Balasaheb Deoras Sahaniwas Phase 2

by PRAKASH NARAYANRAO RAOLE · Gandhisagar, Nagpur 440032

What’s in the report? →

Possession date of Balasaheb Deoras Sahaniwas Phase 2 (MahaRERA P50500011868): 30 March 2022, moved from 31 March 2019 (36 months later), and it has already passed. It has 245 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500011868. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P50500011868, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (March 2022) has passed.

What do you want to know about Balasaheb Deoras Sahaniwas Phase 2?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Balasaheb Deoras Sahaniwas Phase 2 has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 31 March 2021

    Extended at the builder's request (MahaRERA application EXT50500000065)

    Reason the builder gave MahaRERA: “CONSTRUCTION WORK OF PH II IS STARTED LAST YEAR BUT THE EXISTING FLAT OWNER HAVE TAKEN SOME OBJECTION'S HENCE THE WORK IS STOOPED AT PRESENT.THE SETTLEMENT IN THIS RESPECT IS IN PROGRESS.”
  3. 31 March 2021

    Extended at the builder's request (MahaRERA application EXT50500001626)

    Reason the builder gave MahaRERA: “Occupancy Certificate is not obtained”
  4. 31 March 2021

    Extended at the builder's request (MahaRERA application EXT50500005999)

    Reason the builder gave MahaRERA: “NON RECEIPT OF OCCUPANCY CERTIFICATE”
  5. 30 March 2022

    Revised completion date on MahaRERA

Source: Balasaheb Deoras Sahaniwas Phase 2’s extension records on MahaRERA (P50500011868), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Balasaheb Deoras Sahaniwas Phase 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500011868
Status
Lapsed (registration period ended)
Builder
PRAKASH NARAYANRAO RAOLE
Location
Gandhisagar, Nagpur · 440032
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
March 2019
Latest completion date
March 2022
Delay so far
36 months
Homes
245
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Balasaheb Deoras Sahaniwas Phase 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1100%100%100%100%
B 2100%100%100%100%
B 3100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Balasaheb Deoras Sahaniwas Phase 2 every 1–2 months.

Balasaheb Deoras Sahaniwas Phase 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 1 (10 floors) · B 2 (9 floors) · B 3 (10 floors)
  • Land: 1,695 sq m (about 0.4 acres) · sanctioned built-up 3,104 sq m
  • Boundaries filed include: SIR BEZANJI MEHTA ROAD
  • Land, as filed: 178/4,5,6,7
  • Map: Get directions

The builder’s record and reviews

Prakash Narayanrao Raole has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, 1 within the promised date and 4 needed more time (typically 13 months); 1 still being built, 1 past the promised date (typically 62 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Balasaheb Deoras Sahaniwas Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Balasaheb Deoras Sahaniwas Phase 2: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Balasaheb Deoras Sahaniwas Phase 2

What is the possession date of Balasaheb Deoras Sahaniwas Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Balasaheb Deoras Sahaniwas Phase 2 in Gandhisagar, Nagpur is 30 March 2022 — 36 months later than 31 March 2019, the date given at registration. That date has already passed.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Balasaheb Deoras Sahaniwas Phase 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Balasaheb Deoras Sahaniwas Phase 2's builder has filed on MahaRERA, the official one, is 30 March 2022, already 36 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Balasaheb Deoras Sahaniwas Phase 2 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2021, giving the reason "CONSTRUCTION WORK OF PH II IS STARTED LAST YEAR BUT THE EXISTING FLAT OWNER HAVE TAKEN SOME OBJECTION'S HENCE THE WORK IS STOOPED AT PRESENT.THE SETTLEMENT IN THIS RESPECT IS IN PROGRESS."; to 31 March 2021, giving the reason "Occupancy Certificate is not obtained"; to 31 March 2021, giving the reason "NON RECEIPT OF OCCUPANCY CERTIFICATE".

What is the RERA number of Balasaheb Deoras Sahaniwas Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Balasaheb Deoras Sahaniwas Phase 2 in Gandhisagar, Nagpur is P50500011868.

Is Balasaheb Deoras Sahaniwas Phase 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2 is registered as P50500011868 and its status is "Lapsed (registration period ended)".

What is the current construction status of Balasaheb Deoras Sahaniwas Phase 2? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Balasaheb Deoras Sahaniwas Phase 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Balasaheb Deoras Sahaniwas Phase 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2 is registered on MahaRERA as P50500011868, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Balasaheb Deoras Sahaniwas Phase 2?

Balasaheb Deoras Sahaniwas Phase 2 isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Balasaheb Deoras Sahaniwas Phase 2?

For a flat in Balasaheb Deoras Sahaniwas Phase 2 (Nagpur), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Transport Surcharge + 1% LBT. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Balasaheb Deoras Sahaniwas Phase 2 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2 isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 March 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Balasaheb Deoras Sahaniwas Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 March 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Balasaheb Deoras Sahaniwas Phase 2 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Balasaheb Deoras Sahaniwas Phase 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Balasaheb Deoras Sahaniwas Phase 2's possession date changes?

The latest dates are on Balasaheb Deoras Sahaniwas Phase 2's MahaRERA page (P50500011868). GharKundli's Kundli Watch sends a free WhatsApp update on Balasaheb Deoras Sahaniwas Phase 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Balasaheb Deoras Sahaniwas Phase 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2 has 3 buildings filed: BUILDING NO 1 with 10 floors; B 2 with 9 floors; B 3 with 10 floors.

How big is the land of Balasaheb Deoras Sahaniwas Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2 stands on 1,695 sq m of land (about 0.4 acres), with 3,104 sq m of sanctioned built-up area.

What is the track record of Balasaheb Deoras Sahaniwas Phase 2's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Prakash Narayanrao Raole has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, 1 within the promised date and 4 needed more time (typically 13 months); 1 still being built, 1 past the promised date (typically 62 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Balasaheb Deoras Sahaniwas Phase 2?

Google Maps has reviews of Balasaheb Deoras Sahaniwas Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Balasaheb Deoras Sahaniwas Phase 2?

Balasaheb Deoras Sahaniwas Phase 2 by PRAKASH NARAYANRAO RAOLE is in Gandhisagar, Nagpur, pincode 440032, Maharashtra, and is registered on MahaRERA as P50500011868, per GharKundli's check of MahaRERA records. Its boundaries filed there include SIR BEZANJI MEHTA ROAD. Its land is filed as 178/4,5,6,7. GharKundli lists all 6 MahaRERA projects in Mahal (440032).

How many flats are in Balasaheb Deoras Sahaniwas Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2 has 245 homes in 3 towers registered on MahaRERA.

When was Balasaheb Deoras Sahaniwas Phase 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Balasaheb Deoras Sahaniwas Phase 2 was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Does Balasaheb Deoras Sahaniwas Phase 2 have any legal issues or court cases?

No court cases are listed for Balasaheb Deoras Sahaniwas Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Balasaheb Deoras Sahaniwas Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRAKASH NARAYANRAO RAOLE, which has 6 other projects registered on MahaRERA.