What is the track record of Mahalaxmi City Phase V's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Gruhlaxmi Life Space has 5 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 19 months). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Mahalaxmi City Phase V?
Google Maps has reviews of Mahalaxmi City Phase V written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mahalaxmi City Phase V?
Mahalaxmi City Phase V by Gruhlaxmi LIfe Space Pvt Ltd is in Mahalaxmi City, Bokhara, Nagpur (pincode 441111), Maharashtra, and is registered on MahaRERA as P50500017428, per GharKundli's check of MahaRERA records. Its boundaries filed there include Outer Ring Road.
How many homes are in Mahalaxmi City Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase V has 28 homes in 2 towers registered on MahaRERA.
When was Mahalaxmi City Phase V registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahalaxmi City Phase V was registered on MahaRERA on 13 August 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Mahalaxmi City Phase V?
No court cases are listed for Mahalaxmi City Phase V on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Mahalaxmi City Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Gruhlaxmi LIfe Space Pvt Ltd.
Check it yourself on MahaRERA
- How to check the possession date of Mahalaxmi City Phase V
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nagpur (Rural)
- DWARKA NAGARI
- Shree Nagari 3
- DEV BHUMI
- LAKE SHORE OASIS-TWIN DUPLEX
- Royal Dream City-2
- SHIV SOLITAIRE
- SWASTIK IMPERIAL
- Park House Tranquil
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.