EMPRESS ROYAL EFGH
by VIGNAHARTA CORRUGATORS PVT LTD · Dombivali, NagpurAlso near Pipla, Mouza - Nagpur, Gokul Housing Society
Possession date of EMPRESS ROYAL EFGH: 30 January 2028, moved from 30 December 2025 (25 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500009773, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about EMPRESS ROYAL EFGH?
How the possession date of EMPRESS ROYAL EFGH has moved
30 December 2025
Completion date given when the project was registered
30 January 2028
Extended at the builder's request (MahaRERA application EA04072501952)
Reason the builder gave MahaRERA:
“"In this project, the flats have only been registered. However, since some internal work is still pending, the project has not been fully completed and the Occupancy Certificate (OC) has not yet been received. Therefore, an extension is req…” Read the full reason
“"In this project, the flats have only been registered. However, since some internal work is still pending, the project has not been fully completed and the Occupancy Certificate (OC) has not yet been received. Therefore, an extension is required to complete the remaining work and obtain the OC."”
Source: EMPRESS ROYAL EFGH’s extension records on MahaRERA (P50500009773), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on EMPRESS ROYAL EFGH
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500009773
- Status
- Registered and active
- Builder
- VIGNAHARTA CORRUGATORS PVT LTD
- Location
- Dombivali, Nagpur · 440018
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2025
- Latest completion date
- January 2028
- Delay so far
- 25 months
- Homes
- 160
- Sold or booked
- 100%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of EMPRESS ROYAL EFGH, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| EMPRESS ROYAL E | 100% | 100% | 100% | 95% |
| EMPRESS ROYAL F | 100% | 100% | 100% | 95% |
| EMPRESS ROYAL G | 100% | 100% | 100% | 95% |
| EMPRESS ROYAL H | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- EMPRESS ROYAL E: covers G2+10FLORS
- EMPRESS ROYAL F: covers G2+10FLORS
- EMPRESS ROYAL G: covers G2+10FLORS
- EMPRESS ROYAL H: covers G2+10FLORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on EMPRESS ROYAL EFGH every month.
EMPRESS ROYAL EFGH: buildings, flats and land, as filed on MahaRERA
- Buildings: EMPRESS ROYAL E (12 floors, 40 units) · EMPRESS ROYAL F (12 floors, 40 units) · EMPRESS ROYAL G (12 floors, 40 units) · EMPRESS ROYAL H (12 floors, 40 units)
- Land: 7,178 sq m (about 1.8 acres) · sanctioned built-up 16,461 sq m
- Boundaries filed include: GANDHI SAGAR LAKE
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of EMPRESS ROYAL EFGH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
EMPRESS ROYAL EFGH: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about EMPRESS ROYAL EFGH
What is the possession date of EMPRESS ROYAL EFGH?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for EMPRESS ROYAL EFGH in Dombivali, Nagpur is 30 January 2028 — 25 months later than 30 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for EMPRESS ROYAL EFGH?
Builders and listing sites often quote an earlier "target" date for handover. The completion date EMPRESS ROYAL EFGH's builder has filed on MahaRERA, the official one, is 30 January 2028, already 25 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of EMPRESS ROYAL EFGH extended?
According to GharKundli's check of MahaRERA records (updated October 2026), EMPRESS ROYAL EFGH's builder applied to MahaRERA to extend the completion date once: to 30 January 2028, giving the reason ""In this project, the flats have only been registered. However, since some internal work is still pending, the project has not been fully completed and the Occupancy Certificate (OC) has not yet been received. Therefore, an extension is required to complete the remaining work and obtain the OC."".
What is the RERA number of EMPRESS ROYAL EFGH?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of EMPRESS ROYAL EFGH in Dombivali, Nagpur is P50500009773.
Is EMPRESS ROYAL EFGH registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EMPRESS ROYAL EFGH is registered as P50500009773 and its status is "Registered and active".
What is the construction status of EMPRESS ROYAL EFGH?
According to GharKundli's check of MahaRERA records (updated October 2026), EMPRESS ROYAL EFGH's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does EMPRESS ROYAL EFGH have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is EMPRESS ROYAL EFGH safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), EMPRESS ROYAL EFGH is registered on MahaRERA as P50500009773, its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if EMPRESS ROYAL EFGH's possession date changes?
The latest dates are on EMPRESS ROYAL EFGH's MahaRERA page (P50500009773). GharKundli's Kundli Watch sends a free WhatsApp update on EMPRESS ROYAL EFGH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does EMPRESS ROYAL EFGH have?
According to GharKundli's check of MahaRERA records (updated October 2026), EMPRESS ROYAL EFGH has 4 buildings filed: EMPRESS ROYAL E with 12 floors and 40 units; EMPRESS ROYAL F with 12 floors and 40 units; EMPRESS ROYAL G with 12 floors and 40 units; EMPRESS ROYAL H with 12 floors and 40 units.
How big is the land of EMPRESS ROYAL EFGH?
According to GharKundli's check of MahaRERA records (updated October 2026), EMPRESS ROYAL EFGH stands on 7,178 sq m of land (about 1.8 acres), with 16,461 sq m of sanctioned built-up area.
Where can I read reviews of EMPRESS ROYAL EFGH?
Google Maps has reviews of EMPRESS ROYAL EFGH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is EMPRESS ROYAL EFGH?
EMPRESS ROYAL EFGH by VIGNAHARTA CORRUGATORS PVT LTD is in Dombivali, Nagpur (pincode 440018), near Pipla, Mouza - Nagpur, Gokul Housing Society, Maharashtra, and is registered on MahaRERA as P50500009773, per GharKundli's check of MahaRERA records. Its boundaries filed there include GANDHI SAGAR LAKE.
How many homes are in EMPRESS ROYAL EFGH?
According to GharKundli's check of MahaRERA records (updated October 2026), EMPRESS ROYAL EFGH has 160 homes in 4 towers registered on MahaRERA, and 100% of them are sold or booked.
When was EMPRESS ROYAL EFGH registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EMPRESS ROYAL EFGH was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on EMPRESS ROYAL EFGH?
No court cases are listed for EMPRESS ROYAL EFGH on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of EMPRESS ROYAL EFGH?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIGNAHARTA CORRUGATORS PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of EMPRESS ROYAL EFGH
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Nagpur →
Other projects in Dombivali
- Sai Siddhi Residency
- EMPRESS DREAMS
- KUBER HEIGHTS
- Naivedya
- REGENCY SAPPHIRE
- SAMRUDDHI CHS LTD
- VINAYAK EXOTICA 9
- DYNAMIC CREST PHASE I - RIMO/EVEREST
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.